iSa MANAGEMENT PLAN

TEAM Blue

The purpose of this plan is to describe the management philosophy, program organization, schedule, and major milestones that serve as the guidelines for execution of ISa.

Program Identification

This program management plan (PMP) is for iSa. This program will deliver ISa hardware, software, and documentation. Team Blue is responsible for the integration, acceptance testing, and training for this project.

Program Management Overview

Execution of this program will be performed in accordance with the procedures defined by the set of planning documents. These documents include Program Management Program (PMP), Resource Plan (RP), Funding Plan (FP), Marketing Plan (MP), Staff Plan (SP), and Risk Management Plan (RMP). The responsibilities of each team member, the capabilities of the system, and the Program deliverables are detailed under the contractual provisions, as well as BlueTeam’s technical, management, and cost proposals.

This Program Management Plan (PMP) describes the management philosophy, program organization, schedule, and major milestones that serve as the guidelines for execution of this project. The PMP also provides the customers and the team with the information needed to monitor and evaluation the progress. This plan provides the following information:

  • Corporate organization
  • Areas of responsibilities of each member of the organization
  • Work breakdown structure (WBS)
  • Program planning
  • Progress reporting and team management
  • Detailed schedule and major milestones
  • Program overviews

This PMP also provides the guidelines for these followings:

  • Risk Management
  • Evaluation Plan
  • Testing Plan
  • Resource Management Plan
  • Funding Plan
  • Marketing Plan
  • Installation Plan

Corporate Structures

Blue team was formed in spring 2008 at Old Dominion University. Blue team’s members are responsible for the planning and development of the iSa System. We will be either directly involved in the entire process or outsource the responsibilities to other entity. The corporate structures are:

  • CEO & President, Blue Team corporation
  • Vice President
  • iSa System Program Office that will execute the program and provide day-to-day management, engineering, and administrative resources necessary to management and maintain the program.

Management Approach

Blue Team’s goal is to work closely with the customers and specialists to fully understand the system requirements. The management approach, therefore, is based on the philosophy that successful Programs are delivered by goal-oriented teams. A program manager (PM) will lead the team toward this goal. A PM is responsible for all planning, programmatic, technical and financial aspects of the program. The PM will assigned and distribute tasks among each team member to assure that the project is carried out effectively and successfully. The primary duties of the PM include these aspects:

  • Planning
  • Scheduling
  • Technical activities
  • Customer liaison
  • Program related decisions (with the approval and suggestion from team members)

A key element of Blue Team project is specialist and customer involvement. Blue Team seeks specialists’ opinions during the development and installation process as well as customer active involvement to create a product that meets that customers’ goal.

Project Team

Blue Team’s goal is to provide an effective, low cost COTS system. Through strategic planning and an extensive selection process, Blue Team has assembled a cohesive Program Team that will work together to develop and implement each component that is needed to comprise the ISa System.

  • Program Manager (PM)

Matthew D Salyer

  • Senior at OldDominionUniversity, expected graduation date: December 2009
  • Major in Computer Science with a minor in Information Technology
  • Interest :graphics design, web design, web database
  • Skills: Programming (C++, Java, Visual Basic), graphic design and web design (Dreamweaver), web design,

Responsibility

The PM will manage the Blue team and is responsible for the planning and coordination of the day-to-day technical, contractual, and financial aspects of the program. She/he is responsible for the development and management of all program schedules, the coordination of all team members and all program activities.

  • Hardware Specialist (HS)/ Risk Specialist (RS)

Scott Wood

  • Senior at Old Dominion University, expected graduation date:

December 2008

  • Major in Computer Science with a minor in Computer Engineering
  • Interest : Networking, Programming
  • Skills: Programming (C++, ASP, VBasic), Networking

Responsibility

The RS is responsible for identifying all possible risks that are associated with the iSa. All identified risks will need mitigating actions to reduce or eliminate the risks.

The HS is responsible for evaluating existing hardware options that are available to the team. The HS is in charge of determining where and when COTS are acceptable and when new hardware must be developed. The HS must evaluate available hardware options and advise the team on which options are best for the fulfillment of the team’s goals

.

  • Senior Engineer (SE)

Dominic Eldridge

  • Junior at Old Dominion University, expected graduation date: December 2008
  • Major in Computer Science
  • Interest: Database, Network Security
  • Skills: Database Administration, Network Security, UNIX/LINUX System

Administration, Web design, Programming (Perl, C++, HTML)

Responsibility

The SE is responsible for the development and implementation of the system software function as defined in the system specification. She/he will assure that the integration for all systems components meet the performance requirement for the system.

  • Financial Director (FD) / Webmaster (WB)

Scott Seto

  • SeniorOldDominionUniversity, expected graduation date: May 2008
  • Major in Computer Science
  • Interest and Skills: Software engineering, computer network, military history

Responsibility

FD is primarily responsible for managing the financial risks of the ISa System project. She/he is also responsible for financial planning and record-keeping, as well as defining and reporting the budget for each project phase (defined in staffing plan). He will work closely with the technical director to ensure that the project meet budget requirement for each phase.

The WM is responsible for determining the functionality and look of the website that will house the rate-it engine. As WB, the responsibilities include creating the team and product websites, as well as managing the web developers in future phases.

