TOWN OF WATERFORD
SHORELAND ZONE
PERMIT
Date:
Status:
Adopted March, 2003
SHORELAND ZONE PERMIT PROCEDURE
- Acquire permit application from the Town Office or at waterfordme.org.
If the structure or explanation requires installation of a wastewater disposal system or expansion of an existing system, a soils analysis and wastewater disposal system design must accompany this application. - If item B is required, Question 31, Section A, B and C, must be completed and signed by the Code Enforcement Officer and Plumbing Inspector PRIOR to the Planning Board review.
Any additional permits, approvals, and/or reviews required on Page 6 must be acquired or completed PRIOR to final review by the Planning Board. - Copy of Deed to accompany application.
- Photographs of the lot to be developed and/or the structure to be renovated are required with the application (front, rear, and side views).
- Any questions regarding the permit application will be answered at any regularly scheduled Planning Board meeting or may be answered by contacting a Planning Board member for assistance.
All applications shall be submitted with three copies.
SHORELAND ZONE PERMIT FEE SCHEDULE*
STRUCTURES ACCESSORY TO PERMITTED PRINCIPAL STRUCTURES$
PERMITTED PRINCIPAL STRUCTURES$
PERMITTED COMMERCIAL STRUCTURES$
NON-CONFORMING STRUCTURES OR USES$
*Applicant is responsible for any additional review costs incurred by the town.
An application for a permit shall be accompanied by a non-refundable fee of $25 plus $1 per $1,000 of the estimated cost including materials and labor over $2,000. This application fee shall be made by cash or check, payable to the Town of Waterford.
Town of Waterford
Shoreland Zoning Permit Application
GENERAL INFORMATION
1. APPLICANT / 2. APPLICANT'S ADDRESS / 3.APPLICANT'S TEL.#4. PROPERTY OWNER / 5. OWNER'S ADDRESS / 6. OWNER'S TEL.#
7. CONTRACTOR / 8. CONTRACTOR'S ADDRESS / 9. CONTRACTOR'S TEL. #
10. LOCATION/ADDRESSOFPROPERTY / 11. TAX MAP & LOT # / 12. ZONING DISTRICT
13. Descriptionof property including a description of all proposedconstruction, e.g. land clearing, road building, parking areas, septic systems,wells (please note that a site plan sketch is required on page 5).
14. PROPOSED USE OF PROJECT / 15. ESTIMATED COST OF CONSTRUCTION
Page 1
SHORELAND AND PROPERTY INFORMATION
16. LOT AREA / 17. FRONTAGE ON ROAD (FT.)18. SQ. Fr. OF LOT TO BE COVERED BY NON-
VEGETATED SURFACES / 19. ELEVATION ABOVE 100 YR. FLOOD (FT.)
20. FRONTAGE ON WATER BODY (FT.) / 21. HEIGHT OF PROPOSED STRUCTURE
22. EXISTING USE OF PROPERTY NON-
VEGETATED SURFACES / 23. PROPOSED USE OF PROPERTY
NOTE: Question 24 applies only to expansions of portions of existing structures
which are less than the required setback.
24. (A) TOTAL VOLUME OF PORTION OF STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK AS OF 1/1/89:
______CUBIC FT.
(B) VOLUME OF EXPANSIONS OF PORTION OFSTRUCTURE WHICH IS LESS THAN REQUIRED SETBACK FROM 1/1/89 TO PRESENT: ______CUBIC FT.
C) VOLUME OF PROPOSED EXPANSION OF PORTION OF STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK:
______CUBIC FT.
D) % INCREASE OF VOLUME OF ACTUAL AND PROPOSED EXPANSIONS OF PORTION OF STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK SINCE 1/1/89
(% INCREASE = B + C/A x 100): ______%
25. IS THIS PROPERTY LOCATED IN A SUBDIVISION?
( ) YES ( ) NO
IF YES, WHAT IS THE NAME? ______
26. HOW IS THIS PROPERTY CURRENTLY ZONED?
( ) SP (Stream Protection)
( ) RP (Resource Protection)
( ) VS (Village Shoreland)
( ) RS (Rural Shoreland)
27.( A) SQ. FT. OF PORTION OF EXISTING STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK AS OF 1/1/92 (100') ______/
(B) SQ. FT. OF PROPOSED EXPANSION OF PORTION OF STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK (FORMULA TO FIGURE % EXPANSION
B/A x 100 + % EXPANSION): ______
C.) HAS THE STRUCTURE EVER BEEN EXPANDED?
