Highway Renewal Projects

Highway Renewal Projects

HIGHWAY RENEWAL PROJECTS

The following is a list of road and bridge capital projects planned to be undertaken in 2012-13.

Northern/Remote

Continue construction of the all-weather road on the east side of Lake Winnipeg

Pave 18km of PTH 6 north of Devils Lake

Grade widen and pave 23km of PTH 6 south of Grand Rapids including drainage improvements

Pave 26km of PTH 6 north of Grand Rapids

Grade widen and gravel shoulder of 30km of PTH 10 north of The Pas

Continue grade approximately 174km of PR 280, cost-shared with Manitoba Hydro

Replace the structure on PR 287 at Cormorant Lake Narrows near Cormorant

Complete the grade and gravelling of nine km of PR 373 north of Norway House

Complete grade and paving of 51km of PR 373 north of Sea Falls

Continue paving 15km of PR 373 north of Jenpeg

Continue paving seven km of PR 374 southwest of Cross Lake

Continue paving 16km of PR 374 from Kichi Sipi Bridge to Cross Lake

Grade five km of PR 384 (Moose Lake Road) near Lobstick Creek

Improve grade on various locations of PR 391

Capital Region

Continue construction of structures and roadworks for CentrePort Canada Way

Pave 7.5km of PTH 6 south of Grosse Isle

Make intersection improvements on PTH 15 at PR 206

Make intersection and safety improvements on the Perimeter Highway

Improve illumination on the Perimeter Highway at St. Mary’s Road

Rehabilitate structure at east interchange of PTH 1 on the Perimeter Highway

Commence structure rehabilitation on the Perimeter Highway at PTH 75

...2

- 2 -

Western Manitoba

Complete minor structure rehabilitation on PTH 1 at the Assiniboine River

Construct a three-kilometre service road in Brandon parallel to PTH 1

Pave three km of shoulders of PTH 1 east of Douglas

Pave 18km of PTH 1 west of Sidney

Replace structure on PTH 2 at Jackson Creek west of Sinclair

Pave 12km of PTH 2 between Sinclair and Reston

Pave 22km of PTH 10 north of Minto

Continue reconstruction of PTH 10 north of Brandon

Pave 24km of PTH 16 east of Gladstone and 18km between Binscarth and Foxwarren

Replace structure on PTH 34 at Gillespie Drain south of Gladstone

Continue construction of PTH 110, the Brandon east access

Rehabilitate structure on PR 250 at Assiniboine River north of Alexander

Pave remaining 10km of PR 340 between Wawanesa and Shilo

Eastern Manitoba

Rehabilitate structure on PTH 1 at Birch River (east of Prawda)

Pave eight km of PTH 1 between MacGregor and Bagot

Pave 10km of PTH 1 through Portage la Prairie

Rehabilitate structure on PTH 1 at Assiniboine River east of Portage la Prairie

Replace structure on PTH 2 at Codner Drain near Starbuck

Pave 13km of PTH 11 near McArthur Falls

Rehabilitate structure on PTH 11 at Powerview Creek near Pine Falls

Commence structure replacement on PTH 12 at Rat River Diversion southwest of Zhoda

Rehabilitate structure on PTH 23 east of Morris at the Red River

Pave 15km of PTH 59 between PTH 52 and PR 210

Continue reconstruction of PTH 75 in the town of Morris and intersection improvements at the U.S. border

Rehabilitate structure on PR 207 at the Cordite Drain north of PTH 15

Pave 16km of PR 207 from PR 206 to PTH 1 through Lorette

...3

- 3 -

Complete paving of PR 210 from Ste. Anne to Landmark

Rehabilitate structure on PR 211 at Winnipeg River west of Pinawa

Pave two km of PR 216 between New Bothwell and PR 311

Grade and gravel various locations of PR 304 between Manigotagan and Wallace Lake

Pave various locations of PR 311 between PR 200 and PTH 12

Grade and gravel various locations of PR 315 between PR 313 and the Ontario boundary

Interlake

Replace structure on PTH 6 at Burnt Lake Drain north of Lundar

Complete rehabilitation of fivekm of PTH 9 between PTH 44 and Craig Avenue in Selkirk

