St Edmund’s Parish AGM
Church maintenance update
Thursday 25th May 2017
RECAP
- Quinquennial Inspection Reports were published in July 2014 and September 2014 for St Joseph’s Church and St Edmund’s Church and Presbytery, respectively.
- Surveyor’s budget estimate for the works amounted to £207,700 (excl. VAT or fees), split into following categories:
- H&S
- Urgent
- 0 - 1 year
- 1- 5 years
- Desirable
- F&GP committee focus was to action ‘immediate’ works deemed H&S, urgent or to be completed in 0-1 year
- Surveyor’s budget estimate for these immediate works:
Church works / Surveyor’s Budget
St Edmund’s + Presbytery / £53,080
St Joseph’s / £52,100
TOTAL / £105,180 / Approx. 50% of QR total
- F&GP deemed some works could be cancelled and others deferred, awaiting the decisions on the future of the church buildings:
Church works / Surveyor’s Budget / Cancelled / Deferred / To action (budget)
St Edmund’s + Presbytery / £53,080 / £6,300 / £26,700 / £20,080
St Joseph’s / £52,100 / £12,200 / £14,700 / £25,200
TOTAL / £105,180 / £18,500 / £41,400 / £45,280
CHURCH WORKS UPDATE
- Majority of immediate works ‘to action’ nearly completed May 2017:
- Church lighting upgrades (internal + external)
- Fire safety review and first aid kits renewal
- Internal woodwork repairs
- Internal decoration (mainly at Presbytery)
- External decoration (mainly at St Joseph’s)
- Lightning conductors testing + maintenance
- Gutter cleaning
- Fencing and general signage
- Outstanding items of immediate works:
- Slip-resistant paint to St Edmund’s steps
- Tree pruning at St Joseph’s (to be completed in autumn)
- Actual expenditure:
Church works / To action (budget) / Spent / Saving
St Edmund’s + Presbytery / £20,080 / £10,642 / £9,438
St Joseph’s / £25,200 / £12,862 / £12,338
TOTAL / £45,280 / £23,504 / £21,776
- Huge gratitude to those who have given their time to date, to undertake the work themselves, or obtain competitive quotes and oversee the works so they were delivered cost effectively (Rory, Sean, Arthur, Tony)
GOING FORWARDS
- Father’s Pastoral Plan to be undertaken in the coming year
- Future of the church buildings will not be determined before the Pastoral Plan and it will take a few more years before any decision is made
- Required works to be undertaken to ensure building’s general upkeep for continued use by Father and parishioners in years to come
- Key repair or upgrades works will also need to be undertaken to avoid the properties falling into more costly disrepair if left unattended
- F&GP committee to undertake further review of QR works, to include:
- Deferred immediate works
- 1- 5 years works
- Desirable works
- Current surveyor’ budgets for remaining works as per QR report:
Church works / Immediate works
(H&S + Urgent + 0-1 year) / Long term works
(under QR review)
Works completed / Cancelled / Deferred / 1-5 years / Desirable
St Edmund’s + Presbytery / £10,642 / £6,300 / £26,700 / £26,000 / £29,400
St Joseph’s / £12,862 / £12,200 / £14,700 / £31,600 / £19,900
TOTAL / £23,504 / £18,500 / £41,400 / £57,600 / £49,300
- £148,300- Total QR surveyor’s budget for works yet to be undertaken
- St. Edmund’s deferred works (H&S + Urgent + 0-1 year) include:
St. Edmund’s - QR surveyors budget £26,700
Church / Presbytery
External window repairs, redecorate all high level windows + sacristy / Repair and paint external windows
+ internal redecorations
Disabled access audit / DPC review and upgrade
Internal light fittings upgrades
Church roof –repair broken tiles / Central heating upgrade
Sanitary ware upgrades to sacristy / Sanitary ware upgrades to presbytery
Confirm legal boundary / Roof insulation
- St. Joseph’s deferred works (H&S + Urgent + 0-1 year) include:
St. Joseph’s - QR surveyors budget £14,700
Church
Church tower decorations and inspection
Disabled access audit
Grounds – upgrade of car park drainage
Side path improvements