TARGET CORPORATION

T- 1136 TARGET

SPRINGFIELD, PA

SUMMARY

The Target Store at 857 Baltimore Pike, Route 420 in Springfield, Pennsylvania was reviewed and inspected by Thomas Branham of Elevator Consulting Services, Inc. on January 26, 2014. My QEI number is 1339 and am certified by NAESA. NAESA is the National Association of Elevator Safety Authorities. We have identified corrective items that in our opinion need to be addressed by the Elevator Contractor. They are free to offer an explanation or dispute any individual item within the report but we can offer a reasonable reason for each and every negative evaluation. They are evaluated on and for the ASME 17.2 Code for Inspectors Manual and industry standards for acceptable installation and maintenance procedures.

Exit 3 on Interstate 476 – East approx. 2 miles

Geno’s / Pat’s – Take Columbus off freeway 95 - Go South turn Right on Reed – Go to 9th Street / right – 2 blocks – 1209 9th Street

Jim – SFT

Service Vendor – Schindler

Note: ILO – Inside Looking Out

OLI – Outside Looking In


T-1136 SPRINGFIELD

PASSENGER ELEVATORS 1 & 2

CORRECTIVE ITEMS

The following minimum items need corrective action taken:

State ID 1 – Location 30065 #1 ANLT 1 – 03/13/12 DUE

2 – Location 30065 #2 2 – 03/13/12 DUE

General

1.  Provide a file folder per unit for testing, visit documentation. Keep documentation current per code and Target contract. No maintenance log per unit(ANLT), Document call backs, repairs and testing. It is required by the contract.
Completion Date ______Initialed ______

2.  Clean the machine room. Remove defective vermaport chains and crate.
Completion Date ______Initialed ______

3.  Provide Group II key ring per ASME 17.1 Rule 8.2 code and per contract.
Completion Date ______Initialed ______

4.  Replace the fire Phase I key switch collar. The lettering has worn off.
Completion Date ______Initialed ______

5.  There is 2 – 3 inches of water in the pit. Assist Target by spotting the car so it can be removed.
Completion Date ______Initialed ______

Elevator One

6.  Perform the annual no load test as required by ASME 17.1 and Target contract. Properly tag and provide a copy of the test for review. Last tag date 3-12. Even if AHJ does not enforce Annuals, Target requires it in the Contract.

Completion Date______Initial_____

7.  The door locks, both on 1st and 2nd floors, are missing a cover plate. Replace missing plate, lock is open for mischief without plates.
Completion Date ______Initialed ______

8.  Secure the handrail to the cab wall, 2 standoffs are loose.
Completion Date ______Initialed ______

9.  Replace 2 burned out car operating panel lights, 1R and 1 in the auxiliary COP.
Completion Date ______Initialed ______

10.  Lube the bottom roll pin of the sill mount closures. Flush the rust out first with WD-40 and follow up with a higher viscosity.
Completion Date ______Initialed ______

11.  Scroll through all the I/O’s of the LCD screen of the controller and document / record all the settings, keep on site. Precautionary effort in case the ROM memory is lost.
Date Completed ______Initialed ______

Elevator Two

12.  Perform the annual no load test as required by ASME 17.1. Properly tag and provide a copy of the test for review. Last entry on tag was 3-12. Even if AHJ does not enforce Annuals, Target requires it in the Contract.

Completion Date______Initial_____

13.  Secure the loose handrail in the car, right side (OLI) at first floor front opening.
Completion Date ______Initialed ______

14.  Replace the top floor, front side, clutch release roller. The rear roller is all chewed up. Check the clutch for a sharp edge.
Completion Date ______Initialed ______

15.  Rear slow speed car doors are not plumb. Properly hang the doors. (No overlap on doors on bottom half.)
Completion Date ______Initialed ______

16.  Lube the bottom roll pin of the sill mount closures. Flush the rust out first with WD-40 and follow up with a higher viscosity.
Completion Date ______Initialed ______

17.  Replace 4 burned out car operating panel lights 1R, 2, 2R on Front COP and 1R auxiliary COP.
Completion Date ______Initialed ______

18.  Scroll through all the I/O’s of the LCD screen of the controller and document / record all the settings, keep on site. Precautionary effort in case the ROM memory is lost.
Date Completed ______Initialed ______


T-1136 SPRINGFIELD

ESCALATORS 4 (UP) & 5 (DN)

CORRECTIVE ITEMS

The following minimum items need corrective action taken:

