MPS Master

SECTION 22 66 00

CHEMICAL WASTE SYSTEMS FOR LABORATORY FACILITIES

************************************************************************

Note To Specifier: Review every paragraph within this Section. Delete those items, products, sentences, etc. that do not pertain to the Project this Section is being used for. Delete the Note to Specifier hints within this Section during the Review.

************************************************************************

PART - GENERAL

SUMMARY

Section Includes: Include labor, materials, equipment, and accessories to furnish and install an acid waste piping system connected to the plumbing waste system.

SYSTEM DESCRIPTION

Acid Waste System: Furnish and install a complete acid resistant drain, waste, and vent system as specified and as shown on Contract Drawings.

Plastic pipe, stainless steel pipe, or glass pipe used in the system shall be acceptable to the State Plumbing Code, applicable fire codes, and the State Fire Marshal.

System shall include pipe runs, sanitary pattern drainage fittings, and accessories from neutralizing tank to sinks and drain connections, including acid resistant vents through roof.

************************************************************************

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

Note To Specifier: In Minnesota, you cannot blend sanitary and acid. In Minnesota, on remodeling projects, if the existing system is blended, and you are connecting to that system, the new and existing chemical waste system has to go to an acid basin.

************************************************************************

SUBMITTALS

Shop Drawings: Contractor shall submit a Shop Drawing portfolio showing acid waste and vent piping and methods of assembly for approval by Architect/Engineer. Each component, variation, model number, and option called out in this Specification is to be clearly indicated in submittal for each pipe and other items. Shop Drawings not complying will be subject to rejection and resubmittal.

Certification of Neutralizing Medium: Contractor shall submit a supplies verification that the neutralizing medium meets the following:

Calcium carbonate content is certified to 90percent or more.

Limestone dust is less than 0.25percent by weight.

Limestone chips are 2 to 3 inches in size.

QUALITY ASSURANCE

Regulatory Requirements:

State Plumbing Code

State Building Code

Local Codes and Ordinances

Local Authority having jurisdiction

Certification: Contractor shall obtain a letter of approval from the local plumbing inspector for the use of plastic pipe, inside the building, above and below the floor for the acid waste and vent system.

PART - PRODUCTS

MANUFACTURERS

Orion Acid Waste System above and below ground.

B. Kimax pipe as manufactured by O. I. Schott.

C. Stainless Steel Pipe Above and Below Ground: Pipe and fittings with pushfit joints shall be as manufactured by Blucher-Josam or Owner approved equal.

D. Neutralization Tanks: Neutralization tanks shall be as manufactured by Schier Products Company, Zurn Chemical Drainage, IPEX/Enfield Industrial Corporation or Orion Fittings, Inc.

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

E. Not Acceptable: PVCP, PVC, or ABS pipe and fittings are not acceptable.

MATERIALS

Application: Acid waste piping system, glass, stainless steel, or plastic, shall be of the same manufacturer, applicable material, and style throughout.

ORION PIPE AND FITTING: Polypropylene pipe and only no-hub fittings (mechanical joints).

2.04 KIMAX PIPE (GLASS PIPE)

2.05 STAINLESS STEEL PIPING

Material: Acid waste and vent system shall be of Type 316 stainless steel drainline employing pushfit spigotandsocket couplings.

Field Fabrication: Fabrication shall be in accordance with manufacturer's recommendations.

2.06 NEUTRALIZATION TANKS

General: Neutralization tanks shall be of type, material, and size specified. Tank shall be sized by manufacturer. Inside dimensions shall be 24inch diameter by 36inch height. Liquid holding capacity shall be approximately 55gallons. Inlet, outlet, and vent connections shall be arranged to meet installation requirements.

Materials: Tank, cover, and dip tubes shall be fabricated of high density polypropylene 5/16inch wall thickness.

Tank Cover: The tank shall be fitted with a matching highdensity polyethylene gasketed and bolted cover for tanks mounted on slab. Tanks below slabongrade to be fit with adjustable extension with painted diamond plate cover. A lift ring shall be provided in cover.

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

Fabrication: Tank shall be of molded, seamless construction, with flanged top and boltdown cover. The centerline of the inlet and the outlet piping shall be at the same elevation and the inlet dip tube shall be a minimum of 4inches above the bottom of the tank. The centerline of the vent opening shall be a minimum of 1inch above the centerline of the inlet and outlet.

Distributor Box: The inlet dip tube will have a polypropylene distributor box to keep the neutralization agent from clogging the outlet piping. The distributor box shall be a factory installed, 9inch cube with perforated sides, and the solid top will be drilled to allow the outlet pipe to be extended into the box.

Extensions: Below grade installations shall be furnished with a polypropylene walled adjustable extension, a manway and a primer painted, 1/4inch thick nonskid steel deck plate cover with lift ring.

Neutralization Agent: The neutralization agent shall be limestone chips, 2to 3inches in size, and with a calcium carbonate content in excess of 90percent. Contractor shall provide the required amount of this neutralization agent to fill the tank to a level just below tank outlet. Water shall be added to the tank before placement of neutralization agent.

PART - EXECUTION

ABOVE GROUND PIPING INSTALLATION

Pipe Routing: Contractor shall ascertain location of electrical panelboards, and shall keep piping out of area above panelboards, for a distance of 3'6" in front of and 1'6" from each side of panelboards. This includes all VAV box control panels.

BELOW GROUND PIPING INSTALLATION

Trenching: Trench bottom shall be continuous, relatively smooth and free of rocks. Where ledge rock, hardpan or boulders are encountered, pad trench bottom using a minimum of 4inches of tamped earth or sand beneath pipe.

