Road Management Plan Report, June 2013

Road Management Plan Report, June 2013

ROAD MANAGEMENT PLAN REPORT

JUNE 2013

Table of contents

1.Introduction

2.Public Notices

3.RMP Review

4.RMP Review Recommendation

Attachment 1

1.2011 Road Management Plan Audit Recommendations:

2.2012 Road Management Plan Audit Recommendations:

3.Risk Management / Insurance Branch Comments

4.Road Management (Feb 2010 version) Review

Road Management Plan Report June 2013 – DM#8401424 1

  1. Introduction

A review of the City Of Melbourne’s Road Management Plan (Feb 2010 version) was undertaken by the Engineering Services Branch in June 2013, pursuant to section 54 (5) of the Road Management Act 2004 and section 301 of the Road Management (General) Regulations 2005.

The RMP review included the following actions:

  • Placement of public notices in The Age and Melbourne Leader newspapers and Victorian Government Gazette;
  • Establishment of a RMP review committee comprising Michael Norton (Principal Engineer Infrastructure - Chairperson), Craig Stevens (Principal Engineer Services), Bandara Rajapakse (Team leader Infrastructure Design) and Lionel Galappatthi (Team Leader Assets and Maintenance Works);
  • Analysis of the RMP audit report recommendations conducted in 2011 and 2012 by independent auditor Frank Sultana; and
  • Seeking advice from the Council’s Risk Management / Insurance Branch and the Council’s public liability insurer Civic Mutual Plus.
  1. Public Notices

Public notices were placed in The Age and Melbourne Leader newspapers and the Victorian Government Gazette in May 2013 allowing for the 28 day period for the receipt of any public submissions. No public submissions were received.

  1. RMP Review

The review committee met on two occasions dated 13 and 25 June 2013. The review comprised the following elements:

  • Assessment of the 2011 and 2012 RMP audit report recommendations for relevance to impact on the Council’s current RMP version;
  • Assessment of advice received from Council’s Risk management / Insurance Branch and Civic Mutual Plus (Council’s public liability insurer) on suggested improvements / enhancements to the Council’s current RMP;
  • Review of the Council’s current RMP intervention and response time standards and any administrative / document reference updates. The review committee adopteda practical approach to the achievement of response times to ensure that Council’s liability to a claim is further protected; and
  • The RMP review is detailed in Attachment 1 table
  1. RMP Review Recommendation

The RMP review committee recommends the following:

  • The Council’s current RMP (version Feb 2010) be amended as detailed in Attachment 1 table including minor updates to reference documents;
  • The process to amendthe Council’s RMP be pursuant to section 54 (6) of the Road Management Act 2004 and sections 303 and 304 of the Road Management (General) Regulations 2005;
  • The RMP (2013 version) be amended in November 2013; and
  • The amended RMP be approved by the Manager Engineering Services as Council delegate in accordance with Council’s resolution dated 24 November 2009

Road Management Plan Report June 2013 – DM#8401424 1

Attachment 1

  1. 2011 Road Management Plan Audit Recommendations:

Recommendation / RMP Review Committee Comment / Impact on RMP
1. CityWide (CW) needs to continue to improve its performance regarding the rectification of defects to ensure total compliance with the requirements of the RMP. / CIS routine maintenance response time are being achieved but recommended that response times for high risk business hours & out of hours maintenance items be extended to provide some additional buffer. / Yes Impact:
High risk response times in RMP Appendix 2 Table 2 be amended to four hours for both business hours and for out of hours.
2. Engineering Services (ES) must continue to improve its performance in the Minor Works Program and continue to monitor the adequacy of the level of funding / Recommendation is not relevant to RMP review / No impact
3. There should be consultation with VicRoads and service authorities regarding the rectification of referred defects so that an understanding is gained about the appropriate service levels; (Since the audit was undertaken, ES has initiated discussions with VicRoads on this issue) / Recommendation is relevant to 3rd party assets including VicRoads (coordinating road authority for arterial roads) and utility companies including water, gas, electricity and telecommunications and public transport companies. Recommended that current reporting practice is adopted in RMP with response times extended and record keeping of reported fault only kept on Council’s database system. / Yes impact.
Adopt response times for 3rd party assets as per item #1 above. Include notification to 3rd party agency and record reference number only in Council’s database system.
4. For some renewal works, more thought and consultation needs to take place with regard to the design levels and location of existing service authority assets / Recommendation is not relevant to RMP review / No impact
5. Unauthorised service reinstatements should be monitored with a view to reporting back to industry organisations on the extent this issue is having on the maintenance of assets and the management of risks / Recommendation is not relevant to RMP review / No impact
  1. 2012 Road Management Plan Audit Recommendations:

