Project Name – Project Plan – Appendices G to J
Project Name – Project Plan – Appendices G to J
Project name
Project plan
appendices G to J
Project Name – Project Plan – Appendices G to J
Appendix G – Procurement plan
Project procurement requirements matrix
WBS / Goods or service to be procured / Quality / Budgeted cost / When required / Procurement strategy contract type / Activities in procurement process / Possible providers / Duration of procurement process / When to commence procurement / Who is responsible / Schedule adjusted / Added to RAM / NotesDepartment of Transport and Main Roads Generic OnQ template Page 2 of 11
Project Name – Project Plan – Appendices G to J
Appendix H - Project controls
– change request
– change log
– issues register
– learnings register
To delete this guidance text box, double mouse click in the left margin and then press delete.
Type here
Department of Transport and Main Roads Generic OnQ template Page 3 of 11
Project Name – Project Plan – Appendices G to J
Change log
Project
Change request / Description / Value / Date / Status / Current budget / Days extension / Current completion dateCR 1
CR 2
etc
Issues register
Learnings register
1
2
3
4
5
6
7
8
9
10
11
Department of Transport and Main Roads Generic OnQ template Page 5 of 11
Project Name – Project Plan – Appendices G to J
Appendix I – Report format
Project manager's report to end month
1. Progress during month
2. Issues
3. Risks and opportunities
4. Activities for next period
5. Resourcing
6. Project control - Select from the following, as appropriate
6.1 Time
Forecast completion date
Original required completion date
Forecast completion dateCompletion date variation
Variation on program critical path (months)
Notes:
Major milestones
Milestones
/Date
/Notes
Estimated
/Actual
6.2 Variations or contingencies management
(This is the project budget, not the funding appropriation or current year allocation)
Forecast cost & budget to complete are as follows:
Business case / Project plan / Revised budget / Revenue / Forecast final costBudgeted work
Variations
Cost of Work
Contingencies
Total Estimated cost
Variation Log
6.3 Cost
Forecast final expenditure position relative to funding appropriation– all financial years
Overall Project / $M / NotesOriginal Approved Appropriation
CBRC Approved/Revised Appropriation
Forecast Final CostVariation on Revised Appropriation
Notes:
Current expenditure position – all financial years
Overall Project / Expenditure ($M) / Revenue ($M) / Total ($M)Previous financial years
This financial year
Total project to Date
Notes:
Expenditure details – This financial year
Month / Original ExpenditureEstimate (cumulative)
$M / Actual Expenditure year to Date
$M / Variation year to Date
$M / Original /Revised Allocation
$M / Revenue
$M / CBRC
Approved/ Revised Project Budget (All years)
$M / Forecast Final Project Cost (All years)
$M
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
6.4 Earned value (where appropriate/possible)
Earned value and schedule performance on the project to the end of month relative to latest baseline budget (project plan + variation Nos. … to …) are shown below:
Planned Value Cost (BCWS) / Earned Value Cost (BCWP) / Actual Cost (ACWP) / Schedule Performance Index (SPI) / Schedule Variance (SV) / Cost Performance Index (CPI) / Cost Variance (CV)Note These figures exclude contingencies
BCWS = budgeted cost of works scheduled
BCWP = budgeted cost of works perform
CPI - cost performance index = BCWP/ACWP (- Target > 1)
ACWP = actual cost of works performed
CV - cost variance = BCWP - ACWP (Target +ve)
SPI - Schedule performance index = BCWP/BCWS (Target >1)
SV - schedule variance = BCWP - BCWS (Target +ve)
Interpretation of figures -
The project is …… ahead/behind schedule on cost because…….
The project is …… ahead/behind schedule on time because……
The revised baseline shows project completion to be …………..
The following corrective action is proposed ……………......
Department of Transport and Main Roads Generic OnQ template Page 9 of 11
Project Name – Project Plan – Appendices G to J
Appendix J - Quality management plan
Activity / Deliverable / Tools / Standards to be applied / Strategy to meet standards specified / Responsibility /Department of Transport and Main Roads Generic OnQ template Page 11 of 11