TURN KEY SERVICES
INTRODUCTION
This document outlines the comprehensive set of services which have been during the project rollout phases.
The services include Project Management, Network Design & Integration and Network Build Services.
Project Management: provides the highly experienced team to manage all of the actors involved in the project to ensure the key project objectives are met
Network Design & Integration provides:
Detailed Network Design
Detailed Network Planning (incl RNP)
NetworkEngineering
NetworkAcceptanceProcedures
NetworkValidationIntegration
Network Build Services: provides a full set of services for the smooth build-out of the network
Site Engineering
Equipment Installation, Commissioning and Integration
NETWORK DESIGN & INTEGRATION
Network Design and Integration provides the end-to-end design and integration of the network. The INTRACOM TELECOM fully understands the complexity of integrating large complex networks through its many years of experience obtained around the world.
The Network Design & Integration package includes five integral and mutually dependant services:
Detailed Network Design: defines a phasing of the network’s architecture based on the schedule of services to be offered and provides an architectural blue-print for each identified phase.
Detailed Network Planning: structures the network’s technical architecture using if applicable necessary radio and transmission network planning tools
Network Engineering: provides the rules and methods for engineering all of the network components; equipment, sites, services and applications
Network Acceptance Procedures: defines the procedures to integrate, test and accept the overall network and the individual equipment components
Network Validation & Integration: validates the functioning of the network on either a platform or pilot network prior to full network deployment.
Network design process
DETAILED NETWORK DESIGN
Detailed Network Design defines a phasing of the network’s architecture based on the schedule of services to be offered and provides an architectural blue-print for each identified phase.
Tasks per phase
Defining the services and functions that are to be delivered over the network
Defining the network segments: Base Station Sub-system , Network Sub-system
Defining the content of the sites (BTS.) for the corresponding network segment
Defining the “user” planes (transmission, mobile switching, data network)
Defining the “Control and Signalling” plans
Defining the Management Plans
Defining the signalling network
Developing Network Synchronisation procedures
Developing network security criteria (equipment and path redundancy, reconfiguration)
Identifying network dimensioning criteria
Inputs
SWO´s inputs: Technologies , Services , Performances, Phasing, External interfaces. ,
INTRACOM TELECOM inputs: Portfolio , Roadmaps , Initial Architecture
DETAILED NETWORK PLANNING
Detailed Network Planning structures the network’s technical implementation answering the basic questions what is to be delivered, where and when. Planning is performed for each network segment .
Tasks
Dimensioning of the network (e.g. quantity of base stations and sectors, number of sites per type, capacity of trunks)
Defining the network’s topology
Inputs
SWO´s inputs: SWO´s segments and service types, performances, availability, coverage, quantities of users and cities, traffic matrix
SELEX inputs: Product technical description
INTRACOM TELECOM inputs: Field Information Database of the considered areas (area topography, high points, population and enterprise densities,etc)
Deliverables
Traffic forecasting
Node and system location
Detailed definition and configuration of site type
Network dimensioning (access, edge, core, interconnection)
Network topology and routing
Tools
For the Radio Network Planning CONTRACTOR is using a tool which offers a comprehensive, multi-technology radio planning environment to help wireless operators during the whole network life, from initial design to expansion and optimisation.
NETWORK ENGINEERING
Network Engineering provides the rules and methods for engineering all of the network components; equipment, sites, services and applications
Tasks
Defining labelling rules for all network components (sites, equipment, racks, NMS virtual objects.)
Defining addressing rules for the equipment
Defining the physical interface per equipment (electrical/optical, , connector types, …)
Establishing redundancy rules for configuring the equipment => model of equipment hardware & software configuration
Defining the number of racks and the number of sub-racks per rack for each site
Defining the power supply rules (type, margins,) per site
Defining the layout rules per site
Defining the installation rules per site
Inputs
Network Architecture Blue Print, Network Planning, Product Technical Descriptions
Deliverables
Detailed bill of quantities per site including hardware and software configurations
NETWORK ACCEPTANCE PROCEDURES
This service defines the procedures to integrate, test and accept the overall network and the individual equipment components.
Tasks
Defining the Site Acceptance Test Procedures (SATP) to accept the appropriate functioning of the equipment. Proposed Acceptance procedures are attached in Annex H “Acceptance Test Procedures”
NETWORK VALIDATION & INTEGRATION
This service validates the end-to-end functioning of the network on either a platform or pilot network prior to full network deployment. The network is validated with respect to key parameters;
Functional
Performance
Tasks
Defining the test plan
Defining the test procedures
Executing the tests
Analysing the results
Resolving the eventual trouble tickets with the suppliers
Inputs
SWO’s Service requirements (functional, performance…)
Architecture Blue-Print, Product Technical Description, Network Engineering Bill of Quantities
Deliverables
Results of tests
NETWORK BUILD SERVICES
With an unparalleled strong presence in all countries in Europe, INTRACOM TELECOM has the local resources, contacts, skills and experience to build the most demanding mobile network. INTRACOM TELECOM’s network build service offering extends from performing site engineering surveys to equipment installation and all works in between.
