Procurement Plan
I.General
1. Project information:
Country / Borrower : Republic of Kenya
Project: Water and Sanitation Service Improvement Project [WaSSIP]
IDA Credit No. 4376
Project Implementing Agencies: Athi Water Services Board (AWSB); Lake Victoria North Water Services Board (LVNWSB) and Coast Water Services Board (CWSB).
2.Bank’s approvalDate of the procurement Plan [Original Oct 31, 2007], Revision 2January 1, 2010:
- Date of General Procurement Notice: November 30, 2007
- Period covered by this procurement plan: January 1 – December 31, 2010.
II. Goods and Works and non-consulting services
- Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:
Procurement Method / Prior Review Threshold / Comments
1. / ICBand LIB (Goods) / Prior Review for all contracts
2. / NCB (Goods) / ≥500,000 / for CWSB the first two NCB contracts of any valuewould also be prior review(completed).
3. / ICB (Works) / Prior Review for all contracts
4. / NCB (Works) / ≥5,000,000 / for CWSB the first two NCB contracts of any value would also be prior review(completed).
* CWSBCoast Water Services Board.
- Prequalification.Bidders for (i) Implementation of Ruai and Gatharaini Sewerage System including Rui-Rwaka, Gatharaini North and Gatharaini South; (ii) Expansion of Mumias and Butere Water Supplies including the construction of Mumias sewerage and Butere on site sanitation; and (iii) Rehabilitation of Mzima Pipeline-Bulk Supply Systems, shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.
- Procurement Packages with Methods and Time Schedule (Summary)
- ATHI WATER SERVICES BOARD - WORKS
No / Contract Description / Estimated Cost USD / Procurement Method / Review by Bank (Prior/Post) / Bid submission & Opening
1 / NairobiCity Water Distribution Network - Rehabilitation and Improvement Works to General Waruingi Street, Eldama Ravine Road, Makadara and Mbotela Estates and Extensions to Shauri Moyo and Maringo Estates / 2,888,438 / ICB / Prior Review / 17-Jun-09
2* / Development of Alternative Sources for Kiambu and towns along Nairobi Transmission mains / 4,200,000 / ICB / Prior Review / 7-Apr-10
3(a) / Drilling and Equiping of boreholes (emergency works) in Nairobi / 656,691 / NCB* / Post Review / 14-Apr-09
3(b) / Construction of elevated pressed steel water tanks (emergency works) in Nairobi / 468,811 / NCB / Post Review / 25-Feb-09
4 / Construction of independent Mataara production Systems 3No. (Karimenu, Thiririka and Ndarugu) to serve Consumers around Ngethu Treatment Works currently served by the Nairobi System. / 5,498,303 / ICB / Prior Review / 6-Mar-09
5 / Rehabilitation of Sewers in Umoja / 200,000 / NCB / Post Review / 6-Jan-10
6 / Construction of Gatharaini Trunk Sewers including Rui-Rwaka, Gatharaini North and Gatharaini South / 19,400,000 / ICB / Prior Review / 26-Jun-09
7 / Construction of Lavington - Riruta Trunk Sewers Extensions / 1,560,646 / ICB / Prior Review / 20-Feb-09
8 / On site sanitation & Hygiene - Construction of VIP Latrines etc / 200,000 / NCB / Post Review / 26-Sep-09
9 / Rehabilitation of Dandora Sewerage Treatment Works and Reconstruction of NgongRiver Trunk Sewers / 6,519,142 / ICB / Prior Review / 6-Mar-09
10 / Construction of Komothai Water Supply – Rehabilitation and Expansion of Existing Works / 1,220,000 / NCB / Post Review / 16-Jul-09
11 / Extension Services to Informal Settlements / 690,000 / NCB / Post Review / 10-Sep-10
12 / Ruiru-Juja Water Supply Works - Weir Intake, Water Treatment Works, Dist Mains, Dist System & metering / 8,266,285 / ICB / Prior Review / 6-May-09
