DOT FORM 468

REVISED 9/2004

C9-04 FORCE ACCOUNT NO.

DEPARTMENT OF TRANSPORTATION

ESTIMATE OF COST

PROPOSED FORCE ACCOUNT WORK

Date

Project No. County

Prime Contractor

Please refer to Standard Specification Section 109.05B. “Force Account” for details of specific procedures in maintaining records and determining compensation for work done on Force Account basis.

I. Description of Proposed Force Account Work:

1. Estimated Total of All Costs:

2. Estimated Time Required to Perform Work

II. Labor Classifications and Rates:

Classification / Hourly Rate

III. Materials:

Item / Quantity(optional) / Unit / Price

IV.  Equipment:

Make, Year, Model, Description / Monthly Rate / Monthly Rate/176 / Regional Factor / Age
Factor / AHER / Hourly
Operating Cost / AHOC / ARPH
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0
0 / 0.0 / 0.0 / 0.0

Allowable Equipment Rates shall be established as defined below (Spec 109.05)

a. Allowable Hourly Equipment Rate (AHER) = Monthly Rate/176 x Adjustment Factors x 70%

b. Allowable Hourly Operating Cost (AHOC) = Hourly Operating Cost x 70%

c. Allowable Rate Per Hour (ARPH) = AHER + AHOC

d. Standby Rate = AHER x 35%

I understand that the total shown is not binding, but that it should represent a realistic approximation. I understand that the labor rates, the equipment rental rates and the material unit costs are binding, I further understand that the work shall not proceed until I receive approval from the Engineer.

Signed:

Contractor

Original to the Engineer

(For Department Use Only)

Date received by Department of Transportation:

Date Approved: By:

State Construction Engineer

Date Notice to Proceed Given:

1 OF 2