INTRACOM TELECOM selects referenced worldwide companies able to cooperate with local and qualified sub-contractors. INTRACOM TELECOM applies a field-proven methodology with performance indicators that guarantee sub-contractors improve their work continuously during the project.
The network build service package contains the following services:
Site Engineering
Site Preparation
RF Equipment Installation
Equipment Commissioning
Site Acceptance ProceduresPROJECT MANAGEMENT
INTRACOM TELECOM’SProject Management skills and practises have been designed for today’s telecommunication environment where the challenges of the operators require customised, integrated and high-speed deployment.
As the challenges of the operators are:
to offer a variety of telecommunication services to their subscribers
to achieve a very fast deployment of their telecommunication infrastructure
the actual telecommunication network implementation cannot only be dealt with the installation of various components of the network.
INTRACOM TELECOM’s Project Management approach ensures the delivery of an integrated solution able to control any task occurring at any stage of the project life cycle in a synchronised way.
For the efficient functioning of the project management organisation, a clear reporting interface within SWO ‘s organisation must be established thus ensuring a clear dialogue between the two parties.
The project management package is described as follows:
General Project Management: A single INTRACOM TELECOM’s interface to manage the complete implementation of the project.
Project office management which include among others
Scheduling & control: Scheduling experts to control the timely execution of all project deliverables
Administration: Financial & contractual expertise as well as contractual support.
Supply Chain: Supply chain specialists to manage the complete logistic chain from purchase order to on site delivery
Technical Office Management: Experienced professionals to supervise the many entities performing the technical services.
Roll Out Management: Experienced professionals to supervise the many entities performing the roll out services.
Documentation Management: The delivery of all documentation generated during the project’s execution in a cohesive and structured manner.
GENERAL PROJECT MANAGEMENT
INTRACOM TELECOM’s General Management delegates the global management of the project’s implementation to a designated General Project Manager (GPM). The GPM is the “mandated representative” responsible for all contractual and high level management aspects of the project.
The GPM is fully committed to the successful and timely completion of the Project. He has a comprehensive responsibility for the respect of the project’s time schedule and budget, for planning the necessary resources, for supervising and controlling the project’s performance, for initiating all required corrective actions and for issuing regular progress reports. The GPM action is supported by the following functions: implementation management, scheduling & control, logistics, documentation management and contract administration.
Tasks
Defining with the SWO the project’s implementation strategy including the scope of work, responsibilities, deliverables and milestones
Establishing the project management organisation, Project Management Plan and Quality plan
Managing, planning and controlling the project’s resources
Managing the project’s key success factors (schedule, performance, cost, quality)
Managing the project’s risks including contingency plans and risk mitigation
Developing regular progress reports and review meetings
SWO´s Benefits
A single interface to manage the project’s implementation
A permanent and comprehensive view on the status of the project’s implementation
Deliverables
The key deliverable will be progress reports covering the following points;
Status of the project’s implementation & logistics
Status of acceptance tests
Red & Green flags and solutions proposed to SWO to avoid project delay
PROJECT OFFICE MANAGEMENT
ADMINISTRATION
General Administration provides the management of all financial and contractual matters with regards to the project.
Tasks
Cost management & cost to complete reports
Preparation of reports and recording minutes of meetings
Change order management
Compliance to contractual requirements
SWO Benefits
Avoid contractual misunderstanding or conflict by a close contractual follow up
Satisfaction on contractual entitlement
Deliverables
Responsiveness to contractual claims and change orders
CENTRAL PLANNING
Scheduling & Control ensures the timely implementation of the project through the development of a Master Plan Schedule and the tracking of its progress. The schedule will be based on the key objectives defined by the SWO and will cover all tasks related to the implementation of the project.
Tasks
Developing a master plan schedule covering all tasks related to the project’s implementation
Monitoring of the schedule to ensure tasks are being performed on time
Proposing and implementing corrective actions should tasks fall behind schedule
SWO Benefits
Immediate notification of any slippage’s in the time schedule enabling the timely implementation of corrective actions
Deliverables
The key deliverable is the Master Plan Schedule which includes the following elements;
The major phases, milestones and performance goals of the project
An exhaustive list of all associated tasks, including their related dependencies, duration, start and completion dates
The resources and responsibilities to perform each task
The project’s critical path
SUPPLY CHAIN MANAGEMENT
Supply Chain Management provides the professional management of the complete supply chain from assisting the development of purchase orders to having equipment delivered on site and on time.