13 / Office Refurbisnments for WAB / 200,000 / NCB / Post Review / 5-May-10
14 / Drought Intervention Works in Nairobi - Drilling of 30 Boreholes (in Lots) / 736,722 / NCB* / Post Review / 16-Nov-09
15 / Drought Intervention Works in Nairobi - Equiping 30 new boreholes (in Lots) / 928,125 / NCB* / Post Review / 16-Nov-09
16 / Drought Intervention Works in Nairobi - Construction of Steel Towers for Water Storage tanks / 281,250 / NCB / Post Review / 16-Nov-09
II. LAKE VICTORIAL NORTH WATER SERVICES BOARD
PROCUREMENT PLANS – WORKS CONTRACTS
N0 / Project Description / Contract sum USD / Procurement method / Review by Bank / Bid submission & OpeningPrior / Post
A / REHABILITATION AND EXPANSION OF WATER SUPPLIES
PACKAGE 1: REHABILTATION WORKS (Water)
1 / Cluster 3 (Hamisi, Serem, Kaimosi, Jeptulu) / 1,436,114.59 / ICB* / Prior / 19-Jun-09
PACKAGE 2: EXPANSION WORKS (Water supply)
2 / Mumias / 16,070,095 / ICB / Prior / 14-Feb-10
3 / Kapsowar/Kapcherop / 589,304 / NCB / Post / 3-Feb-10
4 / Malaba / 1,732,406 / NCB / Post / 12-Jan-10
5 / Lessos / 1,300,053 / NCB / Post / 17-Mar-10
6 / Cluster 1 (Lumakanda and Kipkaren) / 1,396,409 / ICB / Prior / 23-Oct-09
7 / Cluster 2 (Chesikaki, Sirisia, Cheptais) / 2,306,032 / NCB / Post / 10-Jan-10
8 / Expansion of Chebara Water Treatment Works and additional reticulation system in EldoretTown / 5,038,196 / ICB / Prior / 4-Feb-10
9 / Extending services to informal settlements / 500,000 / NCB / Post / 5-Mar-10
10 / Kimilili / 2,109,650 / ICB / Prior / 24-Jan-10
PACKAGE 3: EXPANSION WORKS (waste water &San)
11 / Expansion of sanitation system of Malaba Kocholia scheme / 100,286 / NCB / Post / 24-Feb-10
12 / Development of sewerage system for Kimilili town / 100,857 / NCB / Post / 29-Dec-09
Sub Total for Expansion / 32,679,403
Miscellaneous
LVNWSB Upgrading office premises / 90,411 / NCB / Post / 31-Aug-09
WSPs Upgrading office premises and laboratory / 250,685 / NCB / Post / 31-Aug-09
Sub Total for Miscelleneous / 341,096
Grand Total Cost / 33,020,499
III COAST WATER SERVICES BOARD –
PROCUREMENT PLANS – WORKS CONTRACTS
No / Project Description / Contract sum USD / Procurement method / Review by Bank (Prior/Post) / Bid submission & OpeningW1 / Prequalification* for Rehabilitation of Mzima Pipeline-Bulk Supply Systems / N/A / ICB / Prior / 26-Aug-09
Bidding** for Rehabilitation of Mzima Pipeline-Bulk Supply Systems / 18,000,000 / ICB / Prior / 7-Mar-10
W2 / Source improvement - Tiwi Well Field/Likoni Pipeline-Bulk Supply Systems / 3,912,100 / ICB / Prior / 7-Mar-10
W3 / KilifiTown Water Reticulation, New Reservoir, and Kilifi Rural Water Supply-Kilifi WSP / 1,789,300 / NCB / Prior / 24-Apr-10
W4 / Malindi Towns Reticulation Improvement-Malindi Water Service provider / 1,268,000 / NCB / Prior / 3-Apr-10
W5 / Extending services to informal settlements- Mombasa and Malindi for Tertiary Pipelines (NGO contracts) / 545,400 / NCB / Post / 3-Jan-11
W6 / Extending services to informal settlements-Mombasa and Malindi for Trunk Mains / 545,400 / NCB / Post / 3-Jan-11
W7 / Malindi Sewerage/ponds/septic dumpsite / 500,000 / NCB / Post / 3-Apr-10
W8 / Rehabilitation and expansion of urban and rural water supplies for Kwale-Kwale WSP / 1,949,200 / NCB / Post / 1-May-10
W9 / Rehabilitation and expansion of urban and rural water supplies for Tana River-Tana River WSP / 601,600 / NCB / Post / 8-May-10
W10 / Rehabilitation and expansion of Voi urban and Taita Taveta rural water supplies-TAVEVO WSP / 1,464,000 / NCB / Post / 15-May-10
W11 / Rehabilitation and expansion of urban and rural water supplies for Lamu-Lamu WSP / 1,601,600 / NCB / Post / 22-May-10
