90% PS&E Checklist
______
CORRIDOR: CONTRACT:
CONSULTANT: LETTING DATE:
NTTA Use Only
DATE: REVIEWED BY:
Comments: ______
PMO/GEC Use Only Grade A B C D F
Accept Reject Date: By:
Comments:
______
DATE: REVIEWED BY:
Verify all design is in compliance with the NTTA Design Guidelines
Check all elements that apply to the project. If not applicable, explain why.
Color & Finishes Lighting Sign Structures Signage Walls Bridge Structures
Mainlane Elements Toll Gantry Structures Landscape/Irrigation Public Art
Comments:
NOTE: If any of the above boxes are not checked, an explanation must be provided as why Guidelines cannot be met.
Verify all design is in compliance with the following NTTA manuals and/or guidelines:
Roadway Electrical System Maintenance Design PS&E Procedures Manual
Crash Attenuator Sign & Traffic Control Devices
Comments:
NOTE: If any of the above boxes are not checked, an explanation must be provided as why Guidelines cannot be met.
______
Design coordinated with adjacent project.
Verify all design in compliance with the established design criteria for this project.
Submittal being tracked in EPDS.
Comments:
Previous Plan Submittal
Revised Plans Comments Incorporated from previous review
Comments:
Consistent with NTTA CAD Guidelines
Title Sheet Updates
Project Description Contract No. Section No. Project Limits
Project Length Bridge Length Begin/End Sta. Design Speed & ADT
Location Map TDLR Inspection Signature Block
Exceptions, Equations and Railroad Crossings Adoption Date of Governing Specifications
Comments:
Index Sheet(s) Updates
Volumes Listed TxDOT Standards NTTA Standard Drawings Municipal Standards
Comments:
Project Layout Updates
Major Intersections Labeled Legible Project Stationing
Comments:
Typical Sections Updates (Include labels, legends and dimensions where appropriate)
------Existing------
ROW Shoulders Border Width Lane Width
Barrier Type of Curb Median
------Existing Pavement Structure------
LTS HMAC Base CRCP JRCP
Comments:
------Proposed------
Existing/Propposed ROW Shoulders Cross Slopes Lane Width
Type of Curb Side Slopes Station Limits Lane Direction
Border Width Walls Flumes Mow Strips
Ditch Sections Median
------Proposed Pavement Structure------
LTS Embankment Type___ HMAC Type___ CRCP JRCP Prime Coat
Comments:
General Notes Updates
Included Specification Data Special Specification (Project Specific)
Comments:
Summary Sheet Updates
Estimate & Quantity Summary TCP Removal Earthwork
Roadway Drainage Retaining Walls Bridge
Pavement Marking/Delineation ITS SW3P Miscellaneous
Other
Comments:
Traffic Control Plan Updates
Sequence of Work Narrative Advance Warning Signs Construction Sequence Typicals
Temporary Pavement Temporary Shoring Detour/ Alignment
Phasing Layout Work Zone Pavement Marking Work Zone Signing
Channelization Devices Temporary Traffic Signals/Illumination
Standards
Comments:
Removal Plan Updates
Existing Roadway Topography (pavement, curb, driveways, etc.) Known existing utilities (OH or UG)
Removal items identified Legend
Comments:
Geometric Layout Updates
Control Point Coordinates Baseline and/or Centerline Graphic Scale
North Arrow Overall view of project with primary control monumentation
Roadway Names Chain Names Lane Assignments
Comments:
Horizontal Control Alignment Data Updates
Curve Data PC, PI, PT Stations & Coordinates Radius and DOC
Deflection Angle Tangent Length and bearings Stations and Station Equations
Station/offset information (relative to other alignments)
Comments:
Superelevation Data Sheet Updates
Begin/End Superelevation Superelevation Rates
Comments:
Plan/Profile Sheet(s) Updates
------Plan View Update------
Existing/Proposed ROW Existing/Proposed Utilities Existing/Proposed Cross Drainage
Lane Assignments Stationing/Bearings Bench Mark
Control Points Labeled North Arrow Horizontal Scale
Type of Curb Riprap Mow Strips
Retaining Walls Crash Attenuators MBGF/Barrier/Rail
SGT/TAS Construction Easements Horizontal Curve Data
Existing Roadway Topography (Background) Proposed Roadway (Foreground)
Comments:
------Profile Update View------
Existing Ground Profile Proposed Grade Line Cross Drainage Structures
Station/Elevation Grades Vertical Curve Data
Comments:
Paving & Bridge Deck Contours - Updates
Intersection(s) Bridge(s)
Comments:
Miscellaneous Roadway Details (ADA Items, Transition for Curb Ends, etc.) Updates
Included In progress
Comments:
Retaining Wall Detail(s) Updates
Plan & Profile Begin/End Stations Typical Sections
Comments:
Drainage Updates
Drainage Area Map Discharge Relationship Storm Drain Layouts
Drainage Calculations Storm Drain Profiles Storm Drain Master Plan
Comments:
Culvert Layout(s) Updates
Existing Plan/Profile Proposed Plan/Profile Design Data (Size, Length, Type)
Draft Hydraulic Report(s) (Bridge Class only)
Comments:
Utility Plan Updates
Existing Utilities Layout Proposed Utilities Layout Conflict Resolution
Comments:
Bridge Layout(s) Updates
Plan and Elevation Begin/End Stationing Spans Rail
Riprap Limits Typical Sections Test Hole Data
Comments:
Bridge Detail(s) Updates
Abutment Details Bent Details Slab Details Beam Unit Details
Quantity Tables Compliance with Aesthetic Criteria
Comments:
Railroad Exhibit Updates (when required)
TxDOT Checklist Railroad Checklist (UPRR, BNSF, DART, etc.)
Comments:
Signing Layout(s) Updates
Sign Layout Guide Sign Details OH Sign Structure Elevations
Preliminary Sign Support Details
Comments:
Illumination & Signal Layout(s) Updates
Illumination Layout(s) Signal Layout(s) Signal Phase Diagram Temporary Signal
Comments:
Pavement Marking & Delineation Layout(s) Updates
Pavement Marking Plan Design details
Comments:
ITS Layout Updates
DMS Locations CCTV Camera Locations ITS Legend Power Source
AVI Speed Map Antennae Traffic Sensors Pavement Sensors
Fiber Conduit Layout Ground Box Locations (1000’ min. spacing)
Comments:
Landscape and Irrigation Updates
------Landscape------
Plant Layout Planting Details Legend
------Irrigation------
Irrigation Layout Hydraulic Data Control System
Fiber Connection Power Source
Comments:
Storm Water Pollution Prevention Plan – SW3P - Updates
EPIC SW3P site plan for construction phases SW3P Data Sheet
Comments:
Earthwork Cross Sections – Preliminary
50’ Intervals Pavement Limits Retaining Walls ROW
Side Slopes Vertical & Horizontal Control Barrier/Rail
Comments:
Estimate Updates
Cost
Comments:
Proposal – Updates
Proposal Book Included for Review
Comments:
FD-01-F3 Rev-1 Page 1 of 6 Release Date: 06/24/2009