Tasks
Tracking of deliveries to ensure equipment is delivered on time and to take appropriate actions should delays become apparent
Provisioning of facilities for the warehousing of equipment
Managing equipment inventory
Transporting equipment to sites
SWO Benefits
Delivery of the right material, in the right quantity, to the right place, at the right time
Smooth functioning of the logistic process which is key to keeping to the time schedule
ROLL OUT MANAGEMENT
IMPLEMENTATION MANAGEMENT
Objective
A dedicated project organization for the GSM project will be established. This local project organization will be focal point for all tasks related to this project. Through these project organization central functions like manufacturing, central technical assistance centre, technical department, support by system specialists can be dedicated on demand to support the local organization.
Structure of the organization
The following graph shows the typical structure of the project organization:
Commercial in confidence
/ Turn Key ServicesCommercial in confidence
/ Turn Key ServicesShort description of the responsibilities inside the project organization
Steering Board
The Steering board constitutes the members of the high level management of SWO and INTRACOM TELECOM as well as the Key Account Manager (KAM). The board will hold regular meetings in order to monitor the project status and to clear points that could not be solved for any reason on the working level.
General Project Manager
The GPM is heading the project. He has the overall responsibility for the project implementation and is the main interface to the SWO regarding all topics concerning the project implementation and he reports to the steering board and to the INTRACOM TELECOM management.
The responsibilities of this function are as follows:
Unique and sole interface towards the SWO
Define & develop SWO relationship strategy: understand client environment, determine client interfaces and identify client responsibilities
Analyze the Project Statement of Works: confirm scope, contractual issues and validate risk assumptions
Establish the project’s structure including the project management organization
Establish & Implement the Project Management Plan (PMP)
Approve processes and procedures
Initiate and ensure the know-how transfer (internal and external)
Set-up the project team and assign project roles & responsibilities to individuals
Set-up and implements the Project configuration management: change, fault and documentation management
Manage the project’s risks including contingency plans and risk mitigation
Define the project’s key indicators (schedule, budget, quality)
Set-up the project reporting and review meetings
Close-out the project
Set-up the rules for an efficient Change Management Process and follow-up its effectiveness.
Validate assumptions and contractual risks.
Negotiation of contracts with subcontractors and suppliers
Project office
The project office constitutes all administrative functions necessary for the project and it assists the GPM in his daily business. The responsibilities of this function are as follows:
Determine contractual Obligations and Constraints versus SWO, subcontractors and suppliers
Analyze legal and commercial terms and conditions ruling the project
Identify Project completion criteria
Identify SWO, subcontractors and suppliers contractual responsibilities
Follows the evolutions of the contractual scope
Manage change or variation throughout project delivery
Lead the change order process as the outcome of the Change Management Process
Act as the focal point for issues arising under the contract: litigation, file, etc.
Establish and maintain contract file documentation
Monitor and follow-up contractual payments
Certify invoices & follow-up
Cost Control of Investment (Capex) and of Operational costs (Opex)
Ensure and lead permanent Budget Review and associated risks with Financial Control
Approve all Purchasing / Procurement processes, documents and contracts
Support the GPMO in all contract related matters, such as negotiations …
Insurance handling.
Preparation of complete and comprehensive files to forward the issue to the client or subcontractor
Establish a regular reporting document showing the various issues with details on cost, sales, man-hours, involved materials, etc.
Follow-up of all claim related actions of the various departments within the project
Technical Project Management
The technical project manager is the focal point for all technical related tasks inside the project. The TPM is responsible for the technical definition of all system elements and interfaces and he will have the lead in the system acceptance testing. He is the contact point towards the technical departments and he calls in and coordinates the system specialists when needed. He reports to the GPM.
The responsibilities of this function are as follows:
Detailed technical clarification of the contract
Analysis of SWO requests from the feasibility point of view
Provision of solutions for technical problems
Interface for technical support towards Competence Centres, TAC, TEC
Problem solving follow-up and corresponding regular reports
Answering technical SWO inquiries
Support and Set up of the Acceptance tests
Ensure translation of saleable items into the Supply Chain tools and follow-up
HW Reconfiguration
Follow-up of technical SWO requirements and technical change management
Planning/Introduction/First-off of new products in the project
Provision of information regarding new HW products
Provision of information on the phase out of the existing HW modules in the network
Follow-up of retrofit of the HW modules
HW CC and Central Inventory
Ensure availability of project inventory data (Configuration Management)
Establishing/upgrading of a project related HW InfoBase
Establishing/updating fault database of the system
SW CC and SW Production Coordination
Provision of information regarding new products, SW releases, services
Establishing/updating of a project related SW InfoBase
Planning/Introduction/First-off of new SW releases
Acceptance of new SW releases
Provide documentation numbers for INTRACOM TELECOM’s Products in accordance with INTRACOM TELECOM standards