W12 / Upgrading of Offices-WSPs (TAVEVO & Lamu) / 75,000 / NCB / Post / 10-Apr-10
W13 / Upgrading of offices-CWSB / 350,000 / NCB / Post / 3-Apr-10
W14 / Meter Installation / 120,000 / NCB / Post / 6-Jan-10
W15 / Construction of Mzima Repair kit shade at Mazeras / 45,000 / Shoping / Post / 16-Jan-10
W16 / Additional Works arising from Addendum consultancy for Mzima Works / 1,900,000 / NCB / Post / 11-May-10
- ATHI WATER SERVICES BOARD
REVISED PROCUREMENT PLANS - GOODS CONTRACTS
No / Contract Description / Estimated Cost USD / Selection Method / Review by Bank (Prior/Post) / Submission of bids & Bid opening
1 / Supply of Operational vehicles in lots: 12 Salon Cars, 37 4x4 WD Double Cabs, 6 4X4 Utility Vehicles and 40 motorcycles, 1 Lorry and 1 mini-lorry (AWSB, WSPs, NWSC, WAB, WASREB) / 1,498,058 / ICB / Prior / 7-Nov-08
2 / Supply of 2 Exhauster vehicles / 153,946 / NCB / Prior / 27-Nov-08
3 / Supply of Office Furniture for WASREB & WAB / 30,000 / NCB / Post / 7-Apr-10
4 / Supply of Office Equipment - Computers & Printers and other accessories in lots (AWSB, WSPs, WASREB & WAB) / 176,302 / NCB / Post / 7-Nov-08
5 / Communication (upgrading) and Document Management System / 60,500 / NCB / Post / 10-Oct-09
6 / Supply and installation of software: Lot 1 Financial/billing software and Lot 2Asset management Software / 120,000 / NCB / Post / 21-Aug-09
7 / Supply of consumer and master water meters, equipment and tools for WSPs & NWSC / 1,147,100 / ICB / Prior / 4-Jun-09
7(a) / Supply of Pre-Paid Meters / 200,000 / NCB / Post / 17-Nov-09
8 / Supply and Installation of Fleet Management and GPS Tracking system for NWSC / 150,000 / NCB / Post / 17-Jul-09
9 / Supply of water pipes, sewers and fittings for informal settlement works / 3,118,000 / ICB / Prior / 14-Oct-09
10 / Supply of plastic water tanks (emergency works) / 229,100 / NCB / Post / 13-Feb-09
11 / Disaster Recovery Site and Network for NWSC / 250,000 / NCB / Post / 2-Dec-09
12 / Supply of Water pipes, sewers and fittings for Peri-Urban Areas / 2,200,000 / ICB / Prior / 4-Sep-09
13 / Materials for Drought Mitigation Measures in NairobiCity - Water Tanks / 115,867 / NCB / Post / 14-Aug-09
- LAKE VICTORIA NORTH WATER SERVICES BOARD
PROCUREMENT PLANS - GOODS CONTRACTS
No / Contract Description / Contract Cost USD / Procurement Method / Review By Bank Post/Prior / Submission of bids & Bid opening
A / Support for Operationalisation and Strengthening of LVNWSB & WSPS
1 / Operational vehicles - 1 No Salon Car + 14 No 4 x 4 + 1 No Minibus +20 Motorbikes+2 SUVs includes cars for ESMF(US$ 50,000) / 512,820 / ICB / Prior / 20-Nov-08
Office Equipment - Computers & Printers and other accessories + 2No.small capacity & 1No.Large capacity phocopier including WSPs and ESMF / 272,000 / NCB / Post / 7-May-09
3 / Communication equipment - LVNWSB / 15,000 / shopping / Post / 23-Mar-09
4 / Upgrading software (Archiving System,AutoCAD,Antivirus,operating system) / 49,800 / shopping / Post / 25-Jan-10
5 / Office furnishing LVNWSB+WSPs / 60,000 / shopping / Post / 21-Jul-09
A / Sub Total - LVNWSB / 909,620
B / Support to Operationalisation and Strengthening of WSPs
1 / Provide GPS for Customer Survey for Mumias and Kimilili 20 each / 20,000 / shopping / Post / 30-Dec-09
2 / Communication equipment -WSPs / 20,000 / shopping / Post / 27-Jan-10
3 / Pressure Monitors / 100,000 / NCB / Post / 30-Jan-10
4 / Meters / 133,035 / NCB / Post / 28-Apr-09
5 / Accounting/finacial management software-Amatsi / 50,000 / shopping / Post / 25-Jan-10
Sub total - WSPs / 323,035