  • Marketing Manager (MM)

Brad Travalgio

  • Senior at Old Dominion University, expected graduation date: December 2008
  • Major in Computer Science
  • Interest: Network, web database, web design, web programming

Skills: Web database and programming (PHP, HTML, XML, mySQL, pl/SQL),

  • Skills: programming (Java, C/C++)

Responsibility

MM is primarily responsible for managing contact with subcontractors. This person is responsible for strengthen and expand ISa System awareness and develop new marketing channels that are critical for the successful of the product. As a guardian for brand values, the MM will develop, implement and evaluate the annual strategic plan and oversee various marketing programs including developing market research programs. Finally, the MM will build the framework for marketing initiatives and devise marketing and PR campaigns.

  • Documentation Specialist (DS)

Mark Mahn

  • Senior at Old Dominion University, expected graduation date: December 2008
  • Major in Computer Science
  • Interest: Artificial Intelligence
  • Skills: Programming (Java, C++, ANSI C, Perl, and SQL)

Responsibility

The DS provides overall documentation direction for the Program Team. The DS will ensure that everyone on the team has met the required documentation specifications, and that each person is aware of the tasks he/she has been assigned. The DS will also provide documentation of each meeting in which an overview of tasks assigned is given.

Program Duration

The ISa System program is a 3-year duration project, from initializing the project to delivering the first product. The schedule consists of the preliminary design phase which will last through May of the year 2008, the construction and development process will be completed around the last quarter of 2009, the evaluation and testing process will last though the third quarter of 20010 and the first delivery of the product will be in April of 2011.

Work Breakdown Structure (WBS)

Constructed using Microsoft Visio, WBS[1] reflects the budgeted cost versus resources required to complete each task. The WBS phase (see staffing plan) numbers are integrated as part of the master program schedule. For each WBS element, budgets for work planned, actual cost and estimates to complete are managed by the Project Manager with the assistance of the Funding Director. The WBS is an essential tool used to track program costs, progress, and earned values relative to master program schedule.

Program Planning

The Blue program team will maintain the program master schedule. The master schedule contains a line item for each WBS element and will be used to track the progress of each element. All deviations from the master schedule must be coordinated with the program office It is the responsibility of each team member to call attention to possible schedule deviation at the earliest opportunity. The program will be develop in phases[2], formal review will play an integral part in monitoring program progress.

Team Blue will use the “top-down approach” for our schedule. This means that we will start with the largest items of the project and break them into their subordinate items. This helps make constructing the WBS more convenient.

Progress Performance Assessment (PPA)

All members of the Blue Team will participate in the PPA. As a team, all members will track technical and financial progress of the project. Reviews will be held Weekly to assure the project’s goals will be met. The PPA contains the followings,

  • Report of progress to date
  • Present work to be performed for the next period
  • Present status of all the deliverable
  • Discussion of technical and programmatic issues (if exist)

In preparation for each meeting, the PM will collect the current status of on-going activities, progress against schedule and budget, and plan the activities for the next meeting. Quality reviews for all documentations and activities will be performed periodically.

Technical Progress and Report

The schedule of the program is established during the planning phase and monitored throughout the performance period. The schedule contains an entry for each WBS element. The percentage of completion for each WBS element is determined as necessary to manage program progress and is reviewed at least quarterly.

Financial Management and Report

The financial management for the program is established during the planning phase and is monitored throughout the performance period. A budget representing labor costs, material purchase, overhead cost, travel expenses, and other expenditures is prepared and implemented for each phase.

The Project Manager with the assistance of the Financial Manager will oversee the overall spending profile of the program. They will use the financial summary provided by the Contracts Administrator to assess the technical progress in order to track the overall status of efforts.

Earned Value Ratio (EVR)

EVR will be reported quarterly. The EVR will be reported in form of Schedule Performance Index (SPI) ratio and the Cost Performance Index (CPI) ratios. If the ratios are below 0.90, further explanation is needed. SPI and CPI are defined below:

SPI = BCWP/BCWS

CPI = BCWP/ACWP

Where BCWP = Budgeted Cost of Work Performed

BCWS = Budgeted Cost of Work Scheduled

ACWP = Actual Cost of Work Performed

Quality Process and Reporting

Quality management on the program will be a team effort. It is the responsibility of the quality system manager to coordinate conduct, quality reviews, and audits. The Project Manager task is to oversee the development and implementation of the System Quality Program Plan.

Monthly Progress Report

In order to ensure the goals of the project to be met, Blue Team will produce a monthly progress report. The report should include, but not limited to the followings,

  • Progress summary
  • Milestone deliverables, planned, actual, and forecast
  • Earned value schedule and cost performances indices
  • Critical list of all items, responsibilities, and activities
  • Risk status
  • Resource profile
  • Milestones/deliverables planned, actual, and forecast status
  • Quality Actions
  • Configuration change control issues

Reviews

Reviews will play an integral part in the management and monitoring of all phases of the ISa System project. Informal reviews with the program team members will be held on a weekly basis to ensure that the project stay on track and meet the planned deadlines. Reviews includes the followings,

  • Program management review
  • Technical reviews
  • Software requirement review
  • Hardware requirement review
  • Preliminary design review
  • Critical design review
  • Quality review

1

[1] For detailed WBS see Work Breakdown Structure document

[2] For detailed phase information see Staffing Plan and WBS document