TEMPORARY BRIDGE INSPECTION REPORT
INSPECTED BY:______
DATE:______
LOCATION:______
______
______
CONFIGURATION: ______
WEATHER:______
- DRIVE ACROSS BRIDGE: ______
- BRIDGE APPROACH: ______
- ABUTMENTS:______
- BEARINGS:______
- DECKING:______
- TRUSSES:______
- TRANSOMS AND BRACING: ______
- GUARD RAIL:______
- PIERS:______
- DEFLECTION:______
- LOADING:______
- FINISHES:______
-Check the above categories as they are completed.
-See TEMPORARY BRIDGE INSPECTION NOTES for the explanation of categories.
TEMPORARY BRIDGE INSPECTION REPORT
- DRIVE ACROSS:______
a.)Noise at slow speed:______
b.)Noise at ______mph:______
c.)Evenness (slow):______
d.)Evenness at _____mph: ______
- SIGNS ______approach: ______
a.)Speed limit:______
b.)Weight restriction:______
c.)Visibility:______
d.)Appropriateness:______
e.)Striping:______
TEMPORARY BRIDGE INSPECTION REPORT
- ABUTMENTScompass pt.______
a.)Backwall(sound)______
Settled from deck______
Gap to deck______
Bridge seal______
b.)Bearing shelf(sound)______
Settled______
Clean______
- BEARINGScompass pt.______
a.)Fixed(sound)______
Seated correctly______
Moved______
b.)Sliding(sound)______
Seated correctly______
Clean______
Dust covers on______
TEMPORARY BRIDGE INSPECTION REPORT
- JOINTS______
a.)Fixed(sound)______
Seated correctly______
b.)Expansion(sound)______
Seated correctly______
- DECKINGevenness:______
Noise______
Damage______
Surfacing intact______
Side bolts (if fitted)______
Curbs intact______
Surface angles intact______
- TRUSSESpins/clips______
Transom connection______
Rakers______
Tie beams______
Reinforcing chords______
General panel condition______
Spacer bolts______
TEMPORARY BRIDGE INSPECTION REPORT
- TRANSOMS/BRACING:______
Transom condition______
Vertical Bracing______
Sway bracing______
Bracing frames______
Horizontal bracing______
- GUARD RAILS, ETC.:______
a.)Guard rails______
Fixed per detail______
Secure______
Any panel damage______
b.)Bollard condition______
c.)Upstand wall condition______
d.)Crash Barriers______
e.)Footwalk condition______
f.)Handrail condition______
g.)Utility bearers______
TEMPORARY BRIDGE INSPECTION REPORT
- PIERS
a.)Pier cap condition______
b.)Columns plumb______
c.)Any settlement______
d.)Span junction detail______
e.)Distribution beams______
- DEFLECTIONcompass pt.______
Inner truss (inches)______
- LOADING
From ______AM/PMTO ______AM/PM
Day of the week ______
CARS/LIGHT TRUCKSTrucks ______Heavy/Special
- FINISHES (explain)
NOTES
______