PRM032/1

DEPARTMENT OF PUBLIC WORKS

ACKNOWLEDGEMENT OF HANDING OVER OF SITE

(Building Services – Clause 20 – PW677)

WCS NO:
REFERENCE NO:
CONTRACT NO:
PROJECT:
PROJECT MANAGER:
CONTRACTOR:
ADDRESS:
TEL: / FAX:

1.  The guarantee/securities required was accepted by the Department on

HEAD OF CONTRACT UNIT / DATE

2.  I/ we, the undersigned, hereby acknowledge that the site upon which the abovementioned service must be executed, has been handed over to me today and that the corner beacons of the site have been indicated. *

3.  I/we the undersigned, confirm(s) that the Priced Bill of Quantities has been submitted to the Department.

4.  I/we the contractor, have received copies of the following documents:

1
2
3
4
5
6
7
8
9
CONTRACTOR / DATE
PROJECT MANAGER / REPRESENTATIVE / DATE

NOTE: Site cannot be handed over without certification of acceptance of guarantee/securities by the section: CONTRACT DOCUMENTATION, of the Department.

* Delete which is not applicable

2002-04-04

PRM032/2

DEPARTMENT OF PUBLIC WORKS

ACKNOWLEDGEMENT OF HANDING OVER OF SITE

(Clauses 13 & 14 of GCC 1990)

WCS NO:
REFERENCE NO:
CONTRACT NO:
PROJECT:
PROJECT MANAGER:
CONTRACTOR:
ADDRESS:
TEL: / FAX:

1.  The guarantee/securities required was accepted by the Department on

HEAD OF CONTRACT UNIT / DATE

2.  I/ we, the undersigned, hereby acknowledge that the site upon which the abovementioned service must be executed, has been handed over to me/us today and that the corner beacons of the site have been indicated. *

3.  I/we the undersigned, confirm(s) that a detailed schedule of the existing installation(s) was made available.*

4.  I/we the contractor, have received copies of the following documents:

1
2
3
4
5
6
7
8
9
CONTRACTOR / DATE
PROJECT MANAGER / REPRESENTATIVE / DATE

NOTE: Site cannot be handed over without certification of acceptance of guarantee/securities by the section: CONTRACT DOCUMENTATION, of the Department.

* Delete which is not applicable

2002-04-04