Recommendation / RMP Review Committee Comment / Impact on RMP
1. CW needs to continue to improve its performance regarding rectification of defects to ensure total compliance with the requirement of the RMP / See 2011 RMP audit review action #1 / Yes impact.
See above.
2. CW should record all repair details for a “make safe” situation / Recommendation is not relevant to RMP review - operational recommendation. / No impact
3. ES must finalise the development of suitable KPIs for the CIS contract to ensure that CW’s performance is monitored. It is suggested that in the rectification of defects within the set time limits, 100% should be achieved for high & medium risk defects and 80% for low risk defects / Recommendation is not relevant to RMP review - performance management recommendation. / No impact
4. There should be continued consultation by ES with service authorities regarding the standardisation of intervention levels and/or the development of agreements for Council’s service provider to rectify certain defects at the service authorities cost / Recommendation is not relevant to RMP review – 3rd party asset repairs outside scope of Civil Infrastructure Services (CIS) contract and RMP review. / No impact
5. ES and CW should finalise the actions in the CIS routine and minor maintenance lean review / Recommendation is not relevant to RMP review – continuous improvement recommendation. / No impact
6. Engineering Services should continue to coordinate efforts by all Council Branches to ensure all relevant road data is imputed into the Assetmaster and COMPASS GIS systems / Recommendation is not relevant to RMP review – related to management of asset data. / No impact
7. Road routine maintenance performance should be monitored and considered as part of the RMP review which is due in 2013-14FY. / CIS routine maintenance performance and contract KPIs agreed and are being achieved. No modification to CIS contract is recommended. Response times recommended to amended as per 2011 RMP audit review action #1. / Yes Impact.
See above.
  1. Risk Management / Insurance Branch Comments

Recommendation / RMP Review Committee Comment / Impact on RMP
  1. In regards to Council’s liability exposure if possible the benchmarks set in our Civil Infrastructure contract should be slightly higher than the Road Management Plan, but certainly not the other way round. If the benchmarks are exactly the same in both documents then the moment there is underperformance in the Civil Infrastructure contract it will mean we have breached our Road Management Plan and have legal exposure if the claimant can demonstrate this breach (in court or via Freedom of Information). From a legal perspective reactive intervention should be Council’s first risk priority.
/ Agree. A more conservative approach to response times and management of 3rd party defects has been identified through the RMP review process. See 2011 RMP audit review actions #1 and #3. / Yes impact
  1. Consider how the plan can cope with damage to infrastructure during extreme weather events, e.g., if flooding causes a large number of high risks across the municipality then can we repair or make safe if our resources are going to be stretched? There is a section on Force Majeure on page 20 but this seems to relate to formally declared natural disasters and events as opposed to more regular once a year type extreme weather events.
/ Emergency service response is already provided in the CIS contract. Municipal response to major emergencies ie severe storm / flooding events is coordinated through Council’s Emergency Management plan. Issues related to the repair of damaged infrastructure from extreme events would be coordinated Council’s recovery response. / No impact
  1. Page 33, Intervention Levels for Third party claims – consider a conservative approach for these. We’re continuing discussions with Lionel about claims involving third party assets, particularly Telstra pit covers. In 2011 we received a claim that alleged that “Council had knowledge ofthe defective footpath, conveyed its knowledge of the defective footpath to Telstra and failed to monitor Telstra's repair of the footpath.” The plaintiff's solicitors indicated that they will rely on, not only the existence of a 'sunken pit', but also the presence of a 'raised edge' of footpath adjacent to the 'sunken pit’. We successfully argued that we didn’t have liability in this matter and did not have to pay any compensation, however we had considerable costs just to investigate and defend.
/ Agree. See 2011 RMP audit review action #3 / Yes impact

3. Risk Management / Insurance Branch Comments (cont’d.)

  1. Recommend reviewing the non-road areas such as off-street car-parks that are listed in the register of public roads. Listing these aspects in the Road Management Plan makes them judged against the Road Management Plan standards. A comment from one of our lawyers who takes a more aggressive approach to defending liability claims is that “if you leave a road off you can never be liable for it under Section 107 of the Road Management Act”
/ Disagree. Off street car parks should be retained in Council’s RMP and on Council’s register of public roads. However, the non-road classification in eth register of public roads should be changed to ancillary area to be consistent with the Road Management Act 2004. / No impact
  1. The MAV audit also recommended that we document our maintenance programs and standards for our Shared Pathways and this is being followed up separately with Park Services so that they detail this in their documents rather than the Road Management Plan.
/ Agree. Management of Park pathways public liability risk should be managed separately to Council’s RMP. / No impact
  1. Page 23, response times for High Risks - 40minutes appears to be a little ambitious; in our benchmarking with other metro Councils we’ve found they have a 4 hour period for responding to high risks. In last year’s MAV Insurance Liability audit your branch scored maximum points for our reactive and proactive inspections from a sample of four roads and footpaths, however intervention levels were not fully met in the two previous audits.
/ Agree. See 2011 RMP audit review actions #1 and #3 / Yes impact
  1. We also undertook some comparison with the VicRoads Road Management Plan and their levels are also considerably more conservative than Council’s, with a 4 hour period for their highest category defects/risks.
/ Agree with conservative response times.
See 2011 RMP audit review actions #1 and #3 / Yes impact
  1. There also seems to be no definition for low, medium and high risks, perhaps you could use the definitions that you’ve used within the Civil Infrastructure contract.
/ Noted. High / medium / low risks are already defined in Council RMP (see section 6.3) / No impact
  1. Just a general comment on ‘repairing or make safe’ - Council’s actions regarding particular claims may be argued as not appropriate if it can be demonstrated by claimants that the actions were not reasonable (e.g., if someone was injured where a temporary witches hat was placed over a high risk area for several days as opposed to another better temporary solution such as hot mix asphalt.)
/ Noted. Repair / make safe requirements are detailed in the CIS contract spec. A common sense approach is required as the action will vary based on severity of damage, risk assessment, case by case and location. / No impact