Pave 20km of PTH 68 east of Lake Manitoba Narrows

Make intersection improvements on PTH 68 at West Vogar Access

Make minor structure repairs on PR 204 at Red River near Selkirk

Pave 10km of PR 232 south of Winnipeg Beach

Pave 10km of PR 233 north of PTH 68 near Arborg

Pave the Gimli access road

Parklands

Pave 14km of PTH 5 north of Riding Mountain to Norgate

Pave 10km of PTH 5 south of McCreary

Replace structure on PTH 5 at Turtle River near Laurier

Rehabilitate structure on PTH 10 at Bowsman River north of Bowsman

Complete intersection improvements on PTH 20A in Dauphin at Mountain Road

Continue reconstruction of 20km of PTH 83 north of San Clara

Pave 15km of PR 269 east of Fork River

Complete paving of PR 483 to Pelican Rapids

Replace structureon PR 489 at the tributary of the Garland River south of Duck River

Grade twokm of PR 588 west of Swan River

...4

- 4 -

FLOOD REPAIR PROJECTS

Damaged Infrastructure Substantially Completed

HwyLocationDescription of Work

1Assiniboine River Diversion west of Portage, east bankStructure rehabilitation

1Assiniboine River Diversion west of Portage, west bankStructure rehabilitation

1At the Assiniboine River, Grand Valley (east bank)Structure rehabilitation

1At PR 459, Grand Valley (east bank)Structure rehabilitation

22.1km west of the PTH 22 junctionSlope stabilization

3One km east of the Saskatchewan boundaryMinor culvert rehabilitation

30.6 km east of east junction of PTH 83Minor culvert rehabilitation

53.2 km north of the north junction of PR 265Culvert replacement

5At Wilson RiverSlope stabilization

5At the Assiniboine RiverStructure rehabilitation

66.4 km north of PR 227Minor culvert rehabilitation

812.8km north of RivertonMinor culvert rehabilitation

10In the vicinity of Minnedosa, 0.8km west of PR 355Slope stabilization

10One km north of the U.S. borderMinor culvert rehabilitation

10NE 15-36-26WMinor culvert rehabilitation

10In the vicinity of the Pioneer elevatorMinor culvert rehabilitation

10One km south of Smith CreekSpot road improvements

104.7 km south of MafekingMinor drainage improvements

10MafekingSpot road improvements

16At theAssiniboine River (west of Russell)Structure rehabilitation

17One km west of PTH 8Minor culvert rehabilitation

17PR 233 -PR 224Minor culvert rehabilitation

171.6 km west of PTH 7 - 4.6km westMinor culvert rehabilitation

186.7 km north of the U.S. borderCulvert replacement

20North of PR 271Spot road improvements

2015 km east of PR 271Minor culvert rehabilitation

21Three km north of the east junction with PTH 2Slope stabilization

...5

- 5 -

HwyLocationDescription of Work

2110.4 km north of PTH 2Minor drainage improvements

21North of HartneyAcquisition of right-of-way

22At the Souris RiverStructure rehabilitation

23Lizzie Avenue in Morris, PR 246Spot road improvements

23PR 422 - west dike, MorrisSpot road improvements

23At PTH 21Spot road improvements

232.3 km west of PTH 5Culvert replacement

24The east junction with PR 264Spot road improvements

266.6km east of PR 430 -PR 248Spot road improvements

34At the Pembina River BridgeSpot road improvements

3417.6 km north of PTH 1Spot road improvements

34At the Assiniboine River, north of HollandStructure

411.3 km north of PR 571Spot road improvements

59At Road 25NMinor culvert replacement

677.5 km east of PTH 6 -5.4 km eastSpot road improvements

68Six km east of Lake Manitoba NarrowsGrading, flood protection

75Two km south of PR 246 (St. Jean Baptiste), MorrisSpot road improvements

75Morris River -PR 205 (north- and southbound lanes)Spot road improvements

75Morris River - 10 km north of the river (service roads)Spot road improvements

75Three km south of PR 246 (service roads)Spot road improvements

75Two km north of north junction of PTH 23 to five km northShoulder rehabilitation

