CGIT Minutes – 2014 May WGM Phoenix

Monday Q1:

Rob Snelick (NIST), Wendy Huang, Sandra Martinez (NIST), Vince McCauley

Reviewed Agenda; Details on HL7 CGIT wiki.

Motion to approve agenda Sandra, 2nd Vince 3-0-0 Approved.

Project Review:

1.Version 2.8.1 in support of OO (LOI and eDOS)

2.RnCL – no progress

3.RnCL Release 2 – Finished - Reaffirmation

4.SAIF – no progress

5.ELR – progress, to be finished by September (create XML profile for the ELR R2 implementation guide). NIST is on target to complete this work.

6.Binding Syntax – in progress

7.V2 Tables Project -- progress

8.Functional Requirements Specification – To be discuss in Q3 (PSS) and in Order and Observations. Slide deck and white paper have been updated.

9.Tables

10.Improved Conformance Specification Project

a.V2 Value Set Specifications

  • Progress continues; S&I Framework have in principle adopted the proposal and is going to apply to HL7 V2 LOI implementation guide. More discussion to table place Thursday Q1 and Q2 in vocab.

b.Conformance Statements in Based Standard

  • No progress

c.Message Profile ID

  • See notes below

Action Item: Wendy. 629 update project details to 2.9. Rob to do write-up and provide XML schema.

Approve minutes from January San Antonio meeting:

Motion to approve minutes Rob, Sandra 3-0-0

Action Item: Rob list activities of a conformance facilitator

Message Profile IDs and MSH.21

An in-depth discussion on possible solutions for managing profile OIDs took place. How to update and version; When does a change in the implementation guide constitute the need for a new OID or version? A number of solutions were proposed. The plan is to document the proposal and then discuss again and vote.

Action Item: MSH.21 how to manage Profile versions using OIDs; Rob to summarize proposed solutions.

1.New OID entirely

2.Add .1 .2 to OID

3.Delta OID

4.Encoded string with date and version in EI.1

5.Add new MSH element with version and date info (release number).

6.Change MSH.21 DT

Monday Q3:

Rob Snelick, Sheryl Taylor, Nathan Bunker, Abdul Malik Shakir, Salima Shakir

Agenda:

  1. Functional Requirements Specifications – Project Scope Statement
  2. Conformance Tutorial

Functional Requirements Specifications – Project Scope Statement

Started to present the PSS for the Specifying Functional Requirements; this is a guide describing how to specify functional requirements (such as incorporate). This work is in collaboration and is tied to other PSS with Orders and Observations. Much of the quarter was spent explain the level of store requirements for the incorporation of data. Rob presented a set of slide explaining the concepts. See:

LRI_FunctionalRequirementsD2.4.pptx

Conformance Tutorial