Humble Monthly Activity Report

Humble Monthly Activity Report

Piney Point Village

Batch # 1 Progress Report

for MAY 2013

BATCH # 1 PAVING & DRAINAGE
IMPROVEMENTS PROJECT

BATCH # 1 PAVING

DRAINAGEIMPROVEMENTS

PROJECT

HARRIS COUNTY, TEXAS

Weekly Progress Report

HDR|Engineering Inc.

Project No.12-022

Week Ending

April 12, 2014

Submitted to

Piney Point City Council

4635 Southwest Freeway, HoustonTX77027-7169

(713) 622-9264. Fax (713) 622-9265.

Page 1 of 8

Piney Point Batch # 1 Paving & Drainage

ImprovementsProject Progress Report for

Week ending April 12, 2014

March 30, 2014 to April 12, 2014Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

MOBILIZATION:

  • This period no work was performed on this aspect of the project.

PAVING ITEMS:

JAMESTOWN ROAD

  • This period no work was performed on this aspect of the project.

CALICO LANE

  • Placed primer coat and Asphalt for Calico.
  • Formed up, placed steel reinforcement and concrete for the driveways on Calico.

Removing the old culvert and concrete driveway on Wendover. View to the west.

JAN KELLY LANE

  • Formed up, placed steel reinforcement and concrete for the driveways on Calico.

GINGHAM DRIVE

  • Formed up, placed steel reinforcement and concrete for the driveways on Calico.

March 30, 2014 to April 12, 2014

Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

PAVING ITEMS: (cont.)

GREEN OAK DRIVE

  • Completed.

DRAINAGE ITEMS: AAA Paving

JAMESTOWN ROAD

  • Placed 24-inch storm pipe between Tynebridge and Jamestown to the back easement running north and south till the contractor ran into a gas.
  • On hold till CenterPoint gas can move their line out of the way.

CALICO LANE

  • Repaired sprinklers.
  • Graded and dress up the ditches.

Placed back one of the dyed concrete driveway on Gingham. View to the West.

March 30, 2014 to April 12, 2014

Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

DRAINAGE ITEMS: AAA Paving(cont.)

JAN KELLY LANE

  • Graded and dress up ditches.

GINGHAM DRIVE

  • Graded and dress up ditches.

WENDOVER LANE

  • Dress up the work site and placed sob grass.

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • Completed.

Placed back one of the dyed stencil concrete driveway on Gingham. View to the southeast.

WATER ITEMS:

JAMESTOWN ROAD

  • The water line on Tynebridge is completed.

March 30, 2014 to April 12, 2014 Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

WATER ITEMS: (cont.)

JAN KELLY LANE

  • Completed.

CALICO LANE

  • None required

GINGHAM DRIVE

  • None required

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • None required

WENDOVER LANE

  • None required

TREE PROTECTION:

JAMESTOWN ROAD

  • This period no work was performed on this aspect of the project at this time.

CALICO LANE

  • This period no work was performed on this aspect of the project at this time.

JAN KELLY LANE

  • This period no work was performed on this aspect of the project at this time.

GINGHAM DRIVE

  • This period no work was performed on this aspect of the project at this time.

March 30, 2014 to April 12, 2014 Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

TREE PROTECTION: (cont.)

WENDOVER LANE

  • Removed the tree protective fencing.

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • Completed

Stenciling one of the dyed concrete driveways on Jan Kelly. View to the east.

SUPPLEMENTAL ITEMS:

JAMESTOWN ROAD

  • This period no work was performed on this aspect of the project.

CALICO LANE

  • This period no work was performed on this aspect of the project.

JAN KELLY LANE

  • This period no work was performed on this aspect of the project.

March 30, 2014 to April 12, 2014

Activity/Status

Batch # 1 Paving & Drainage IMPROVEMENTS

SUPPLEMENTAL ITEMS: (cont.)

GINGHAM DRIVE

  • This period no work was performed on this aspect of the project.

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • Completed

Placing concrete for one of the driveways on Gingham. View to the southwest.

Placing back one of the sidewalks on Gingham. View to thesoutheast.

Next Week’s Planned Activities

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

MOBILIZATION:

  • This period no work was performed on this aspect of the project.

PAVING ITEMS: AAA Paving

JAMESTOWN ROAD

  • This period no work was is planned on this aspect of the project.

CALICO LANE

  • Placement for the sod grass weather permitting.

JAN KELLY LANE

  • Placement for the sod grass weather permitting.

GINGHAM DRIVE

  • Placement for the sod grass weather permitting.

GREEN OAK DRIVE

  • Completed

WENDOVER

  • Placement for the sod grass weather permitting.

DRAINAGE ITEMS: AAA Paving

JAMESTOWN ROAD

  • On hold.

CALICO LANE

  • Completed.

Next Week’s Planned Activities

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

Clean and dress up the south side of Calico after the asphalt has been placed. View to the west.

DRAINAGE ITEMS: AAA Paving (cont.)

JAN KELLY LANE

  • Completed

GINGHAM DRIVE

  • Completed

WENDOVER LANE

  • Dressing up the area and complete the placement of the sod grass.

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • Completed

Next Week’s Planned Activities

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

WATER ITEMS:

JAMESTOWN ROAD

  • This period no work is planned on this aspect of the project.

CALICO LANE

  • None required

JAN KELLY LANE

  • Completed

GINGHAM DRIVE

  • None required

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • None required

TREE PROTECTION:

JAMESTOWN ROAD

  • This period no work is planned on this aspect of the project.

CALICO LANE

  • This period no work is planned on this aspect of the project.

JAN KELLY LANE

  • This period no work is planned on this aspect of the project.

GINGHAM DRIVE

  • This period no work is planned on this aspect of the project.

Next Week’s Planned Activities (cont.)

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

TREE PROTECTION: (cont.)

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • Completed.
SUPPLEMENTAL ITEMS:

JAMESTOWN ROAD

  • This period no work is planned on this aspect of the project.

CALICO LANE

  • This period no work is planned on this aspect of the project.

JAN KELLY LANE

  • This period no work is planned on this aspect of the project.

GINGHAM DRIVE

  • This period no work is planned on this aspect of the project

GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL

  • This period no work is planned on this aspect of the project.

Next Week’s Planned Activities (cont.)

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

Laid out to cut the old asphalt for tying in the new pavement view to the east.

Placed concrete back on a Wendover driveway. View to the north.

Next Week’s Planned Activities (cont.)

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

Placed concrete for the driveways on Wendover. View to the north.

Graded the ditch out at Jan Kelly and Calico. View to the south

Next Week’s Planned Activities (cont.)

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

View of the regarding of the ditches on Calico after the asphalt placement had been placed. removed from the drain line running between Tynebridge and Jamestown. View to the east.

Next Week’s Planned Activities (cont.)

April 13, 2014 to April 19, 2014

Batch # 1 Paving & Drainage IMPROVEMENTS

View of the regarding of the ditches on Calico after the asphalt placement had been placed. removed from the drain line running between Tynebridge and Jamestown. View to the east.

Page 1 of 8