Project Name – Project Plan – Appendices G to J

Project Name – Project Plan – Appendices G to J

Project name

Project plan

appendices G to J

Project Name – Project Plan – Appendices G to J

Appendix G – Procurement plan

Project procurement requirements matrix

WBS / Goods or service to be procured / Quality / Budgeted cost / When required / Procurement strategy contract type / Activities in procurement process / Possible providers / Duration of procurement process / When to commence procurement / Who is responsible / Schedule adjusted / Added to RAM / Notes

Department of Transport and Main Roads Generic OnQ template Page 2 of 11

Project Name – Project Plan – Appendices G to J

Appendix H - Project controls

– change request
– change log
– issues register
– learnings register
To delete this guidance text box, double mouse click in the left margin and then press delete.

Type here


Department of Transport and Main Roads Generic OnQ template Page 3 of 11

Project Name – Project Plan – Appendices G to J

Change log

Project

Change request / Description / Value / Date / Status / Current budget / Days extension / Current completion date
CR 1
CR 2
etc


Issues register

Issue No / Category / Description / Action by / Date / Priority / Action / Status


Learnings register

No / Category / Description / Learning / Date / Author / Sections affected
1
2
3
4
5
6
7
8
9
10
11

Department of Transport and Main Roads Generic OnQ template Page 5 of 11

Project Name – Project Plan – Appendices G to J

Appendix I – Report format

Project manager's report to end month

1. Progress during month

2.  Issues

3.  Risks and opportunities

4.  Activities for next period

5.  Resourcing

6.  Project control - Select from the following, as appropriate

6.1 Time

Forecast completion date

Original required completion date

Forecast completion date
Completion date variation
Variation on program critical path (months)

Notes:

Major milestones

Milestones

/

Date

/

Notes

Estimated

/

Actual

6.2 Variations or contingencies management

(This is the project budget, not the funding appropriation or current year allocation)

Forecast cost & budget to complete are as follows:

Business case / Project plan / Revised budget / Revenue / Forecast final cost
Budgeted work
Variations
Cost of Work
Contingencies
Total Estimated cost


Variation Log

No / Date / Variation / Source of funds / Amount / Time extension / Completion date

6.3 Cost

Forecast final expenditure position relative to funding appropriation– all financial years

Overall Project / $M / Notes

Original Approved Appropriation

CBRC Approved/Revised Appropriation

Forecast Final Cost
Variation on Revised Appropriation

Notes:

Current expenditure position – all financial years

Overall Project / Expenditure ($M) / Revenue ($M) / Total ($M)

Previous financial years

This financial year

Total project to Date

Notes:

Expenditure details – This financial year

Month / Original Expenditure
Estimate (cumulative)
$M / Actual Expenditure year to Date
$M / Variation year to Date
$M / Original /Revised Allocation
$M / Revenue
$M / CBRC
Approved/ Revised Project Budget (All years)
$M / Forecast Final Project Cost (All years)
$M
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun

6.4 Earned value (where appropriate/possible)

Earned value and schedule performance on the project to the end of month relative to latest baseline budget (project plan + variation Nos. … to …) are shown below:

Planned Value Cost (BCWS) / Earned Value Cost (BCWP) / Actual Cost (ACWP) / Schedule Performance Index (SPI) / Schedule Variance (SV) / Cost Performance Index (CPI) / Cost Variance (CV)

Note These figures exclude contingencies

BCWS = budgeted cost of works scheduled

BCWP = budgeted cost of works perform

CPI - cost performance index = BCWP/ACWP (- Target > 1)

ACWP = actual cost of works performed

CV - cost variance = BCWP - ACWP (Target +ve)

SPI - Schedule performance index = BCWP/BCWS (Target >1)

SV - schedule variance = BCWP - BCWS (Target +ve)

Interpretation of figures -

The project is …… ahead/behind schedule on cost because…….

The project is …… ahead/behind schedule on time because……

The revised baseline shows project completion to be …………..

The following corrective action is proposed ……………......

Department of Transport and Main Roads Generic OnQ template Page 9 of 11

Project Name – Project Plan – Appendices G to J

Appendix J - Quality management plan

Activity / Deliverable / Tools / Standards to be applied / Strategy to meet standards specified / Responsibility /