83At Municipal Road 210 NMinor culvert rehabilitation

83At Minnewasta CreekCulvert replacement

110Victoria Avenue -PR 457Grading

200Emerson - four km north of EmersonSpot road improvements

200PR 311 -St. AdolpheSpot road improvements

200PR 210 - the Floodway bridgeSpot road improvements

201Three km east of Roseau River First NationSpot road improvements

201PTH 50 -PR 209Spot road improvements

...6

- 6 -

HwyLocationDescription of Work

20113.6km east of PR 242Spot road improvements

205Morris River Bridge -PR 422Spot road improvements

210St. Adolphe - three km east of PR 200Spot road improvements

217PR 246 - three km east of PR 200Grade reconstruction

222Two km north of HnausaMinor culvert rehabilitation

231At Gimli yardMinor culvert rehabilitation

233One km south of PR 325Spot road improvements

240PR 240, eight km south of PR 245Spot road improvements

2401.6 km north of PTH 1 - Delta BeachSpot road improvements

240One km south of PTH 23Culvert replacement

242At PR 242 (north of Westborne)Spot road improvements

242North of the junction with PR 242 - Lynchs PointSpot road improvements

242At Westbourne drainMinor culvert rehabilitation

243PTH 75 - the RM boundarySpot road improvements

2450.02 km east of PR 342Minor culvert rehabilitation

246Two km north of PR 205 - PTH 23Spot road improvements

246PTH 75 (St. Jean Baptiste) - five km south of PTH 23Spot road improvements

2476.4 km east of PR 332Minor culvert rehabilitation

247West of PTH 75Spot road improvements

248PR 227 - PTH 6Culvert replacement

2500.5km south of Assiniboine river - 0.5 km north of riverGrading

2525.5 km north of PTH 3Minor culvert rehabilitation

2534.5 km east of PTH 18Culvert replacement

253At nine km east of the north junction with PR 458Minor culvert rehabilitation

2544.6 km north of PTH 2Spot road improvements

254Three km north of PR 345Spot road improvements

2543.6 km north of PTH 1Spot road improvements

25410 km south of PTH 3 and PR 254Minor culvert rehabilitation

...7

- 7 -

HwyLocationDescription of Work

254Eight km south of PTH 3Minor drainage Improvements

2560.2km north of the U.S. BorderMinor culvert rehabilitation

257At Scallion Creek (Virden)Minor structure rehabilitation

259At the Assiniboine River, 4.4 km east of the CPR lineGrading

259At the Assiniboine River flood relief structureMinor structure rehabilitation

2644.2km south of PTH 42Spot road improvements

26410.7km south of PTH 42Minor culvert rehabilitation

265East of Plumas - PTH 50Culvert replacement

2668.5 km south of PR 268Minor culvert rehabilitation

268At Birch RiverMinor culvert replacement

268Birch River - Woody RiverSpot road improvements

268NE corner 22-39-25WCulvert replacement

271NE 34-32-20WMinor culvert rehabilitation

271Two km west of PTH 20Spot road improvements

2710.3km west of PR 489Spot road improvements

272In the vicinity of Duck BayGrading

274Ranch Creek, 29.7km southwest of east junction, PTH 5Spot road improvements

275North of 19-36-27WMinor culvert rehabilitation

2765.0 km north of Ste Rose - seven km south of PR 328Surfacing, road repairs

27820.5 km north of PTH 50Culvert replacement

305At the flood relief channelStructure rehabilitation

305At the Assiniboine RiverStructure rehabilitation

31720.5 km west of PTH 12Culvert replacement

320Various locationsSpot road improvements

3234.8 km west of PR 236Spot road improvements

3230.5 km west of PR 322Spot road improvements

324At PR 222Minor culvert rehabilitation

3255.6 km west of PTH 17Spot road improvements

...8

- 8 -

HwyLocationDescription of Work

3293.2km east of the junction with PR 326Minor culvert rehabilitation

330PTH 75 - PR 205Spot road improvements

331At Hoop and Holler BendGrade reconstruction

331Hoop and Holler CutSpot road improvements

332At Tobacco Creek in the vicinity of Lowe FarmAcquisition of right-of-Way

334One km south of PTH 2Minor culvert rehabilitation

3386.9km north of PR 245 - PR 305Minor culvert rehabilitation

340At Black Creek (north of Wawanesa)Structure

341At 0.7km and 11.1km east of PTH 10Minor culvert rehabilitation

34115.5 km east of PTH 10Minor culvert rehabilitation

342At 8.6 km north of PTH 23Culvert replacement

3420.7 km south of PR 245Culvert replacement

3423.6 km north of PTH 23Culvert replacement

34517.6 km east of PTH 83Grading

34616.3 km north of PTH 3Culvert replacement

3474.1 km west of PTH 22Spot road improvements

348West of BrandonBridge removal

350Four km south of MacGregorSpot road improvements

35215.2 km north of PTH 16Minor culvert rehabilitation

36411.2 km west of PR 481 - 11.7 km west of PR 481Spot road improvements

366At Municipal Road 151 WMinor culvert rehabilitation

366NE corner 33-38-26WMinor culvert rehabilitation

366In the vicinity of Elk Lake, 3.2 km south of PR 367Minor culvert rehabilitation