( ) YES ( ) NO IF YES, WHY? ______
BY WHAT PERCENTAGE? ______
28. SOIL EROSION, SEDIMENTATION AND PHOSPHOROUS CONTROL PLAN.
DESCRIBE AND ILLUSTRATE ON ATTACHED SHEETS HOW THE DESIGN OF THE SITE INCLUDING DRIVEWAYS, PARKING AREAS, DRAINAGE SYSTEMS, CULVERTS AND RELATED FEATURES WILL MINIMIZE AND CONTROL OFF-SITE RUN-OFF, DRAINAGE, SEDIMENTATION AND PHOSPHOROUS EXPORTING IN COMPLIANCE WITH LOCAL ORDINANCES, STATE LAWS AND REGULATIONS (attach site plan diagram).
29. ROADS AND DRIVEWAYS STANDARDS.
DESCRIBE HOW ROADS AND/OR DRIVEWAYS AND DRAINAGE SYSTEMS, CULVERTS AND OTHER RELATED FEATURES WILL MEETLOCAL ORDINANCES CONSTRUCTION STANDARDS (attach diagrams drawn to scale).
30. SIGNAGE
WILL SIGN(S) BE LOCATED ON THE PROPERTY?
( ) YES ( ) NO
IF YES, DO THEY COMPLY WITH LOCAL ORDINANCE REQUIREMENTS? ( ) YES ( ) NO
Page 2
31. APPLICATION
A) APPLICATION FOR BUILDING PERMIT (MANDATORY ITEM)
1. Please attach site plan showing:
- Existing and Proposed Structure
- Sewage Disposal Facilities
- Lot Dimensions and Adjoining Owners
- Proximity to all Water Sources
2. Type of Construction: Single FamilyMulti-FamilyNo. RoomsFrameMobile
ModularMotelGarageOther______
3. Dimensions of Proposed Structure: Length______Width______Height______
4. Flood Plain Area Only: Elevation of 1st floor is below ground level______
Elevation of 2nd floor above ground of 1st floor is below ground level______
5. Type of sewage: Private System______
6. Is proposed system located in a Special Flood Hazard Area?______
7. If private sewage system is to be installed, altered, or replaced, fill in Section C.
8. Provisions:
B) APPLICATION FOR PLUMBING PERMIT
1. Type of Building: Commercial______School____Residential_____Single-Family______
Multi-Family_____New______Remodeling______
2 Number of: Sinks______Toilets______Lavatories_____Bathtubs______Showers______
Hot Water Tanks______Dishwashers______Cloth Washers______Mobil or Modular Home
- Water Source : Private______Public______Well_____Spring_____Other
- Licensed Master Plumber in Charge:______
C) APPLICATION FOR PRIVATE SEWAGE DISPOSAL SYSTEM 1. 1. Attach soils from certified soils scientist or equivalent.
2. Type of System: Septic Tank______Aerobic______Holding Tank______
SizeMfg.Size
3. New______Replacement______
4. Drainfield: Bed______Trenches______Other______
5. Type of Drainfield: Bed______Trenches______Other______
SizeSizeSize
6. No. Bedrooms______
7. Location of Structure of Property Lines; Location of Water Source and Sewage System; Location of nearest well, spring, lake or water source to sewage system
SIGNATURE OF APPLICANT______DATE______
CODE ENFORCEMENT OFFICER______DATE______
PLUMBING INSPECTOR______DATE______
SITE PLAN
Enclosed with this applicationis a sheet of graphpaper for you to usein sketchinga diagram of the site/lot to be developed. It is important that you draw the site plan diagram as accurately as possible to show to scale the distances between all features youhave drawn in the sketch. You must include the following on your sketch.
- Lot Lines
- Area to be cleared of trees and vegetation
- Accurate setbacks from shoreline and side and rear property lines
- Exact position of proposed structures including decks, porches, out-buildings, etc.