3. Risk Management / Insurance Branch Comments (cont’d.)

  1. Alternative approaches – One of our lawyers with a slightly differing view to MAV Insurance has advised us that for more legal protection you could remove the prescriptive/mandatory time frames from the Road Management Plan and just keep this document very high level and flexible, whereas you would have a separate Road Management Policy that lists the specific standards. Apparently City of Dandenong do this but other Councils haven’t taken this approach.
/ Disagree. This would require a complete rewrite of Council’s RMP which offer no additional value to Council and is considered not necessary. Current RMP provides sufficient risk protection to Council. / No impact
  1. Further notes from the MAV Insurance guidelines:
Achievable versus Aspirational
  • It is crucial that if a RM Plan is to offer maximum assistance in defending claims it must be achievable and compliance must be capable of being demonstrated under the scrutiny of litigation. It serves no good purpose for a RM Plan to be aspirational in nature - so don’t set the bar higher than you can reasonably jump. The most common areas that tend to be unachievable are:
  • proactive inspection timelines
  • intervention levels – consider the legal precedent to determine whether they are really achievable or necessary given your resources and competing priorities. The Supreme Court of Victoria Court of Appeal decisions of Boroondara City Council v Cattanach [2004], and Greater Shepparton City Council v. Davis [2004] found that councils do not owe a duty of care to protect pedestrians from obvious defects or hazards in footpaths and roads
  • timeframes for response to defects that are over intervention levels.
/ Agree. RMP review has identified several improvements to the Council’s current RMP as detailed above. / Yes impact
  1. Road Management (Feb 2010 version) Review

Road Management Section / RMP Review Committee Comment / Impact on RMP
S 2.7 City of Melbourne Strategic Direction / Update Council Plan details / Minor - Administrative
S 2.8 Definitions / Update DSE State Government Department definition / Minor - Administrative
S 4.1 AssetMaster / Remove or cleaning from 3rd dot point / Minor - clarification
S 4.2 Road asset Register Content / Include exclusion for responsibility of Arterial Roads
Remove 5th paragraph page 13
Include reference to Civil Infrastructure Services contract – defect reporting of 3rd party road / non road infrastructure is based on City of Melbourne standards which may differ from the 3rd party agency service levels and intervention standards which take preference as the responsible asset owner. / Minor - clarification
S 5.4.1 Analysis of Accident Data and Traffic Counts / Update to current Road Safety Plan version / Minor - Administrative
S 6.4 Civil Infrastructure Services Contract / Include sentence on maintenance of Bridge pavement surfaces / Minor - clarification
S 8.2 References / Include reference to Pavement Asset Plans and remove Bridge maintenance manual and Framework for Sustaining the City of Melbourne’s assets (July 2006) / Minor - Administrative
Appendix 2 table 1 Inspection Frequencies – Asset in Road Reserve / Include reference regarding exclusion of surveillance on arterial roads / Minor - clarification
Appendix 2 table 2 Response times – Roadway, Footpath, Kerb & Channel / Change response times based on 2011 RMP audit recommendation # 1 / Major – amended standard
Appendix 2 table 8 Traffic Signs and Sign Supports / Change significant risk to high.
Change response times based on 2011 RMP audit recommendation # 1 / Major – amended standard
Appendix 2 table 10 Response Times – Guard Rails / Change significant risk to high.
Change response times based on 2011 RMP audit recommendation # 1 / Major – amended standard
Appendix 2 table 12 Response Times – Third party assets / Change response times based on 2011 RMP audit recommendation # 1 and # 3 / Major – amended standard
Appendix 2 table 13 Intervention Levels – Third party assets / Include qualification on Council responsibility / Minor - clarification
Appendix 2 table 14 Third party Pavement Reinstatement Non-Compliances / Change response times based on 2011 RMP audit recommendation # 1 / Major – amended standard
Appendix 2 table 16 Response Times and Intervention Levels – Pavement marking / Include reference to exclude traffic signal and pedestrian crossing line marking maintenance as per VicRoads Agreement / Minor - clarification
Appendix 3 Summary of Maintenance Standards – Bridge Structures / Update Bridge asset list / Minor - clarification

Road Management Plan Report June 2013 – DM#8401424 1