Chapter 2 Development of Appraisal Data

Chapter 2 Development of Appraisal Data

MH Supplement:2409.22-2010-1
EFFECTIVE DATE: October 18, 2010
DURATION: Effective until superseded or removed / e(5)
Page 1 of 5
FSH 2409.22 - timber appraisal
CHAPTER 2 – DEVELOPMENT OF APPRAISAL DATA
/ Forest Service Handbook
sandy, oregon

fsH 2409.22 – TIMBER APPRAISAL

Chapter 2 – Development of Appraisal Data

Mt. Hood Supplement No.: 2409.22-2010-1

Effective Date: October 18, 2010

Duration: Effective until superseded or removed

Approved: /s/ Kathryn J. Silverman for
GARY L. LARSEN
Forest Supervisor / Date Approved:October 14, 2010

Posting Instructions: Supplements are numbered consecutively by Handbook number and calendar year. Post by document name. Remove entire document and replace with this supplement. Retain this transmittal as the first page of this document.

New Document(s): / Chapter 2
e. (5) / 5 Pages
Superseded Document(s): / Chapter 2
e. (5)
(MH Supp. No. 2001-1 May 2001) / 5 Pages

Digest:

e. (5) / Updates Road Maintenance rates for timber sale appraisal. Based on Rd Maintenance Commensurate Share spreadsheet program developed in 2004 and updated in Sept 2010. Adds a mandatory list of road segments that make up the Forest coop pool.

e. Adjustment for Sale Characteristics.

(5)Sale Operational Costs

ROAD MAINTENANCE.

Road Maintenance Cost Guide

1. Table I:

Mandatory deposit and user maintained rates for timber haul includes:

A. Recurrent traffic and non-traffic generated maintenance, i.e. blading,

spot subgrade repair, spot surface replacement, brushing, logging out,

culvert–ditch maintenance, slough-slide removal, etc.

B. Operational maintenance, i.e. pavement markings, signs, traffic controls,

etc.

In addition to the above, mandatory deposit for timber haul includes:

D. Chip seals, surface treatments, bridges, etc.

E. Overhead - 29%.

MAINTENANCE COST PER CCF MILE

MAINTENANCE LEVEL / SURFACE TYPE / RECREATION SHARE
LOW / MEDIUM / HIGH
2 / NAT & AGG / 0.27 / / / / / / / / / / / /
2 / AC & ST / 0.41 / / / / / / / / / / / /
3 / AGG wo/SRR / 1.59 / 1.24 / / / / / /
3 / AGG w/SRR / 2.39 / 1.88 / / / / / /
3 / AC & ST / 0.76 / 0.66 / / / / / /
4 & 5 / AC & ST / 1.04 / 0.91 / 0.85
Rd 46 / AC / / / / / / 0.91 / / / / /

Table II: Mandatory COOP Road Segments

Road # / Segment / SADT / Rec. Class
13 / Lost Lake to County Segment / 260 / High
18 / M.P. 17 – End of County / 250 / Medium
42 / Jct SH 26 – Jct 57 / 420 / High
42 / Jct 46 – Jct 57 / Medium
43 / All Segments / 100 / Medium
44 / All Segments / 110-175 / Medium
46 / All Segments / 420 / High
48 / All Segments / 300+ / High
57 / Jct 46 – Jct 5810 / 110-220 / Medium
57 / Jct 5820 – Jct 42 / High
63 / Jct 46 – Jct 70 / 210 / Medium
All other roads are Low Rec

2. Table III: Rock haul. Same elements included for timber haul are included in the following

table.

MAINTENANCE COST PER C.Y. MILE

MAINTENANCE LEVEL / SURFACE TYPE / RECREATION SHARE
LOW / MEDIUM / HIGH
2 / NAT & AGG / 0.24 / / / / / / / / / / / /
2 / AC & ST / 0.35 / / / / / / / / / / / /
3 / NAT & AGG / 1.36 / 1.06 / / / / / /
3 / AC & ST / 0.66 / 0.59 / / / / / /
4 / AC & ST / 1.04 / 0.91 / 0.85

3. Table IV: Rock haul and any other type of haul that can be measured by the

ton. Same elements included for timber haul are included in the

following table.

MAINTENANCE COST PER TON MILE

MAINTENANCE LEVEL / SURFACE TYPE / RECREATION SHARE
LOW / MEDIUM / HIGH
2 / NAT & AGG / 0.17 / / / / / / / / / / / /
2 / AC & ST / 0.26 / / / / / / / / / / / /
3 / NAT & AGG / 1.03 / 0.88 / / / / / /
3 / AC & ST / 0.54 / 0.46 / / / / / /
4 / AC & ST / 0.63 / 0.55 / 0.52

4. Table V: Water haul. Same elements included for timber haul are included in the

following table.

MAINTENANCE COST PER M GAL MILE

MAINTENANCE LEVEL / SURFACE TYPE / RECREATION SHARE
LOW / MEDIUM / HIGH
2 / NAT & AGG / 0.71 / / / / / / / / / / / /
2 / AC & ST / 1.04 / / / / / / / / / / / /
3 / NAT & AGG / 5.28 / 3.52 / / / / / /
3 / AC & ST / 2.16 / 1.84 / / / / / /
4 / AC & ST / 2.52 / 2.20 / 2.08

5. All Maintenance Level 2,3, 4, 5, with Asphalt Cement or Bituminous Surface Treatment

are mandatory deposit. See Mandatory Coop Table II.

6. All Native and Aggregate Maintenance Level 2 or 3 may be accomplished by the

user or by cooperative deposits.

7. Dust abatement allowance - $3500.00 per lane-mile

INSTRUCTIONS

1. District Timber Departments are responsible for furnishing the following information to

Engineering Departments:

a. Sale area map

b. Timber Volume

c. Average Volume per log Truck

d. Costs per Round Trip Minute (RTM)

2. Engineering Departments are responsible for furnishing the following information

to the District Timber Departments:

a. Road maintenance appraisal

b. All appropriate “C” provisions

3. Recurrent Maintenance – Includes those activities which are anticipated to be needed

on a continuing basis on all roads under Forest Service jurisdiction. Recurrent maintenance

may be accomplished by the user or by cooperative deposits.

4. Subtract 29% from unit costs in Tables I, III, IV and V for Purchaser performed maintenance.

5. Road maintenance rates listed are based on average road maintenance requirements, the

Engineer has the latitude to adjust the rates if the situation warrants, such variation must be

justified and documented in the appraisal.