State ID 4 – Location 30065 #4 Cat 1 Testing 4 – No Doc

5 – Location 30065 #5 5 – No Doc

General

19.  Provide a maintenance log, per unit, in the passenger machine room per Target contract. Document tasking, testing, callbacks and repairs. Put in file holder per unit.
Completion Date ______Initialed ______

Escalator 4(UP)

20.  Clean the top and bottom baskets.
Completion Date ______Initialed ______

21.  Perform annual Category 1 check of all safety devices per code. Document in log per Target contract. Regardless of internal methods, Target requires on-site documentation.
Completion Date ______Initialed ______

22.  Repair the top demarcation lighting to proper working order.
Completion Date ______Initialed ______

23.  Repair the bottom demarcation lighting to proper working order.
Completion Date ______Initialed ______

24.  Schedule a clean down per contract. Provide condition report. If you don’t have one, I will email it to you. Send your request to . On-site documentation is required by the Target contract. N/C
Completion Date ______Initialed ______

25.  There are multiple axels that have no mesh between the riser and tread of next step. Replace the step chain. Option to replace all axels that do not comply with code.
Completion Date ______Initialed ______

26.  Replace the left handrail.
Completion Date ______Initialed ______

27.  Replace the top right handrail newell cluster assembly, bad bearings.
Completion Date ______Initialed ______

28.  When the new A stand was installed on the bottom left deck the decking was never set in place properly. Set the decking back so the splice is not raised.
Completion Date ______Initialed ______

29.  Perform a “loaded gap test” on the escalator. Provide a print out for review. Scan it and email it to .
Completion Date ______Initialed ______

Escalator 5(DN)

30.  Clean the baskets.
Completion Date ______Initialed ______

31.  Perform annual Category 1 check of all safety devices per code. Document in log per Target contract. Regardless of internal methods, Target requires on-site documentation.
Completion Date ______Initialed ______

32.  Schedule a clean down per contract. Provide condition report. If you don’t have one, I will email it to you. Send your request to . On-site documentation is required by the Target contract.
Completion Date ______Initialed ______

33.  Repair bottom demarcation lighting to proper working order.
Completion Date ______Initialed ______

34.  Repair top demarcation lighting to proper working order.
Completion Date ______Initialed ______

35.  Reinsert the bottom left handrail inlet shroud back into the outer decking. Pin with a pan head stainless screw.
Completion Date ______Initialed ______

36.  Perform a “loaded gap test” on the escalator. Provide a print out for review. Scan it and email it to .
Completion Date ______Initialed ______


T-1136 SPRINGFIELD

VERMAPORTS 6 (DN) & 7 (UP)

CORRECTIVE ITEMS

The following minimum items need corrective action taken:

UP UNIT

Date / Hours / Carts
02-10-09 / 79,471.23 / 3,738,140
0-30-09 / 84,493.92 / 3,926,484
03-06-10 / 87,926.60 / 4,025,367
09-16-10 / 92,233.86 / 4,138,653
07-05-11 / 98,545.23 / 4,312,761
01-05-12 / 1023.37 / 4,413,036
05-21-13 / 13,101.90 / 4,673,094
01-26-14 / 18,780.41 / 4,804,282

DN UNIT

Date / Hours / Carts
02-10-09 / 80,640.77 / 3,311,889
09-30-09 / 85,626.39 / 3,506,400
03-06-10 / 88,981.67 / 3,612,765
09-16-10 / 93,237.09 / 3,734,311
07-05-11 / 99,358.98 / 3,921,272
01-05-12 / 101,822.03 / 4,002,189
05-21-13 / 112,492.79 / 4,282,979
01-26-14 / 118,189.14 / 4,421,641

VERMAPORT 6 (DN)

37.  The chains on both sides are sagging out of the tracks in the incline. The left side about 10’, right side closer to 20’. Replace the chain ASAP. Replace the tracks at the same time. The right side chain is currently walking on the sprocket and snaps about every full revolution. Short term may have to remove some links from the current chain, I recommend it be shut down soon unless the chain and track get replaced.
Completion Date ______Initialed ______

38.  The left side safety switch for chain stretch has been circumvented. Can never trip. Reset so it works.
Completion Date ______Initialed ______

39.  Adjust the bottom left access panel door to open. The door is inside the balastrade stainless. Adjust the hinges as needed. Replace bottom hinge that is broken.
Completion Date ______Initialed ______

40.  Adjust the bottom right access panel door to open. The door is inside the balastrade stainless. Adjust the hinges as needed. Clean the bottom access area.
Completion Date ______Initialed ______

