I.ANANTH KUMAR

Address for Communication

Wireless+91-9944527700

+91-9629440629

Key Experience

Senior Planning Engineer with Eight plus (8+) years experience in the field of planning and project management, having a vast experience of working on commercial, airport, residential and Oil & Gas projects.
An experienced professional specialized in engineering management, well known with planning and scheduling, Delay analysis & claims, cost control, contract and project management.

Proficient in Project management software like Primavera Project Planner P3, P6v8.1, Project Execution/Procurement/Monitoring and Control Scheduling techniques using Primavera, Project Measurement system, KPI etc.,

EDUCATIONAL QUALIFICATION

MBA

MajorProject Management

University Alagappa UniversityIndia

BEng

Major CivilEngineering

University Dundee University – Scotland UK

Diploma

Major Electrical Engineering

University T.N.D.T.E (Anna University)

India

Skills:

  • Primavera P3,P5,P6,P6v7,P6V8.3
  • MSPROJECT 2007,2010
  • MAXIMO

Experience

Atpresent Bouygues Batiment International (Top 7th Construction Company in the world) - Qatar

Period:From June 2013 to Present

Details of works:Planning & Scheduling

Position:Sr.Planning Engineer

Projects Details:

Construction of QP District (QR 5.6 Billion).1.54Billion US$,

(9 Office Towers (17 to 47 levels), Hotel, Elevated Car Park, Auditorium, Energy Centre etc)

Duties & Responsibility:

  • Develops project schedules.
  • Project scheduling and execution planning.
  • Prepare the project bar chart, S-curve etc.
  • Integrates project budget and schedule to forecast cash flow requirements
  • Prepare critical path in the project plan and follow up closely
  • Prepare weekly project report, Monthly management report
  • Conduct weekly project meeting with project teams and circulate MOM
  • Update the project status regularly
  • Prepare time impact report base on CPM. Identify delay
  • Identify the project risk in advance and inform management

2 Yr in Aktins - Faithful+Gould (A world Leading Project Mgmt Consultancy)

Period:From June 2011 to June 2013

Details of works:Planning & Scheduling

Position:Sr.Planning Engineer

Projects Details:

Construction of KAIA International Airport KSA value (7.5Billion US$)

Duties & Responsibility:

  • Develops project schedules.
  • Project scheduling and execution planning.
  • Prepare the project bar chart, S-curve etc.
  • Integrates project budget and schedule to forecast cash flow requirements
  • Prepare critical path in the project plan and follow up closely
  • Prepare weekly project report, Monthly management report
  • Review and analysis EOT request by Contractor base on impact to critical path
  • Advise Planning Manager on any issue and potential delay of the project
  • Update the project status regularly
  • Present to Client on the overall working of the programme and the critical path

2Yr in Galfar- Oman.

Period: From July 2009to May 2011

Details of works: Planning & Scheduling

Position:Project Control EngineerSr.Planner

Projects Details:(Minister of Oman- Govt Projects)

  • Construction of Star Hotels (Azaiba Hotel ,SPA AL-Bustan Hotel & Duqm Beach Hotel)
  • Construction of National Heart Centre at Royal Hospital (65 Million US$)
  • EPC Harweel Cluster Phase II Facilities (256 Million OMR)- PETROFAC

(The Project Involves Detailed Engineering, Procurement and Construction for a New Oil and Gas Processing Station and Associated Facilities Including Well Head Works, Oil and Gas Pipelines, Electrical Transmission lines etc.for a Capacity of 10,000 cu.m / day of Oil Production)

Duties & Responsibility:

  • Handling multiple projects.
  • Develops project schedules.
  • Project scheduling and execution planning.
  • Prepare the project bar chart, S-curve etc.
  • Integrates project budget and schedule to forecast cash flow requirements
  • Prepare critical path in the project plan and follow up closely
  • Prepare weekly project report, Monthly management report
  • Update the project status regularly
  • Identify the project risk in advance and inform management

1 Yrs in Etisalat - UAE

Period: From May 2008 up to June 2009

Details of works: Planning & Scheduling

Position: Planning Engineer

Duties & Responsibility:

  • Develop & Maintain the Project Planning, Scheduling & monitoring the Project activities by Using Primavera Project Planner for Enterprise P6.0 Software.
  • Generate S- Curves and histogram for Manpower and cash flow
  • Project Coordination with Our Client & Internal Various Departments includes Engineering , Procurement, Construction, Workshop Fabrication yard , Vendors & Suppliers
  • Study of Engineering drawings and technical specifications
  • Define the WBS Levels & Activity code Levels for having effective control over the Project

3Yrs of Experience in Kier Group, Scotland, UK

Period: From Jun 2005 up to May 2008

Position: Site Engineer.

Details of works: Power plant Operations

  • Directs and supervises of construction Activities,
  • Preparing Work Orders and passes them to Foreman for execution.
  • Preparing Bar Bending Schedule
  • Quotation Preparation. Contractor Co-ordination

PERSONAL SKILLS:

Confident in my work, comprehensive problem solving abilities, thinking creatively, excellent verbal and written communication skills, ability to deal with people diplomatically, willingness to learn team facilitator.

PERSONAL PROFILE

NameI. Ananth Kumar

Date of Birth 16\03\1986

Father’s NameB.Ilangovan

NationalityIndian

ReligionHindu

Passport No K9609514

Driving Licenses International (Qatar)

DECLARATION

I here by declare that the above-mentioned statements are true and correct

Place:

Date:(I. Ananth Kumar)