PUBLIC WORKS AND WWTP REPORT

NOVEMBER 2017

PUBLIC WORKS

  • Monthly maintenance, general cleaning and repairs at Town Hall, Pavilion, Parham Park, Festival Grounds, Public Works buildings and Police Department.
  • MonthlyRecyclables 12.7 tons.
  • Monthly Solid Waste approx. 54.44 tons.
  • Picked up miscellaneous residential brush and debris.147 brush pick-ups that totaled 18 tons of brush.
  • Continue maintenance and repairs on Welcome Banners, Miss Maggie Banners andWinter Banners.
  • Perform ditch, culvert, shoulder and road maintenance along streets. Both private and Town streets.
  • Service and/or repaired 3 Public Worksvehicles1 Administration and 3 Police vehicles.
  • Picked up bagged trash and debris along Highway 19 and Highway 276 from Fie Top Road to the Waste Water Treatment Plant.
  • Changed out Fall Banners to Winter Banners.
  • Began the 2018 Electrical inspections for all town buildings. These are done every 3 years.
  • R&R Park work continues with grounds improvements, sign work and electric work for winter woods and sign.
  • Public Works has installed snow and ice removal equipment in the trucks and is ready for SNOW.
  • Thru the month of November Public Works has worked many hours to have all the Winter Lighting installed and functioning properly for the lighting of the valley November 25th. In addition to working with the Winter Lighting group, Duke Power and HEMC to make Winter Lighting a success we installed an additional 15 pole mounted decorations, additional Winter Woods displays and doubled the decorations at the Festival Grounds.

WWTP

  • Monthly testing, monitoring and analysis; Monthly cleaning and repairs.
  • Monthly Road, Levee, equipment and building maintenance.
  • Continued yearly sewer line and manhole inspections as required by DENR.
  • Installed/repaired 3 sewer services, cleaned and videoed approximately 700’ feet of sewer line and inspected 3 sewer connections/installations.
  • Dewatered 0 gallons of digester sludge.Mixed 0 tons of dewatered sludge.Also, hauled 0 tons of dewatered sludge to landfill.
  • Worked with business owners, homeowners, contractors and others to help resolve sewer related issues such as rain water getting into sewer lines, back-ups, video inspection, private line or service locations and damage to lines.
  • Continue monthly sewer easement maintenance. Bush hogging, tree cutting, spraying and debris removal.
  • This month we received NC811 locate request for 47 tickets. These were all marked in a timely manner.
  • Continue monitoring Johnathan Creek and stream banks for fallen and dead trees that could impact the Town’s sewer creek crossings. This is now required by DENR.
  • Removed fallen trees and debris from Jonathan’s Creek on Moody Farm road and off of Valley Creek Drive.
  • Grease in the Towns sewer collection system and in the Waste Water Treatment Plant is an ongoing and time-consuming problem. Regular grease trap pumping and maintenance is the key to keeping these problems to a minimum. All food handling businesses are required to have grease removing equipment installed and to maintain records of cleaning and maintaining their equipment. The sewer department staff regularly inspects this equipment and looks at records and logs of this maintenance. This month we preformed 4 grease trap inspections. Of these 0 were found to be non-compliant. We continue to work with all businesses on their grease issues and provide assistance and education in hopes of reducing the amount of grease in our sewer system.