Total (LVNWSB + WSPs) / 1,232,655
C / Project Communication
1 / Publication of communication materials (newsletters, bronchures,fliers,etc) / 200,000 / NCB / Post / 4-Feb-10
2 / Printing of promotional materials (calenders, T-shirts etc) / 200,000 / NCB / Post / 8-Feb-10
3 / Visual-audio materials / 50,000 / shopping / Post / 20-Jan-10
4 / Procurement of broadcasting services (radio, TV) / 200,000 / NCB / Post / 19-Jan-10
5 / Procurement of print media services- Supplementaries in print media,Adverts ,Documentaries. / 200,000 / NCB / Post / 28-Jan-10
6 / Development and production of information tools for WSPs e.g Communication Strategy,brochures, flyers, service charters and journals. / 200,000 / NCB / Post / 16-Feb-10
7 / Shows and exhibitions (procurement of murals and exhibition materials) / 100,000 / NCB / Post / 23-Feb-10
8 / Documentation of best practices (tv documentaries and publications) / 200,000 / NCB / Post / 12-Mar-10
9 / Produce media briefing kit on Board's activities inclding IPPF issues / 50,000 / shopping / Post / 12-Jan-10
Subtotal Project Communication / 1,400,000
D / Environmental Management
Laboratory Equipment and Reagents and Consumables / 42,307 / shopping / Post / 17-Jun-09
Subtotal ESMF / 42,307
Grand Total Goods and Services / 2,674,962
COAST WATER SERVICES BOARD - WaSSIP
PROCUREMENT PLANS - GOODS CONTRACTS
No / Contract Description / Contract Cost USD / Procurement Method / Bank Review (Prior/Post) / Submission of bids & Bid opening
G 1 / Operational vehicles - 5No 4X4 S/Cab pickups and 12No 4X4 D/Cab pickups (1) / 487,500 / ICB / Prior / 20-Nov-08
G 2 / Operational vehicles - 39 Motorcycles and 1No Van (2 as rebid) / 151,512 / NCB / Prior / 24-Aug-09
G 3 / Office Equipment - Computers & Printers and other accessories for CWSB and 6WSPs / 210,000 / NCB / Prior / 17-Dec-08
G 4 / Office furnishings / 92,683 / NCB / Prior / 24-Jun-09
G 5 / Environmental Management Goods (Spectrophotometer, Hot Air Oven, Portable Microbiological Analysis Kit, Analytical Weighing Balance) / 280,000 / ICB / Prior / 21-Aug-09
G 6 / Procurement of Meters and fittings for the WSPs / 750,000 / ICB / Prior / 23-Oct-09
G 7 / Water Chemical ( 65% Calcium Hypochlorite ) / 190,000 / NCB / Post / 24-Oct-09
G 8 / Procurement of Bulk flow Meters for Mzima pipeline,4No / 60,000 / Shopping / Post / 9-Nov-09
G 9 / Goods for Informal settlements (Pipes and fittings) / 1,636,200 / ICB / Prior / 4-Dec-09
G 10 / Mzima Repair Kit (600mm dia pipes and fittings) / 250,000 / NCB / Post / 16-Oct-09
G 11 / Hand held GPS system for the WSPs including bulk water company (30No) / 40,000 / Shopping / Post / 7-Nov-09
G 12 / Repair of pipeline Maintenance plant (Excavator) / 25,000 / Shopping / Post / 11-Oct-09
G 13 / Section Valves for Network Sectorization for WPSs(30No) / 200,000 / NCB / Post / 7-Jan-10
G 14 / Pressure Gauges with data card for Monitoring of Project Indicators / 8,000 / Shopping / Post / 2-Jan-10
G 15 / Billing Software & Hardware for 6 WSPs / 200,000 / NCB / Post / 2-Jan-10
G 16 / Communication Equipment (Repeaters,Portable Radios etc) / 150,000 / NCB / Post / 10-Mar-10
G 17 / Backhoe excavator for pipeline maintenance / 130,000 / NCB / Post / 3-Dec-09
G 18 / Assorted Items for pipeline maintenance / 50,000 / Shopping / Post / 3-Dec-09
Total Cost / 4,910,895
III. Selection of Consultants
- Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Selection Method / Prior Review Threshold / Comments
1. / Competitive Methods (Firms) / ≥200,000 / for CWSB the first two contracts of any value would also be prior review (completed).