367Five km east of theShell River BridgeMinor culvert rehabilitation

367South of the Shell River BridgeSpot road improvements

415Four km north of PR 322Spot road improvements

419Four km west of PTH 17Spot road improvements

430One km north of PTH 1 - PTH 26Grading

430At the Assiniboine River (northeast of Portage la Prairie)Structure

...9

- 9 -

HwyLocationDescription of Work

45010.6 km north of the U.S. borderMinor drainage improvements

452Seven km east of PTH 83Spot road improvements

453PTH 10 - PR 340Spot road improvements

4570.5 km east of PTH 1A - 2.5 km east of PTH 1ASpot road improvements

4580.7 km north of PTH 3Minor culvert rehabilitation

4582.9 km north of PTH 3Slope stabilization

459PTH 1 - PTH 10Grading

4621.6 km north of PR 265Minor culvert rehabilitation

467One km west of PTH 83Spot road improvements

4786.5 km south of PTH 45Culvert replacement

485Various locations (south of 23 and 24-35-26W)Minor culvert rehabilitation

485At West Favel RiverSlope stabilization

486Various Locations (north of 16 and 17-34-28W)Minor culvert rehabilitation

488In the vicinity of Minitonas Creek (south of 33-34-27W)Minor culvert rehabilitation

488NE 1-36-27WMinor culvert rehabilitation

489PR 271 - PTH 20 (various locations)Spot road improvement

489NE 8-34-20WSpot road improvements

513Three km west of Frenchman’s Rapids - two km eastGrading

518PTH 6 - five km north of PTH 6Grade and gravel

5181.6km south of PR 415Spot road improvements

530At the Souris River (Treesbank)Bridge removal

549West of the Shellmouth DamSpot road improvements

569One km east of PTH 50 - 2.6km east of PTH 50Minor culvert rehabilitation

57914.5 km west of PTH 16Spot road improvements

583At the Shell RiverStructure rehabilitation

588South of Trout Creek (west of 18-37-28W)Slope stabilization

606In the vicinity of Bethan, 0.5km south of PR 471Spot road improvements

611Fairford Access RoadGrading

620Eden AccessGrading

...10

- 10 -

HwyLocationDescription of Work

6280.5km south of PR 251Culvert replacement

633MacGregor AccessSpot road improvements

646At four km west of PTH 10Minor culvert rehabilitation

650Riverside AccessSpot road improvements

800Hanks Main Market Road (detour for PR 416)Spot road improvements

800Polson Main Market - 1.6 km north of PR 229Spot road improvements

800Silver Main Market - five km west of PTH 17Spot road improvements

800Sumka Main Market - 1.5 km west of PTH 7Spot road improvements

800Thomchuk Main Market - 2.5 km north of PR 231Spot road improvements

800Fraserwood Main Market , 0.8 km west of PTH 7Spot road improvements

800Malonton Main Market, 0.8 km east of PTH 7Spot road improvements

800Meleb Main Market, 1.6km east of PTH 7Spot road improvements

800Narcisse West Main Market, 16 km west of PTH 17Spot road improvements

800Fairford MMR, nine km east of PTH 6 - one km eastSpot road improvements

PR 355 - Main Street (Minnedosa)Spot road improvements

Work Identified for Completion

Eastern Region

150.2 km east of Brokenhead RiverCulvert replacement

75Morris - Plum River BridgeSpot road improvements

217Red River - One km eastSpot road improvements

246Plum River - 0.5 km southSpot road improvements

631Pembina Trail, Bourret Street - 0.4 km southSpot road improvements

South-Central Region

13One km south of Elm CreekSpot road improvements

16Gladstone, PR 260 - Whitemud RiverCulvert replacement

227At the Assiniboine River DiversionStructure rehabilitation

229three km east of the regional boundaryGrading

240At the Assiniboine River (south of Portage la Prairie)Structure

...11

- 11 -

HwyLocationDescription of Work

242At Lynchs PointGrading

242At the Assiniboine River (southwest of Portage la Prairie)Structure

248At the Assiniboine River (Baie St. Paul)Structure

331Hoop and Holler Curve - PTH 13Grading

332At Tobacco Creek, in the vicinity of Lowe FarmReplacement of timber Bridge

415PR 518 - 13 km east of PR 518Grading

518North of PTH 6 - PR 415Grading

800At the Assiniboine River Diversion, Road 71NStructure rehabilitation

Southwestern Region

11.1 km east of PTH 1Slope stabilization

1At the Assiniboine River, Grand Valley (west bank)Structure rehabilitation

1At PR 459, Grand Valley (west bank)Structure rehabilitation

2At the Souris River (Wawanesa)Structure rehabilitation

3At seven km east of PTH 83Spot road improvements

3Two km east of the junction with PR 458Spot road improvements

30.8km east of the east junction with PTH 5Spot road improvements

