SI2007
updated: February 14, 2017
standard input (SI)
DESIGNER/CONSULTANT:
cONSULTANT PROJECT MANAGER:
DEPARTMENT PROJECT MANAGER:
fINAL SUBMISSION DATE:
Revisions to 2007 SI:date / BDC / Description / reason
feb 14 2017 / bdc17s-04 / revisions to civil rights special provision attachments
JAN 19 2017 / BDC17S-02 / REVISION TO SUBSECTION 107.04
JAN 18 2017 / BDC16S-10 / REVISION TO SUBPART 203.03.01
DEC 21 2016 / BDC16S-07 / Revision to Subpart 610.03.01 and 610.03.02
DEC 16 2016 / BDC16S-08 / Revision to Subpart 202.03.03
DEC 15 2016 / Revision to Subpart 912.04.01
nov 04 2016 / BDC16S-05 / Revision to Subpart 106.07.02
Sep 22 2016 / BDC15S-13 / Revision to Section 503
Sep 12 2016 / BDC16S-02 / Revision to Subparts/Subsections 159.03.06, 159.04, 610.03.02, and 610.04
AUG 24 2016 / BDC16S-03 / Revision to Subparts/Subsections/Section 101.03, 159.03.02, 701.03.02, 701.03.03, 701.03.06, 701.03.07, 701.03.15, 701.04, 704, and 1001.04
AUG 15 2016 / BDC16S-01R / Revision to Subsection 102.04
JUL 29 2016 / BDC16S-01 / Revision to Subsection 102.04
JUL 15 2016 / BDC15S-09 / Addition of new Subpart 108.07.03 to the 2007 SI
Feb 17 2016 / BDC15S-14 / Addition of new Subsection 106.10 and Revision to Subsection 108.01
Feb 08 2016 / BDC15S-08 / Addition of new Subpart 105.01.03
Nov 23, 2015 / BDC15S-11 / Revision to Subpart 610.03.07 and subsection 610.04
OCT 28, 2015 / BDC14S-05 / Revision to Subparts/Subsections/division 507, 507.02.01, 507.03.06, 507.04, 509, 509.01, 509.03.01, 509.04, 906.04.01, 906.07 and 913.03.01
Jul 30, 2015 / BDC15S-06 / Revision to Subparts 511.03.01, 606.03.02, 903.02.04, 903.06.02, 904.01.01, 904.01.02, 904.02.02, 904.03.01, 904.03.02, 904.04.02, 905.01.03, 906.04.05, Subsections 906.01, 908.03, 915.05, and Test Method NJDOT C-2
Jun 30, 2015 / BDC15S-07 / Revision to Subparts 401.03.03, 404.03.01 and 406.03.01
Jun 02 2015 / Revision to Subpart 403.03.01 d &E and 406.03.01 E
May 20 2015 / BDC14S-11 / Revision to Subparts 159.02.01 and 159.03.02 and addition of Subsection 913.04
Apr 22 2015 / BDC15S-03 / Revision to Subpart 504.03.02
Apr 08 2015 / BDC15S-04 / Deletion of the FHWA Attachment No. 5(A)
Mar 30 2015 / BDC15S-02 / Revision to Subpart 610.03.07 and Subsection 610.04
Mar 26 2015 / BDC15S-01 / Addition of new Division 420 (PAVEMENT PRESERVATION TREATMENTS) to the 2007 Standard Specification, revision to Subpart 504.02.01; and Subsection 901.07 and addition of Subsections 902.09, 902.10 and Section 1012
Jan 26 2015 / BDC14S-13 / Revision to Subparts 453.03.01 and 453.03.02
Oct 31 2014 / BDC14S-04 / Revision to Subpart 202.03.07
Oct 30 2014 / BDC14S-12 / Revision to Test Method B-3
Sep 26 2014 / BDC14S-10 / Revision to Subpart 152.03.02
Aug 29 2014 / BDC14S-07 / Revision to Subparts/Subsections 401.02.01, 401.03.02, 401.03.03, 401.04, 403.02.02, 403.03.01, 403.04, 404.03.01, 406.03.01, 902.01.01, 902.02.01, 902.02.02, 902.02.03, 902.02.04, 902.03.01, 902.04.01, 902.04.02, 902.04.03, 902.05.01, 902.05.02, 902.05.03, 902.06.01 and 902.06.03. Addition of Subpart 902.01.05 and Subsections 902.07 and 902.08
Aug 15 2014 / BDC14S-09 / Revision to Subsection 102.01
jun 25 2014 / BDC14S-08 / Revision to the State Attachment No. 1
Jun 20 2014 / BDC14S-06 / Revision to Subsection 109.06
may 08 2014 / BDC14S-02 / Revision to Subsection 102.04 and Subpart 108.07.02
Feb 28 2014 / BDC14S-01 / Revision to Subpart 202.03.07
Feb 04 2014 / ------ / Revision to 105.07.01(B) 3, Bureau of Electrical Maintenance, Central region ADDRESS has been changed.
