LOCAL 475 TRAINING CENTER

CRANE RIGGING & SIGNALING TEST

NAME :MEMBER #:

MULTIPLE CHOICE

  1. Identify the crane signal.

A.raise the load

B.lower the load

C.lower the boom

D.raise the boom

ANSWER:

  1. Identify the crane signal.

A.dog everything

B.lower the boom

C.move slowly

D.lower the boom & hold the load

ANSWER:

  1. Identify the crane signal.

A.swing

B.stop

C.lower boom

D.lower boom slowly

ANSWER:

  1. Identify the crane signal.

A.swing

B.stop

C.swing left

D.emergency stop

ANSWER:

  1. Identify the crane signal.

A.swing

B.swing out right

C.swing out left

D.none of the above

ANSWER:

  1. Identify the crane signal.

A.secure clasp

B.dog everything

C.travel

D.move slow

ANSWER:

  1. Identify the crane signal.

A.turn load clockwise

B.wrap it up

C.up slowly with load

D.boom up hold load

ANSWER:

8.Identify the crane signal.

A.travel ( both tracks )

B.swing

C.use wipe line

D.extend boom

ANSWER:

  1. Identify the crane signal.

A.move left

B.stop

C.emergency stop

D.travel away

ANSWER:

  1. Identify the crane signal.

A.up with the load

B.down with the load

C.boom up and hold the load

D.boom up raise load

ANSWER:

  1. Identify the crane signal.

A.up with the load

B.turn around 360º

C.dog everything

D.doom up

ANSWER:

  1. Identify the crane signal.

A.raise load

B.hold load still

C.boom up

D.boom up, hold the load

ANSWER:

  1. Identify the crane signal.

A.dog it off

B.dog off everything

C.extend boom

D.retract boom

ANSWER:

14.Whenever you have to change your pick or place your load on the ground or floor, you should place something under it in the trade we call this:

A.dunnage or cribbing

B.a softener

C.cinder blocks

D.all of the above

ANSWER:

15.When making a lift and your out of sight of object, you will need:

A.a couple of big mirrors

B.another person and / or walkie talkie

C.to send up smoke signals

D.another crane

ANSWER:

16.Dog everything means:

A.emergency stop and move crane

B.lock and secure load where it is and wait for further signal

C.there are dogs running around the load and could interfere with the rigging

operation and cause problems

D.the total weight of all the suspended rigging

ANSWER:

17.A jib on a crane is:

A.a terminal fitting to which mesh is attached

B.a pole held in place with guy lines

C.a beam arrangement suspended from overhead

D.an extension attached to the boom point to provide added boom length

ANSWER:

18.When someone asks you to get rollers you should:

A.go home and get your skates

B.get long pieces of hardwood or pipe to help move heavy equipment along

Flat surface

C.get teflon coated PVC sch, 80 pipe

D.all of the above

ANSWER:

19.When rigging you should:

A.get the job done as fast as possible because the crane is very expensive

B.always wear your sony walkman so the noise from crane won’t bother you

C.think safety and act safely

D.never use gloves

ANSWER:

20.The definition of shackle is:

A.two square knots and a bowline tied together

B.a length of wire rope with an eye at each end

C.the wrapping at the end of a rope with wire or cord to keep the strands and

lay of rope in place

D.a U shaped piece of metal with a bolt or pin through the end

ANSWER:

21.What is the number to the following name. ( Jib Section )

A.6

B.3

C.10

D.5

ANSWER:

22.What is the number to the following name. ( Outriggers )

A.9

B.2

C.1

D.4

ANSWER:

23.What is the number to the following name. ( Main Hoist Line )

A.8

B.7

C.11

D.4

ANSWER:

24.What is the number to the following name. ( Counter Weight )

A.1

B.3

C.2

D.5

ANSWER:

25.What is the number to the following name. ( Live Mast )

A.5

B.10

C.6

D.4

ANSWER:

When you have completed the test

Email your answers to

Passing grade of 75

Your card will be sent or picked up at Training Center