3At the Souris RiverStructure rehabilitation

5One km north of the north junction with PR 265 Culvert replacement

59.1 km north of PTH 2 - 2.6 km north of Assiniboine RiverGrade reconstruction

5Various locationsGrading

10Assiniboine River - 0.2 km north of PR 459Spot road improvements

10At Little Saskatchewan River Valley (near Minnedosa)Spot road improvements

10At the Souris RiverStructure rehabilitation

160.6 km east of Road 85W (near Neepawa)Minor culvert rehabilitation

186.2 km north of PTH 3Culvert jacking

218.0 km north of PTH 23Grade construction

217.5 km north of PTH 1Grade reconstruction

2113.3 km north of the east junction with PTH 2Slope stabilization

...12

- 12 -

HwyLocationDescription of work

210.45 km north of the junction with PR 355Slope stabilization

21At the Souris River (Hartney)Structure rehabilitation

22At the Souris RiverGuardrail replacement

231.6km west of the junction with PTH 18Slope stabilization

24One km west of PR 270Minor culvert rehabilitation

412.1 km south of PTH 42Bit pavement/shoulder gravel

41At the Assiniboine River (south of St-Lazare)Structure rehabilitation

451.8 km west of PR 270 at North Jackfish LakeGrade reconstruction

451.6 km east of PR 354Culvert jacking

83At the Assiniboine River (south of Miniota)Drainage improvements

837.5 km north of PTH 1Culvert replacement

8313.1 km north of the junction with PTH 1Culvert replacement

2504.5 km north of PTH 1Slope stabilization

250In the vicinity of Sandy LakeCulvert replacement

251At the Souris River (Coulter)Structure rehabilitation

254At the Souris RiverStructure rehabilitation

262Various locationsCulvert replacement

265Various locations (in the vicinity of Eden)Culvert replacement

27010 km south of PTH 45 - 8.3km south of PTH 45Minor culvert rehabilitation

2700.2 km south of PTH 24 (Rapid City)Culvert replacement

2708.3 km north of PTH 16Grading

3405.2 km north of the junction with PTH 2Spot road improvements

340At SourisStructure rehabilitation

3421.7 km south of PR 253Grade reconstruction

345At the Souris RiverStructure rehabilitation

346One km north of the junction with PTH 23Slope stabilization

346At the Souris RiverStructure rehabilitation

347At Elgin Creek, east branchMinor structure rehabilitation

...13

- 13 -

HwyLocationDescription of work

347At Elgin Creek, west branchMinor structure rehabilitation

347At the Souris RiverStructure rehabilitation

352Various locations (in the vicinity of Edrans)Culvert replacement

354In the vicinity of OnanoleSpot road improvements

355MinnedosaSpot road improvements

4407.1 km north of PR 253Spot road improvements

452At the Souris RiverStructure rehabilitation

453At Mile CreekMinor structure rehabilitation

455One km east of PTH 21Slope stabilization

464One km north of PR 353 (SE 35-12-16W)Spot road improvements

464At 0.2km north of Road 82N Spot road improvements

465At 0.5 km east of Road 95W Spot road improvements

465PR 262 - PR 466 (various locations)Culvert replacement

466At the PR 465 junction - PTH 16Minor culvert replacement

4701.6 km west of PR 354 - 4.8 km west of PR 354Culvert replacement

471In the vicinity of Bethany and EdenCulvert replacement

4763.2 km north of PTH 16Spot road improvements

478At the Assiniboine River (west of Binscarth)Structure rehabilitation

54210.1 km north of the junction with PR 257Minor culvert rehabilitation

5791.7 km north of PR 478Spot road improvements

5794.8 km west of PTH 16Spot road improvements

579At the Assiniboine River (in the vicinity of Millwood)Structure rehabilitation

6700.6 km east of PTH 42 (town of Shoal Lake)Spot road improvements

8000.3 km east of PR 354 and one km north of PR 470 Culvert replacement

800At the Qu’Appelle River (old PTH 41)Structure rehabilitation

1AAssiniboine River -PR 457Grading

...14

- 14 -

West-Central Region

HwyLocationDescription of work

10At the West Favel RiverSlope stabilization

6829 km east of Lake Manitoba NarrowsGrading, flood protection

239Steeprock - PTH 6 (various locations)Bituminous levelling

417In the vicinity of Lake Manitoba First NationGrading, flood protection

481In the vicinity of Crane River First Nation (FN)Grading, flood protection

4853.6 km south of PR 366Minor culvert rehabilitation

5123.3 km southeast of PTH 68Grade reconstruction

513Six km east of Gypsumville - 16 km west of Dauphin FNConstruct winter road

513PTH 6 - Dauphin RiverGrading

643St. Laurent access (various locations)Bituminous levelling