Jan 24 2014 / BDC13S-14 / Revision to Subparts/Subsections 106.03, 106.07, 904.01.02, 904.01.06, 904.02.02, 904.02.06, 904.03.02, 904.03.06, 904.04.02, 904.04.06, 905.01, 909.02.01, 909.02.02, 913.01.01, 913.01.02, 913.01.03, 913.01.04, and 913.01.05
JAN 15 2014 / ------ / Revision to subpart 65X.03.01(A) updated the list of JCP&L approved Subcontractors, and The Links for civil rights forms have been revised.
Dec 18 2013 / BDC13S-13 / Revision to Subsections/Subparts 101.01, 102.09, 102.10, 102.15, 108.10, 108.20, 152.03.01, 156.03.01 and 159.03.02
Nov 21 2013 / BDC13S-11 / Revision to Subpart 610.03.07 and Subsection 610.04
Sept 18 2013 / ------ / Revision to Subpart 159.03.06, Subsection 159.04 and 610.02.01 (Renamed items per BDC13S-08)
Sept 17 2013 / ------ / Revision IN THE INSTRUCTIONAL TEXT OF subsection 106.09
Aug 19 2013 / BDC13S-08 / Revision to Subparts/Subsection 610.03.01, 610.03.02, 610.04, 912.03.01, and 912.03.02
Aug 12 2013 / BDC13S-10 / Revision to Subpart 404.03.01
July 30 2013 / BDC12S-04 / Revision to Subparts/Subsections 159.02.01, 159.03.02, 159.04, 611.01, 611.02, 611.03.02, and 611.04
Jun 26 2013 / BDC13S-09 / Revision to Subparts 912.03.01, 912.03.02 and 912.04.01
JUN 10 2013 / BDC13S-04 / Revision to Subparts 105.07.01, 159.03.02, 701.03.01, 701.03.15, 704.02.01, 704.03.01, 704.03.02, 704.03.03, 704.03.04, 704.03.05, 704.03.06, 704.03.07, 704.03.08, 704.03.09, and Subsection 918.01
May 13 2013 / BDC13S-07 / Revision to Subsection 105.05
Apr 19 2013 / BDC13S-06 / Revision to Subpart 903.03.05
Mar 08 2013 / BDC13S-05 / Revision to Subpart 159.03.08
Mar 01 2013 / BDC13S-01 / Revision to Subparts 155.03.01 and 156.03.01
Feb 22 2013 / BDC12S-15 / Revision to Subparts 203.03.01, 401.03.03, 401.03.04, 401.04, 402.03.02, 403.03.01, 902.02.04, 902.07.02 and 902.07.04
Feb 15 2013 / BDC12S-10 / Revision to Subpart 159.03.06 and Subsection 159.04
JAN 28 2013 / BDC13S-03 / Revision to the FHWA Attachment No. 4
Jan 18 2013 / BDC13S-02 / Revision to Subsection 102.10
Dec 17 2012 / BDC12S-08 / Revision to Subsection 509.04
NOV 21 2012 / BDC12S-14 / Revision to Subparts/Subsection 506.03.03, 506.04 and 507.03.06
Oct 12 2012 / BDC12S-12 / Revision to Subparts 201.03.01 and 202.03.03
Sep 28 2012 / BDC12S-11 / Revision to Subsection 601.04
Sep 21 2012 / BDC12S-13 / Revision to Subsections 151.04, 152.04, 157.04 and 160.04
aUG 30 2012 / ------ / Revision to THE CONTACT INFORMATION FOR REGIONAL Materials engineer’s office IN THE INSTRUCTIONAL TEXT OF subsection 156.03
July 20 2012 / BDC12S-09 / Revision to the Federal Attachment No.1 (Form FHWA-1273)
may 29 2012 / BDC12S-07 / Revision to Subsections 101.01, 101.03, 104.03 and 109.05
may 02 2012 / BDC12S-03 / Revision to subpart 401.03.03 and Test Method R-1
Apr 20 2012 / BDC12S-02 / Revised Attachments to the Special Provisions for the FHWA & Wholly State Funded Projects
MAr 30 2012 / BDC12s-06 / Revision to Subsection 109.09, Subparts 155.03.01 and 156.03.01
feb 14 2012 / bdc11s-13 / Revision to Subparts/Subsections 151.03.01, 152.03.01, 155.03.03 and 155.04 subsections 651.04, 652.04 and 653.04
JAN 12 2012 / bdc12s-01 / Revision to subsection 101.04
Dec 12 2011 / bdc11s-12 / Revision to subsections 651.04, 652.04 and 653.04
nov 15 2011 / bdc11s-03 / Revision to subsections 102.04, 505.03, 506.03, 509.03, and 554.04
Oct 25 2011 / bdc11s-10 / Revision to Subsections/Subparts 108.14, 155.03.01, 157.04, 158.03.02, and 159.04
aug 26 2011 / BDC11S-08 / Revision to Subparts 401.03.05, 902.03.03, 902.04.03, 902.06.03, and 903.05.04
Aug 12 2011 / BDC11S-09 / Revision to the State Attachment No. 1
July 11 2011 / BDC11S-06 / Revision to Subparts 607.03.02, 607.03.04, 610.03.04 and Subsection 611.02