2. / Single Source (Firms) / Prior Review for all contracts
3. / Individual Consultants / ≥100,000 / for CWSB the first two contracts of any value would also be prior review (Completed)
4. / Single Source (IC) / Prior Review for all contracts
- Consultancy Assignments with Selection Methods and Time Schedule (Summary)
- ATHI WATER SERVICES BOARD -
REVISED PROCUREMENT PLANS - CONSULTANCY SERVICES
No / Contract Description / Appraised Cost Estimate USD / Selection Method / Review by Bank (Prior/Post) / Proposal submission & Opening date
1 / Technical Assistancefor Monitoring & Evaluation / 100,000 / CQS / Post / 23-Oct-09
2 / Combined financial, technical and legal audits for NWSC / 191,216 / QCBS / Prior / 23-Feb-09
3 / Technical Assistance for Communications and Related Works (AWSB, LVNWSB & CWSB) / 248,267 / QCBS / Post / 21-May-09
4 / Technical Assistance for Environmental Monitoring and Resettlement Action Plans / 100,000 / CQS/ICS / Post / 20-Mar-10
5 / Technical Assistance for Project Management and Procurement / 150,000 / CQS/ICS / Post / 15-Dec-09
6 / Supervision of NairobiCity Distribution Network - Rehabilitation & Improvements / 185,000 / QCBS / Post / 4-Sep-09
7 / Development of Alternative Sources for Kiambu and towns along Nairobi Transmission mains / 200,000 / QCBS / Prior / 28-Apr-10
8 / Extension of services to Peri-urban areas (Supervision) / 108,714 / QCBS / Post / 14-Jan-10
9 / Supervision of Independent Mataara Production system and Komothai water supply rehabilitation and extension works / 300,867 / QCBS / Prior / 7-May-09
10 / Design, Preparation of Bidding Docs and Supervision of Works for WaSSIP Informal Settlement Works / 250,000 / QCBS / Prior / 19-Nov-09
10(a) / Design, Preparation of Bidding Docs and Supervision of Works for Extension of Services to Informal Settlements - Huruma / 176,000 / CQS / Post / 3-Nov-09
11 /
Consultation, consensus building (several assignments)
/ 80,000 / CQS / Post / 20-Nov-09
12 / Supevision of Gatharaini Trunk Sewers / 596,433 / QCBS / Prior / 14-Apr-09
13 / Supervision of Lavington and Riruta Sewers Extensions / 281,429 / QCBS / Prior / 29-Dec-08
14 / Supervision of Rehabilitation of Dandora STP and NgongRiver Trunk Sewers / 514,489 / QCBS / Prior / 19-Jan-09
16 / Supervision of Ruiru-Juja Water Supply Works / 360,567 / QCBS / Prior / 6-May-09
17 / Technical Assistance to WSRB (Various Short Term Assignments for development and dissemination of regulatory tools) / 300,000 / QCBS / Prior / 27-Oct-09
17(a) / TA for Development and Implementation of Communication Strategy for WSRB / 100,000 / QCBS / Post / 3-Jan-10
18 / Technical Assistance to WAB (Various Short Term Assignments) / 140,000 / CQS / Post / 30-Jul-09
18(a) / Consultancy services for Detailed Design, Preparation of Bidding Documents & supevision of Refurbishment of the Water Appeals Board (WAB) Offices / 20,426 / LC / Post / 21-May-09
19 / Technical Assistance for Environmental Management / 80,000 / CQS / Post / 20-Dec-09
20 / Project Communication Consultancies (several assignments) / 1,100,000 / QCBS / Post / 28-Apr-10
20 (a) / Consultancy Services to facilitate stakeholders workshop / 49,050 / CQS / Post / 20-Apr-09
