COB 300, Quiz 5, Fall 2001 (FORM B)
Name:______ID--
On the same Scantron that you used for past quizzes, provide answers to the following questions in answer spaces 29-33.
29.MRP stands for:
A. managerial reporting program
B. management report processor
C. material resources program
D. material requirements planning
E. none of the above
Week Number: / 1 / 2 / 3 / 4Item: X, LFL,
LT=2 weeks
Gross requirements / 25 / 0 / 60 / 45
Scheduled receipts
Projected on hand / 30 / 5 / 5 / 0
Net requirements / --- / --- / 55 / 45
Planned-order receipts / 55 / 45
Planned-order releases / 55 / 45
Consider the following MRP record:
(for questions 30-32)
30.What is (are) the correct planned order releases for item X?
A. 55 in week 1 and 45 in week 2
B. 70 in week 1 and 70 in week 2
C. 70 in week 1
D. 45 in week 2
E. none of the above
31.What is the quantity of “X” expected to be on hand at the beginning of week 3?
A. 55
B. 15
C. 5
D. 0
E. none of the above
32.If “X” is used only in item “A” as follows, A then:
X (1 per)
A. the gross requirements for A are 25, 0, 60, and 45 units in weeks 1 through 4, respectively.
B. the scheduled receipts for A are 25, 0, 60, and 45 units in weeks 1 through 4, respectively.
C. the planned order releases for A are 25, 0, 60, and 45 units in weeks 1 through 4, respectively.
D. the projected on hand balances for A are 25, 0, 60, and 45 units in weeks 1 through 4, respectively.
E. not enough information to answer this question.
33.Which of the following is (are) required pieces of information for processing MRP records?
- Planned order receipts
- Current inventory status (e.g., on-hand balances)
- Lead time information
- B and C are required
- all of the above are required