Trenches under slabs shall allow for a 12inch depth of cover over pipe. In open locations, trench depth shall allow for top of pipe to be at least 12inches below the maximum expected depth of frost penetration.

Shield pipe installed beneath surfaces which could be subjected to heavy static weight or constant traffic within a metal or concrete casing.

Backfilling: Fill piping with water of an ambient soil temperature and check joints. Cover to a depth of 6to 8inches with dirt which is free of rocks, debris or particles larger than 1/2inch. Joints shall remain exposed for inspection.

Leave piping to settle and normalize dimensionally; check joints for tightness and tamp soil layer which will act as a cushion for subsequent backfill. During tamping, Contractor shall see that pipe alignment, both vertical and horizontal, is not upset.

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

When laying long runs of piping in high air temperatures, Contractor shall begin from a fixed point and work away from that point, testing and backfilling in accordance with preceding paragraph. This shall allow piping to assume soil temperature progressively as work proceeds.

Thoroughly test system for leaks. When tests prove satisfactory, cover joints with soil and remainder of complete backfill. Sharp rocks which could penetrate initial layer and damage pipe shall be removed prior to final backfill.

INSTALLATION OF POLYPROPYLENE PIPE SYSTEM

General: System shall be installed in accordance with manufacturers recommendations and governing plumbing code. Pipe and fittings in masonry construction to be protected in accordance with manufacturers recommendations.

Glass Pipe System: Install entire system free of stress. Horizontal lines shall allow for lateral movement of pipe and shall be supported by padded hangers every 8to 10feet. Support vertical lines by a padded riser clamp under bottom-most coupling in stack. Riser clamp shall restrict lateral, as well as downward movement.

Support 3inch and larger diameter stacks at each floor by a riser clamp on the pipe at outside diameter.

Support smaller diameter stacks at every other floor.

Pad riser clamps with 1/4inch thick solid Neoprene or BunaN rubber.

Support above ground horizontal acid resistant glass waste and vent piping and fittings in accordance with manufacturers instructions. Insulate in accordance with Specification Section Insulation.

Floor and Wall Penetrations:

Glass pipe passing through fire rated walls or floor slabs shall be installed in accordance with Underwriters Laboratories fire penetration systems for KIMAX glass pipe. System Number 90 or 282 of the UL Building Materials Directory shall be used for concrete or block, floor or wall penetrations. System Number 154 of the UL Building Materials Directory shall be used for gypsum wall penetrations.

Installation and Testing:

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

Install and test in accordance with manufacturers recommendations and local code requirements.

INSTALLATION OF STAINLESS STEEL PIPING SYSTEM

Stainless Steel Pipe System: Install entire system free of stress. Horizontal lines shall allow for lateral movement of pipe and shall be supported by hangers every 8to 10feet. Support vertical lines by a riser clamp under bottom-most coupling in stack. Riser clamp shall restrict lateral, as well as downward movement.

Support 3inch and larger diameter stacks at each floor by a riser clamp on the pipe at outside diameter.

Support smaller diameter stacks at every other floor.

INSTALLATION OF ABOVE GROUND ACID NEUTRALIZATION TANK

Installation of Acid Neutralization Tank: Tanks shall be placed on a flat, solid surface to allow uniform, full support to tank bottom. Such surfaces may be slabongrade floors or raised concrete pads.

INSTALLATION OF BELOW GROUND ACID NEUTRALIZATION TANK

Installation of Acid Neutralization Tank: Buried tanks shall be set on a level, 4inch thick concrete pad, poured at the base of the tank excavation.

Backfill around tanks with fine sand, free of stone, between 6to 8 inches thick around tank, and as high as possible above the fittings. Normal backfill material can be used outside of fine sand. Do not use mechanical tamping methods. Tanks shall be filled with water and neutralization agent before backfilling. No backfill shall be placed on the top of the tank.

Tank shall not be used to support manhole covers, traffic of any kind, or heavy equipment.

The access cover shall be installed with a finished height that will match the floor finish material and will have an epoxy paint finish.

Tank shall not be supported by inlet, outlet, or vent piping system.

Do not subject tank to pressurized or vacuum applications. Pressure tests shall be conducted only on the piping, do not pressure test tank.

TESTS

General: Test system in accordance with State and Local Plumbing Code.

NEUTRALIZATION TANK SCHEDULE

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities

MPS Master

SECTION 22 66 00

************************************************************************

Note To Specifier: Fill in capacities and numbers in yellow blanks below.

************************************************************************

Description:

Tank is based on Schier Products Company, ______, DB99.

Tank shall have a total capacity of ___ gallons and a liquid holding capacity of ___gallons, and be complete with ___inch inlet and outlet, and a ___inch vent connection. Tank shall be ___inch diameter by ___inch high.

************************************************************************

Note To Specifier: Use the next paragraph below for plain cover

************************************************************************

For below grade installation, provide Model AE, adjustable extension and access way with 1/4inch steel traffic pattern cover and lift ring, and a tank cover with Model MWY15, 15inch threaded manway.

************************************************************************

Note To Specifier: Use the next paragraph below for tile cover

************************************************************************

For below grade installation, provide Model AE, adjustable extension and access way with 1/4inch cover recessed 1/8inch for tile covering and lift ring, and a tank cover with Model MWY15, 15inch threaded manway.

Contractor shall furnish and fill the tank with the required amount of limestone to fill the tank to a level just below tank outlet. Water shall be added to the tank before placement of neutralization agent.

END OF SECTION

22 66 00 - 4

Chemical Waste Systems For Laboratory Facilities