DEPARTMENT OF BUILDING AND ENGINEERING SERVICES

PROJECT LIST – GABORONE

SR NO / PROJECT DESCRIPTION / START DATE / COMPLETION DATE / EXTENDED COMPLETION DATE / CONTRACT SUM/ESTIMATE / PROJECT STATUS
1 / National Museum Extension – Gaborone - MLHA / 15.02.07 / 26.10.11 / - / P50m / At tender documentation stage. On hold for sourcing fund .
2 / Ramotswa Library Extension -MLHA / 15.10.07 / 30.09.09 / - / P13,941,730.00 / Project on progress at 10%
3 / Mochudi Library Extension -MLHA / 07.10.09 / 31.12.09 / - / P13,613,323.00 / Project called off after tendering due to funds constraints
4 / Office Partitioning at Plot 181 Kgale Mews for Registrar of Companies - MLHA / 01.02.07 / 03.11.08 / 03.04.09 / P9.3m / Practical completion inspection on 07.04.09
5 / Pilane Leather E state -MLHA / 10.10.06 / 04.06.08 / - / P2,215,839.00 / End of defects inspection done.
6 / Madirelo Hotel School In Gaborone -MLHA / 21.11.08 / 18.02.10 / - / P23,099,142.00 / Completed under defects liability
7 / Industrial Court – Gaborone -MLHA / 01.05.09 / 912 days / - / 374M / Mobilization stage
8 / Improvements to First Offenders Prison in Gaborone - MLHA / 03.10.06 / 01.08.07 / - / P17,199,700.00 / Defects liability
9 / District Labour Office in Gaborone - MLHA / 25.01.05 / 24.08.05 / - / P3.6m / Final Account
10 / Gaborone Records Centre -MLHA / 28.01.06 / 13.03.10 / - / P45m / Construction stage
11 / National State Theatre -MLHA / 01.04.08 / 28.02.13 / - / P300m / Design stage
12 / National History Block in Gaborone -MLHA
13 / Integrated Offices and Staff Houses at Mochudi - MLHA / 01.04.07 / 31.12.11 / - / P35m / Design stage
14 / Gaborone Stadium Upgrading -MYSC / 02.08.07 / 30.12.09 / - / P75m / Construction stage
15 / Gaborone High Court of Appeal – Administration of Justice / 01.05.09 / 912 days / - / 374m / Mobilization stage
16 / Broadhurst Magistrate Court Extension – Administration of Justice / - / - / - / P54m / Tender Evaluation Stage
17 / BIAC Auditorium – State President / 09.09.02 / 18.06.04 / TBA / P16.7m / 92% complete, project suspended by Contractor, claiming right of lien. Negations on going on basis of proposal for completion of project received from contractor
18 / BIAC Hostels, Kitchen and Dining Hall – State President / 15.12.03 / 13.12.04 / TBA / P25.2 m / Defects liability period expires on March 09. Extension of time still under adjudication.
19 / IDM New Campus at Gaborone – State President / - / - / - / P240m / Appointment of Consultants.
20 / Forensic Laboratory at Gaborone – State President / - / - / - / P150m / Stage II Design report
21 / Police Station at Mmathubudukwane / - / - / - / P75m / Tender documentation stage
22 / Police Housing at Block 10 Gaborone State President / - / - / - / P45m / Detailed design stage
23 / Police Housing at Mochudi – State President / 18.05.04 / 17.01.06 / 17.08.06 / P26.8m / At close out stage
24 / Refurbishment of the State House – State President / 25.03.08 / 04.03.09 / 30.04.09 / P5.40m / Work in progress. Poor performance by the Contractor. Notice for termination issued on 30.03.09
25 / HIS Housing at Gaborone – MOH / 29.12.08 / 23.04.10 / - / P28,352,981.00 / 12% complete and slow progress
26 / Plant Protection and Quarantine Laboratory at Sebele –MOA / - / - / - / P34m / Under design stage 3 (pre contract stage) constructions is expected to start by October 2009.
27 / Central Mechanical Workshop at Sebele – MOA / 18.07.08 / 18.01.08 / 02.03.09 / P8,769,539.00 / Progress 70%
28 / Animal Genetic Resource Centre at Sebele – MOA / 19.11.07 / 22.09.08 / 21.02.09 / P11,750,332.00 / In defects liability
29 / Prefabricated Office Block and Refurbishment of Conference Room at MOA Headquarters / 18.08.08 / 07.04.09 / - / P4.8m / Prefabricated building was fully occupied in January 2009, Conference Room to be completed by 07.04.09
30 / The Main Research Laboratory at Sebele – MOA / - / - / - / P65m / ITT sent to PPADB for vetting, construction is expected to start October 2009.
31 / Upgrading of Water and Sewerage System at Sebele – MOA / - / - / - / P4.1m / Adjudication has been completed; waiting for fund, construction is expected to start October 2009.
32 / ISPAAD Fifteen Agricultural Service Centres Countrywide – MOA / - / - / - / P137m / These are new projects for 2009/10, twelve sites have been identified for the projects.
33 / Refurbishment of the Red Block Building for Ministry of Agriculture – Gaborone / 18.07.08 / 14.10.09 / - / P8.31M / Progress at &0% and behind schedule
34 / Survey and Mapping Headquarters at Gaborone MLH / 18.07.08 / 14.10.09 / 20.11.09 / P37.14m / Progress at 40% and on schedule
35 / DPP Head Office at Gaborone – MLH / 01.06.09 / 01.06.11 / - / P80.28m / Construction tender evaluation stage
36 / Cooperative Development centre at Sebele - MTI / 01.06.09 / 01.08.10 / - / P66.42m / Construction tender evaluation stage.
37 / Regional Offices for Department of WaterAffairs at Ramotswa –MEWR
38 / Oodi College of Applied Arts and Technology – (MOE) / 04.12.06 / 21.02.09 / - / P192,640,000.00 / Project delayed due to issue of treatment plant but expected to be completed by July 09
39 / GTC/ATTC at Gaborone – MOE / 03.01.08 / 28.03.09 / 04.08.09 / P66,541,314.77 / 82.7% complete
40 / Mogoditshane Senior Secondary School – MOE / April 2009 / August 2010 / - / P440m / Mobilization stage
41 / DVET Housing at Block 5 Gaborone – MOE / - / - / - / P72m / Tender adjudication completed. Awaiting endorsement of CTB Form by the Client
42 / RTC Extension in Gaborone – MWT / - / - / - / P40m / Being tendered, tender closing 08.04.09
43 / SSKA Terminal Building in Gaborone - MWT / 10.06.08 / 11.05.10 / - / P433,193,262.90 / 33% complete as at 01.04.09
44 / SSKA Cargo Building in Gaborone - MWT / 20.02.06 / 29.09.07 / 05.04.08 / P34,514,792.00 / Practical completion was achieved on 09.03.09. Delays were caused solely by the Mechanical Sub-contractor.
45
46
47
48