41.  Clean all excess grease from the top left vertical shaft pillow block.
Completion Date ______Initialed ______

42.  Rebuild gate pivots, bearings to original design at the top end, both sides.
Completion Date ______Initialed ______

43.  Rebuild gate pivots, bearings to original design at the bottom end, both sides.
Completion Date ______Initialed ______

44.  Replace 5 missing cones on the left side.
Completion Date ______Initialed ______

45.  Replace 26 missing cones on the right side.
Completion Date ______Initialed ______

46.  The top right curve / wheel track has been badly dented, most likely from the bad chain situation. Replace the section of decking.
Completion Date ______Initialed ______

VERMAPORT 7 (UP)

47.  Replace the steel and plastic couplings at the gear shaft, both sides, ASAP.
Completion Date ______Initialed ______

48.  The left side safety switch for chain stretch has been circumvented. Can never trip. Reset so it works.
Completion Date ______Initialed ______

49.  Restore the top starting key switch to its original straight up position.
Completion Date ______Initialed ______

50.  Clean all the excess grease from the top left vertical shaft pillow block.
Completion Date ______Initialed ______

51.  Replace the missing screw on the top left arch clamp and one on the right side. Both are missing one screw.
Completion Date ______Initialed ______

52.  Replace 5 missing cones on the left side.
Completion Date ______Initialed ______

53.  Remove ty-wraps from top left gate and make operational.
Completion Date ______Initialed ______

54.  Rebuild gate pivots, bearings to original design at the top end, both sides.
Completion Date ______Initialed ______

55.  Rebuild gate pivots, bearings to original design at the bottom end, both sides.
Completion Date ______Initialed ______

56.  Replace the right side drive sprocket bearing at the top end.
Completion Date ______Initialed ______

57.  Replace the left side drive sprocket bearing at the top end.
Completion Date ______Initialed ______

58.  Replace both pillow block bearings on the drive shaft.
Completion Date ______Initialed ______

59.  Replace the top left drive bearing due to high rust sludge, bearing is noisy/bad.
Completion Date ______Initialed ______


T-1136 SPRINGFIELD

FREIGHT ELEVATOR 3

CORRECTIVE ITEMS

The following minimum items need corrective action taken:

ANLT – 03/10/12 DUE

60.  Adjust the hoistway door chains at 1st floor. Can part the doors about 6 inches on the right side when car is not there. Sometimes doesn’t close all the way and can bind up the doors. Also the left side does not rest on the floor without pushing it down.
Completion Date ______Initialed ______

61.  Increase dynamic braking in open operation, doors slam pretty hard at 1st floor.
Completion Date ______Initialed ______

62.  Perform the annual no load test as required by ASME 17.1 and Target contract. Properly tag and provide a copy of the test for review. Last tag entry was 3-12. Even if AHJ does not enforce Annuals, Target requires it in the Contract.

Completion Date______Initial_____

63.  Clean the 1st floor hoistway door tracks and door hardware of all fuzz, lint and dirt.
Completion Date ______Initialed ______

64.  Provide a file holder for the unit in the machine room per contract. Insert test reports, log book, oil monitoring sheets and all documentation required by the contract.
Completion Date ______Initialed ______

65.  Clean the pit.
Completion Date ______Initialed ______

66.  The bottom of the gate is out of the track. Reinsert gate shoes back in the track.
Completion Date ______Initialed ______

67.  Adjust the dynamic braking / slowdown at 2nd floor in the open operation.
Completion Date ______Initialed ______

68.  Replace missing door lock roller on 1st floor.
Completion Date ______Initialed ______

69.  Scroll through all the I/O’s of the LCD screen of the controller and document / record all the settings, keep on site. Precautionary effort in case the ROM memory is lost.
Date Completed ______Initialed ______


T-1136 SPRINGFIELD

TARGET RECOMMENDATIONS

Freight Elevator

1.  Provide elevator ID tactile on each elevator at all floors Should be on the jamb so it is visible from the hall button. Can be 4 X 4 tactile piece.

Cartveyors

None

Escalators

None

Passenger Elevator

  1. Provide elevator ID tactile on each elevator at all floors Should be on the jamb so it is visible from the hall button. Can be 4 X 4 tactile piece.
  1. Provide dedicated air conditioner unit for the machine room.
  2. Install the Fit Pit system to get rid of the water problem in the pit.
  1. Upgrade line starters to an E05 Siemens Electronic Starter.

JANUARY 2014 1 OF 11 T-1136 SPRINGFIELD, PA

QEI PERFORMANCE SUMMARY