Dbe Participation Report

Dbe Participation Report

C2-98

DBE PARTICIPATION REPORT

PROJECT NO.(S) / COUNTY / REPORT NO.
CONTRACTOR / DATE / CONTRACT AMOUNT
CONTRACT ID NO / - - - / DBE REQUIRED / % / DBE AMOUNT

Month Ending (CHECK ONE) ______(month) FINAL

APPROVED DBE / VENDOR NUMBER / DESCRIPTION OF WORK / SUPPLIER / OWNER/ OPER. / SUB- CONTR / ORIG. SUBCONTRACT AMOUNT / EARNINGS
TO-DATE

TOTAL DBE EARNINGS TO DATE

/ $
% CONTRACT / %

I HEREBY CERTIFIY THAT THE ABOVE STATEMENT

IS TRUE AND CORRECT AND SUPPORTING DOCUMENTATION

IS ON FILE AND IS AVAILABLE FOR INSPECTION BY

DEPARTMENT PERSONNEL AT ANY TIME.

SIGNED

CONTRACTOR

REMARKS

PAGE OF

DEPARMENT OF TRANSPORTATION

STATE OF GEORGIA

INSTRUCTIONS TO CONTRACTOR

In order to receive credit toward the contractor DBE Goal, the prime contractor must complete the reverse side and submit this form quarterly to the engineer in charge of the contract. Failure to submit this form will result in no credit toward the contract DBE requirements.

1.Report Number: Reports must be consecutively numbered. It will only be necessary to submit a report in a quarter when the approved DBE has performed a portion of the work that has been designated for the contract.

2.Date:Actual date of the quarterly period ending.

3.Earnings To-Date: Show the actual amount that each DBE has earned to-date under the contract based on the unit prices paid to the DBE by the prime contractor and not contract unit prices. When a supplier is used to fulfill the DBE requirements, only 60% of the amount earned by the supplier may be entered. Show the total amount in the space provided.

4.Percent of Contract: This percentage is calculated using the contract amount and the total DBE earnings-to-date.

5.Certification: The contractor or his authorized representative must sign this form prior to submittal. Failure to complete and submit this form in a timely manner may delay monthly progress payments.

GENERAL INFORMATION

When the approved DBE is to provide materials, goods or services, this completed form must be submitted to the Area Engineer.

The prime contractor may change DBE firms only with the approval of the District Engineer, provided the contract DBE Goal is met and the changes conform to contract regulations. This form should be updated and submitted to the Area Engineer.

Upon completion of the work, a final “DBE Participation Report” will be required and submitted to the Area Engineer prior to final payment. All information shown on the form must be completed, including the final earnings of each approved DBE.

When the prime contractor is an approved DBE, it will only be necessary to complete the total DBE earnings to-date.

Joint ventures between non-DBE and certified DBE: Only that portion of the work for which the DBE is responsible may be used to satisfy the requirement.