PRE-FEASIBILITY REPORT

  1. SUMMARY

Project
Name of Company / Mine Owner
Location
Village
Taluka
District
State
1 / Mining Lease Area & Type of land
2 / Geographical co-ordinates / Corner / Latitude / Longitude
3 / Name of Rivers/Nallahs/Tanks/Spring/Lakes etc
4 / Name of Reserve Forest(s), Wild life Sanctuary/ National parks etc.
5 / Topography of the area
6 / Project Proposal
7 / Name of Mineral mined
8 / Rate of Production (in tons)
9 / Mineral Reserve in Million Tons
10 / Life of mine
11 / Drilling/ Blasting
12 / Mining method
13 / Ground water table intersection
14 / Drainage pattern/ water courses
15 / Break-up of Land Utilization Pattern
16 / Water requirement & Source
17 / Solid waste/Tailings
18 / Cost of project (Rs. Lakhs)
19 / Any Other (specify)
Name and address of the company
Registered Office
Mine office
Email
Prospecting Agency
Type of Activity
Utilities (Power, water Requirement)
Manpower Requirement
  1. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

(i)Identification of Project and Project Proponent.

Name of the Project:

(ii)Brief Description of Nature of the Project.

(iii)Need for the Project and its importance to the country and or region,

(iv)Demand Supply Gap:

(v)Demand Supply Analysis:

(vi)Employment Generation (Direct and Indirect)

  1. PROJECT DESCRIPTION

(i)Type of Project (including interlinked and interdependent project, if any)

(ii)Location (map showing general location, specific location and project boundary & project site-specific layout) with coordinates.

The coordinates of the area are

Corner / Latitude / Longitude
A
B
C
D

(iii)Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted.

(iv)Size or Magnitude of operation.

(v)Project Description with Process details (a schematic diagram/ Flow chart showing the project layout, components of the project etc. should be given.

(vi)Raw Material/ Consumables Required along with estimated quantity, likely source, marketing area of final product, mode of transport of raw material and finished product.

(vii)Availability of water, its source, Energy/power requirement and source should be given.

Quantity of wastes to be generated (liquid and solid) and scheme for their management/ disposal.

Selection of Dumping Site:not required

  1. SITE ANALYSIS

Connectivity:

(i)Land Form, and Land Ownership

(ii)Topography along with maps.

(iii)Climatic data from Secondary Sources;

(iv)Social infrastructure available;

5)PLANNING BRIEFPlanning Concept (type of industries, facilities, transportation etc)town and country Planning / Development authority classification:

Population Projection:

(i)Land Use Planning:

(ii)Assessment of Infrastructure Demand (PhysicalSocial):

  1. PROPOSED INFRASTRUCTURE

(i)Industrial Area (Processing Area)-

(ii)Residential

(iii)Green Belt-

(iv)Social Infrastructure

(v)Drinking Water Management (Source and Supply of Water)-

(vi)Sewerage System:

(vii)Industrial Waste Management

(viii)Power Requirement & Supply / Source.

  1. REHABILITATION AND RESETTLEMENT (R & R) PLAN
  2. PROJECT SCHEDULE AND COST ESTIMATES

RECOMMENDATIONS

Project proponent