21 / CapacityBuilding Consultancy for NWSC (several assignments) / 500,000 / QCBS / Prior / 27-Jan-09
22 / Preparation of Hydrogeological surveys for boreholes (Emergency Works) in Nairobi / 8,788 / ICS / Post / 15-Jan-09
22(a) / Supervision of Drilling and Equiping of boreholes (Emergency Works) in Nairobi / 16,800 / SSS / Prior
23 / Facilitation for preparation of AWSB corporate strategic plan / 20,000 / ICS / Post / 16-Feb-09
24 / Employee and customer satisfaction survey / 120,000 / QCBS / Prior / 20-Dec-09
25 / TA to support WSPs with implementation of agreed actions identified during consultative workshops / 50,000 / ICS / Post / 20-Dec-09
26 / TA for Customer Identification Survey & Data Gathering for NWSC / 300,000 / QCBS / Prior / 20-Dec-09
28 / Consultancy Services for Improving Water Security: Masterplan for Developing New Water Sources for Nairobi and SatelliteTowns / 2,750,000 / QCBS / Prior / 14-Oct-09
29 / Consultancy services for Network Instensification for Nairobi City Water Rationing & integrating private borehole / 300,000 / QCBS / Prior / 9-Feb-10
30 / Consultancy services for Master Plans for Selected Informal Settlments in Nairobi / 250,000 / QCBS / Prior / 19-Feb-10
31 / Consultancy services for hydrogeological surveys for Emergency boreholes in Nairobi / 10,240 / ICS / Post / 21-Oct-09
32 / Consultancy services for supervision of Works for Drilling and Equiping of Borehole (Emergency Works) in Nairobi / 90,000 / ICS / Post / 8-Jan-10
33 / Consultancy services for Development of Asset Management Register for AWSB / 100,000 / QCBS / Post / 27-Feb-10
34 / Consultancy services for Independent Financial and Technical Audits for AWSB / 350,000 / QCBS / Prior / 21-Jan-10
35 / Consultancy Services for Risk Management Review (AWSB, CWSB, LVNWSB) / 50,000 / CQS / Post / 1-Mar-10
36 / Consultancy services for design of investment for short term measures / 200,000 / QCBS / Prior / 1-Mar-10
II. LAKEVICTORIA NORTH WATER SERVICES BOARD
PROCUREMENT PLANS - CONSULTANCY SERVICES
No / Project Description / Contract sum Design and Supervision USD / Procurement method / Submission of proposals by consultants
Review By Bank Post/Prior
Lake Victoria North Water Services Board
Consultancy Services For Supervisiob of Kimilili,Kwanza & Malakasi towns water supplies Package 1 / 336,903 / QCBS / Prior / 16-Jul-09
Consultancy Services for rehabilitation of rural water schemes i.e Musanda,Navakholo,Port Victoria,SioPort and 1 rural cluster i.e Hamisi,Serem,Kaimosi,Jeptulu supervision Package 2 / 200,225 / QCBS / Prior / 16-Jul-09
Consultancy Services for Supervision of Mumias and ButereTowns supervision Package 3 / 614,656 / QCBS / Prior / 16-Jul-09
Supervision of expansion of water supplies in 1independent rural schemes i.e Lessos, and 3 rural clusters i.e Custer 1 Lumakanda Kipkarren,Cluster2 Chesikaki,Sirisia,Cheptais Package 4 / 326,345 / QCBS / Prior / 16-Jul-09
5 / Extension of services in informal settlements supervision and design / 105,451 / QCBS / Prior / 8-Mar-10
Expansion of Chebara Water Treatment Works and additional reticulation system in EldoretTown including Kapsowar and Kapcherop WS supervision / 393,564 / QCBS / Prior / 15-Mar-09