Jun 17 2011 / BDC11S-07 / Revision to subpart 160.03.01
Jun 10 2011 / BDC11S-05 / addition of new to subsection 107.17
May 25 2011 / ------ / Revision to subsections/subpart 105.05, 107.09 , 608.02.01 and 608.03.06
Apr 10 2011 / ------ / Revision to subpart 65X.03.01(A) updated the list of JCP&L approved Subcontractors
Mar 30 2011 / BDC11S-01 / Revision to Subsections/Subparts 303.03.01, 401.02.01, 401.03.01, 401.03.02, 401.03.03, 402.01, 402.02.01, 402.02.02, 402.04, 404.03.01, 902.02.02, 902.03.02, 902.03.03, 902.04.03, 902.05.01, 902.05.02, 902.05.03, 902.06.03, 1009.01; and test method B-8. Added Subpart 402.03.02, Section 406, Subsections 902.07, 902.08 & 1009.03 and test methods B-10, B-11 and B-12
Mar 23 2011 / BDC11S-02 / Revision to subpart 152.03.01
DEC 29 2010 / BDC10S-08 / Revision to Subsections 105.05, 106.04, 108.09, 159.03, 159.04, 512.04, 701.03, 701.04, 704.02, 704.03, 704.04, 918.01, 1001.04 and 1001.05
DEC 22 2010 / BDC10S-12 / Revision to Subsections 105.07, 108.11, 152.04, 153.03, 155.03, and 157.03
Nov 16 2010 / BDC10S-10 / Revision to Subsections 609.03, 609.04, & 913.01
Nov 05 2010 / BDC10S-11 / Revision to Subsection 106.03
Oct 14 2010 / BDC10S-02 / Revision to Section 608 and Subsection 919.15
sep 10 2010 / bdc10S-09 / Revision to Subsections152.03, 201.03, 507.03, 509.03, 905.01, & 1011.03
Jun 04 2010 / BDC10S-07 / Revision to Subsections 107.12 & 108.01
May 18 2010 / BDC10S-05 / Revision to Subsections 105.07, 153.03, & 157.03
Apr 26 2010 / BDC10S-04 / Revision TO SUBPART 156.03.05
Apr 16 2010 / ------ / Revision TO 104.03.09, 109.07 & 607.03.01 (D)
Apr 09 2010 / bdc09s-01 / Revision to Subsections 612.02, 612.03, 612.04, & 911.02
Mar 31 2010 / BDC10S-06 / Revision to the FHWA Attachment No. 1 (FHWA-1273)
Mar 29 2010 / BDC10S-01 / Revision to Subsection 507.04 and Subpart 905.03.03
Mar 17 2010 / BDC10S-03 / Revision to Subsection 901.11
mar 10 2010 / ------ / Revision to subpart 65X.03.01(A) updated & REORGANIZED the list of JCP&L approved Subcontractors and instructions
Jan 26 2010 / BDC09S-11 / revision to subsections 508.02 & 508.04 and addition of new Subparts 508.03.03 & 909.02.09
jan 19 2010 / bdc09s-12 / Revision to Subsection 108.06
Dec 07 2009 / BDC09S-08 / revision to subsections 159.03.02, 609.03.01, 610.03.06, &911.03
Nov 24 2009 / BDC09S-10 / Revision to the State Attachment No. 1
Oct 09 2009 / BDC09S-09 / Revision to Subsection 101.01
Sep 21 2009 / ------ / Revision to 654.03.01 & instructions for JCP&L based on QIA-46
Aug 13 2009 / BDC09S-07 / Revision TO SUBPART 160.03.01
Jun 15 2009 / BDC09S-06 / Revision to Subsections 912.03 & 912.04
May 29 2009 / BDC09S-05 / Revision to Subsection 102.03
May 18 2009 / BDC09S-04 / Revision to FHWA and State Attachments
Apr 16 2009 / BDC09S-03R / Revision to Subsection 101.01 of the 2007 Standard Input
Mar 30 2009 / BDC09S-03 / Revision to Subsection 101.01 of the 2007 Standard Input
feb 17 2009 / bdc08s-02 / revision to subsections 101.04, 102.02, 102.04, 104.03, 105.07, 107.04, 107.09, 107.11, 107.12, 108.02, 108.08, 108.19, 108.20, 152.03, 159.02, 159.03, 159.03, 159.04, 160.03, 160.03, 201.03, 202.02, 453.03, 502.03, 503.03, 506.03, 507.04, 511.02, 513.02, 513.03, 606.03, 610.04, 652.03, Section 654, 701.03, 701.03, 701.04, 704.03, 704.03, 704.03, 704.03, 704.03, 704.03, 811.03, 903.03, 904.01, 904.02, 905.01, 911.02, 914.04, 1001.04, & 1001.05
SPECIAL PROVISIONS
1**************************************************************************************************************************1
include PROJECT DESCRIPTION AS SHOWN ON THE KEY sheet, AND FEDERAL PROJECT NUMBER (CONSTRUCTION) WHEN APPLICABLE.