- Location of existing or proposedwells
- Location of existing or proposed septic systems
- Location of driveways and parking areas
- Location of driveway entrance on a public road
- Areas and amounts to be filled or graded
- If the proposal is for an expansion, show the existing structure
andthe proposed expansion (distinguish between the expansion
and the existing structure) - Indicate North on the diagram
SITE PLAN DIAGRAM 1
ADDITIONAL PERMITS, APPROVALS AND/OR REVIEWS REQUIRED
(FOR OFFICE USE ONLY)
CHECK IF REQUIRED
______PLANNING BOARD REVIEW/APPROVAL (e.g. Subdivision, Site Plan Review)
______BOARD OF APPEALS RE VIEW/APPROVAL
______FLOOD HAZARD DEVELOPMENT PERMIT
______EXTERIOR PLUMBING PERMIT (Approved IIIIE 200 Application Form)
______INTERIOR PLUMBING PERMIT
______DEP PERMIT (Site location, Natural Resources Protection Act or Permit-by-Rule)
______ARMY CORPS. ENGINEERS PERMIT
______ARCHAEOLOGICAL SITES (Maine Historic Preservation Commission)
______SEASONAL CONVERSION
______OTHER______
Note: Applicant is advised to consult with the Code Enforcement Officer and appropriate state and federal agencies to determine whether additional approvals and reviews are required.
I certify that all information in this application is accurate. All proposed uses shall be in conformance with this application and the town of Waterford Shoreland Zoning Ordinance. I agree to future inspections by the Code Enforcement Officer at reasonable hours.
APPLICANT'S SIGNATUREDATE
AGENT'S SIGNATURE (If Applicable)DATE
APPROVAL OR DENIAL OF APPLICATION
(FOR OFFICE USE ONLY)
MAP#______LOT# ______
THIS APPLICATION IS: ______APPROVED ______DENIED
IF DENIED, REASON FOR DENIAL:
IF APPROVED, THE FOLLOWING CONDITIONS ARE PRESCRIBED:
Note: In approving a shoreland zoning permit, the proposed use shallcomply with the purposes and requirements of the Shoreland Zoning Ordinance for the Town of Waterford.
PLANNING BOARD SIGNATURES
CEO SIGNATURE DATE
INSPECTION CHECK LIST
( ) Prior to clearing and excavation ( ) Prior to Final Landscaping
( ) Prior to Foundation Pour ( ) Prior to Occupancy
PERMIT# ______FEE AMOUNT ______
Appendix 1
SHORELAND ZONING PERMIT CHECKLIST
(FOR OFFICE USE ONLY)
CHECK OFF FOR ALL STRUCTURES:
COMPLETE SHORELAND ZONING PERMIT APPLICATION
PAY APPROPRIATE FEE
LOT AREA
% OF LOT COVERED BY NON-VEGETATED SURFACES
HEIGHT OF STRUCTURE
SETBACK FROM HIGH WATER MARK SETBACK FROM SIDE AND REAR LOT LINES
% INCREASE OF EXPANSIONS OF PORTION OF STRUCTURE WHICH IS LESS THAN REQUIRED SETBACK
COPY OF INTERIOR AND EXTERIOR PLUMBING PERMITS
COPY OF DEED
SITE PLAN FILED WITH REGISTRY OF DEEDS (IF SEASONAL CONVERSION)
PHOTOGRAPHS OF SITE/STRUCTURE
ELEVATION OF LOWEST FLOOR TO 100 YEAR FLOOD ELEVATION COPY OF ADDITIONAL PERMIT(S) AS REQUIRED
(See Page 8 of Application Form)
CHECK OFF FOR FURTHER REVIEW:
______COPY OF FILE TO BOARD OF APPEALS IF VARIANCE OR SPECIAL
EXCEPTION IS REQUIRED
______COPY OF FILE TO PLANNING BOARD IF PLANNING BOARD REVIEW IS
REQUIRED
CHECK OFF FOR SITE VISITS BY CEO:
SPECIAL PERMIT
PROPERTY OWNER / SHORELAND DISTRICT
ADDRESS OF PROPERTY
NOTE: Where shoreland zoning ordinance requires a variance, a conditional use or special exemption by the Board of Appeals or the Planning Board, this special permit shall be completed by the appropriate board and the attached to the shoreland permit application.
FINDING OF FACTS AND CONDITIONS OF APPROVAL
BOARD OF APPEALS______
PLANNING BOARD______
NOTE: The findings of fact and the conditions of approval should include the reasons why the special permit was granted and specific conditions which clearly define the scope of the use. In reviewing a request for a variance, boards of appeal shall apply the "undue hardship" criteria in the shoreland zoning ordinance. In reviewinga request for a conditional use or a special exception, planning boards shall apply the standards of review provided in the local ordinance.
APPROVED BY:______DATE ______
NOTICE TO APPLICANT:
I HAVE READ AND ACCEPT THE CONDITIONS OF THIS SPECIAL PERMIT
APPLICANT______DATE ______
APPLICANTDATE ______