Pacific Northwest Wildfire Coordinating Group

Operations Committee

Meeting notes:November 19th Conference Call

Committee members present via call: Ted Pierce (NWCC), John Szulc (BIA), Greg Funderburk (NPS), Lonnie Click (WA – Fire Service), KevinKleinworth and Megan Fitzgerald-McGowan (WA-DNR), Bob Madden (OR-Fire Service),Brian Gales (FWS)

Absent: Joe Krish (BLM), Karen Swearingen (ODF), Steve Rawlings (USFS),Bobbie Scopa (PNWCG Liaison)

Guests: None

Agenda

Time Topic Presenter Purpose

0900 Leaders intent ChairProvide direction

OctNotes Discussion Chair Review/Finalize

Tracking commitments ALL Update

Taskings and POW (moving forward) ALL

Hot topics ALL

1030 Adjourn

**Reviewed October 2015 meeting notes and approved for posting

Existing Business

Deliberate Risk Assessment (DRA):

Noel Livingston and Rawlings distributed survey regarding DRA to field users (IC’s, Captains group, AA’s) to solicit feedback. Small work group led by Noel will insure that by the spring Team meetings in March 2016 the geographic area will have one template to utilize. It will be left to each IMT or unit to determine DRA process for examining risk, intent is to have a standard template provide a consistent tool for communicating with users.

Action:Rawlings/Gales will insure completion through Noel and roll out of template at Team training in March. Post approved DRA on the NWCC-MAC Web Page(Pierce).

Geo Board and IC Council Update:

Downsized Interagency T2 IMT’s from nine to eight in 2016. ICAPS is now open for the two Type 1 and eight T2 interagency Teams. Consistent messages from IC interviews – Theater of operations was good, additional info to define process requested, Area command insulated teams from AA’s and reduced complete communication and info sharing, good relationships with READS and AA’s. Private landowner law discussion, briefing to occur at Team training. ICAPS extended through December 21st.

Action: (Need lead POC for this) Add agenda Item in January to look at crew contract, opportunity for contract OVHD, local logging equipment and increased utilization of fire service outside of state mobilization and conflagration. Potential contacts Incident Business Team and NWSA rep.

Alaska Team Letter:

Alaska Coordinating Group letter to PNWCG on hold until Bobbie returns from AK. This should remain with PNWCG or Geo Board.

Action:Scopa transfer the request to the Geo Board as OWT has limited to no involvement with IMT oversight. Pierce/Gales will look for 2013 process document for supporting positions on Alaska Teams with individuals from PNW.

520 Nomination Process completed for 2017 Class:

OWT no longer provides oversight for T1 IMT’s, S520 nomination process should transfer to new oversight.

Action:Szulc to pass this process to the Geo Board to work with IC Counciland Training Working Team to determine who takes ownership of 520 processes in order to stay ahead of needs. Geo Board should oversee PNW application process for 2017 course.

Purpose and Focus of Operations Committee (OWT)

Meeting in January to pull out charter and make sure we know what we need to focus on, what is important to us, and how can we best serve the firefighters.

Action: OWT come to January meeting prepared to discuss/develop POW for 2016 and beyond. What can and should we take on and lead up through PNWCG to enhance operations and fire management in the PNW.

PNWCG / OPS LIAISON

Bobbie accepting new position and Brian no longer active at PNWCG will require new liaison.

Action: Scopa provide replacement name before leaving current position.

ALL HAZARD COMPLEXITY ANALYSIS AND MOBILIZATION:

Type 3 Response more often than Type 1 or Type 2

Action: (Click) to bring info to January meeting.

Task Order (1410-02) for Type 2 Crew Requirements:

Waiting for PNWCG to give specific direction and elaborate on task and its end state.

Action: Gales to request through PNWCG liaison the current need for this tasking. Does PNWCG want OWT to look at a new balance for Type of crews in the PNW. Tie this with crew contract evaluation discussion.

PNWCG PL5: FAST Team Report

Expect taskings in the future to the PNW working teams from report findings through PNWCG.

Wildland Fire Modules

Possible Action: (Rawlings) Consider Briefing Sheet: Capability and Use of Wildland Fire Modules

Short Haul

Action: Is there a need for white paper educating firefighters on the use and expectation of Short-haul. Are all other options considered first (ground transport, heli-spot and etc.)

Type 3 TeamsOut of area teams prepositioned several times during 2015 and generally utilized with good results.

Use of local IMT3s sometimes drains local leadership.

Suggestion for our GACC to provide IMT3s for out of area use. (SW or AK specifically)

Action: Develop Briefing Sheet(Click) Standardization of IMT3s and Utilization inside and outside of GACC, potential to formalize a Washington and Oregon T3 IMT.

Medical Response Protocol:

Insure agencies continue to require page 108 from IRPG as part of the medical plan.

Action:Add to package for out of geographic area teams and mention during AA session at Team training.

Agency Update

DNR:

Filling key positions, busy preparing for legislative session, House Bill 2093 working with private landowners, communities and a wildland fire advisory council.

NPS:

Filled regional budget analyst, regional FMO meeting coming up this winter.

BIA:

FMO meeting December 8-10 in Spokane interagency partners invited to participate

NWCC:

Vacancies include two coordinators, meteorologist, and IT specialist. Satellite dish packages now housed at RAC and can be ordered through the Cache. Adopt a team process clarification for IT items.

Washington Fire Service:

T3 Team application open. Fire Defense Board meeting on December 2. Looking at how to dispatch resources housed in the Snohomish County all hazard data base.

Oregon Fire Service:

Madden will be transitioning to PNWCG look to have a new rep on OWT soon.

USFWS:

Filling key positions, working to enhance interagency coordination in critical sage grouse habitat areas and completing resilient landscapes projects.

January Meeting:

January 27th0900 at NWCC

2016 Operations Working Team Members and Chair Order

Brian Gales – USFWS representative (Chairperson)

Steve Rawlings – USFS representative (Vice Chairperson)

Karen Swearingen – ODF representative

Lonnie Click – WA Fire Service representative

Greg Funderburk – NPS representative

John Szulc – BIA representative

Robert Madden - OR Fire Service representative

Joe Krish– BLM representative

Kevin Kleinworth – DNR representative

Ted Pierce – Dispatch Rep.

Bobbie Scopa – PNWCG Steering Liaison

John Ketchum – Ad Hoc member