subject matter expert (Sme) CONTACT – project manager
1**************************************************************************************************************************1
AUTHORIZATION OF CONTRACT
1**************************************************************************************************************************1
INclude THE FOLLOWING FOR fhwa funded projects
The Contract is authorized by the provisions of Title 27 of the Revised Statutes of New Jersey and supplements thereto, and Title 23 of the United States Code - Highways.
1**************************************************************************************************************************1
*****OR*****
1**************************************************************************************************************************1
INclude THE FOLLOWING FOR wholly state funded projects
The Contract is authorized by the provisions of Title 27 of the Revised Statutes of New Jersey and supplements thereto.
1**************************************************************************************************************************1
SPECIFICATIONS TO BE USED
The 2007 Standard Specifications for Road and Bridge Construction, of the New Jersey Department of Transportation as amended herein will govern the construction of this Project and the execution of the Contract.
These Special Provisions consist of the following:
1**************************************************************************************************************************1
complete and include the following
Pages 1 to ___ inclusive.
1**************************************************************************************************************************1
1**************************************************************************************************************************1
INclude THE FOLLOWING FOR fhwa funded projects
General wage determinations issued under Davis-Bacon and related acts, published by US Department of Labor, may be obtained from the Web Determinations online web site at http://www.wdol.gov/dba.aspx#0 Select state, county and construction type heading: HIGHWAY where the Project is to be performed then click Search.
Pay the prevailing wage rates determined by the United States Secretary of Labor and the New Jersey Department of Labor. If the prevailing wage rate prescribed for any craft by the United States Secretary of Labor is not the same as the prevailing wage rate prescribed for that craft by the New Jersey Department of Labor, pay the higher rate.
State wage rates may be obtained from the New Jersey Department of Labor & Workforce Development (Telephone: 609-292-2259) or by accessing the Department of Labor & Workforce Development’s web site at http://lwd.dol.state.nj.us/labor/wagehour/wagehour_index.html. The State wage rates in effect at the time of award are part of this Contract, pursuant to Chapter 150, Laws of 1963 (N.J.S.A. 34:11-56.25 et seq.).
If an employee of the Contractor or subcontractor has been paid a rate of wages less than the prevailing wage, the Department may suspend the Work, and declare the Contractor in default.
The following FHWA funded project Attachments that are located at the end of these Special Provisions:"
1. Required Contract Provisions, Federal-Aid Construction Contracts (Form FHWA-1273).
2. Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246).
3. Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246).
4. State of New Jersey Equal Employment Opportunity for Contracts Funded by FHWA.
2**************************************************************************************2
5. Emerging Small Business Enterprise Utilization Attachment, FHWA Funded Contracts.
OR
5. Disadvantaged Business Enterprise Utilization Attachment, FHWA Funded Contracts
The ESBE/DBE goals request form and classification codes worksheet are available at
http://www.state.nj.us/transportation/eng/documents/procedures/doc/ESBE-DBEGoalsRequest2012.doc
http://www.state.nj.us/transportation/eng/documents/procedures/xls/WorkClassD2012.xls
e-mail the completed form and worksheet along with a copy of the Engineer’s Estimate to THE BUREAU OF CONSTRUCTION SERVICES at
allow AT LEAST 10 days for CONSTRUCTION SERVICES to respond with a determination on which attachments (FHWA ATTAchment NO. 5 for ESBE or FHWA attachment NO. 5 for DBE) is to be used for the project.
upon receiving the information, fill in the blank (GOALS FOR THIS PROJECT) on the appropriate FHWA attachment LOCATED at the end of these special provisions.
delete the inappropriate fhwa ATTACHMENT
sme CONTACT – Office of Civil Rights, Contract Compliance
2**************************************************************************************2
2**************************************************************************************2
6. Equal Employment Opportunity Special Provisions.