Piney Point Village
Batch # 1 Progress Report
for MAY 2013
BATCH # 1 PAVING & DRAINAGE
IMPROVEMENTS PROJECT
BATCH # 1 PAVING
DRAINAGEIMPROVEMENTS
PROJECT
HARRIS COUNTY, TEXAS
Weekly Progress Report
HDR|Engineering Inc.
Project No.12-022
Week Ending
April 12, 2014
Submitted to
Piney Point City Council
4635 Southwest Freeway, HoustonTX77027-7169
(713) 622-9264. Fax (713) 622-9265.
Page 1 of 8
Piney Point Batch # 1 Paving & Drainage
ImprovementsProject Progress Report for
Week ending April 12, 2014
March 30, 2014 to April 12, 2014Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
MOBILIZATION:
- This period no work was performed on this aspect of the project.
PAVING ITEMS:
JAMESTOWN ROAD
- This period no work was performed on this aspect of the project.
CALICO LANE
- Placed primer coat and Asphalt for Calico.
- Formed up, placed steel reinforcement and concrete for the driveways on Calico.
Removing the old culvert and concrete driveway on Wendover. View to the west.
JAN KELLY LANE
- Formed up, placed steel reinforcement and concrete for the driveways on Calico.
GINGHAM DRIVE
- Formed up, placed steel reinforcement and concrete for the driveways on Calico.
March 30, 2014 to April 12, 2014
Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
PAVING ITEMS: (cont.)
GREEN OAK DRIVE
- Completed.
DRAINAGE ITEMS: AAA Paving
JAMESTOWN ROAD
- Placed 24-inch storm pipe between Tynebridge and Jamestown to the back easement running north and south till the contractor ran into a gas.
- On hold till CenterPoint gas can move their line out of the way.
CALICO LANE
- Repaired sprinklers.
- Graded and dress up the ditches.
Placed back one of the dyed concrete driveway on Gingham. View to the West.
March 30, 2014 to April 12, 2014
Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
DRAINAGE ITEMS: AAA Paving(cont.)
JAN KELLY LANE
- Graded and dress up ditches.
GINGHAM DRIVE
- Graded and dress up ditches.
WENDOVER LANE
- Dress up the work site and placed sob grass.
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- Completed.
Placed back one of the dyed stencil concrete driveway on Gingham. View to the southeast.
WATER ITEMS:
JAMESTOWN ROAD
- The water line on Tynebridge is completed.
March 30, 2014 to April 12, 2014 Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
WATER ITEMS: (cont.)
JAN KELLY LANE
- Completed.
CALICO LANE
- None required
GINGHAM DRIVE
- None required
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- None required
WENDOVER LANE
- None required
TREE PROTECTION:
JAMESTOWN ROAD
- This period no work was performed on this aspect of the project at this time.
CALICO LANE
- This period no work was performed on this aspect of the project at this time.
JAN KELLY LANE
- This period no work was performed on this aspect of the project at this time.
GINGHAM DRIVE
- This period no work was performed on this aspect of the project at this time.
March 30, 2014 to April 12, 2014 Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
TREE PROTECTION: (cont.)
WENDOVER LANE
- Removed the tree protective fencing.
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- Completed
Stenciling one of the dyed concrete driveways on Jan Kelly. View to the east.
SUPPLEMENTAL ITEMS:
JAMESTOWN ROAD
- This period no work was performed on this aspect of the project.
CALICO LANE
- This period no work was performed on this aspect of the project.
JAN KELLY LANE
- This period no work was performed on this aspect of the project.
March 30, 2014 to April 12, 2014
Activity/Status
Batch # 1 Paving & Drainage IMPROVEMENTS
SUPPLEMENTAL ITEMS: (cont.)
GINGHAM DRIVE
- This period no work was performed on this aspect of the project.
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- Completed
Placing concrete for one of the driveways on Gingham. View to the southwest.
Placing back one of the sidewalks on Gingham. View to thesoutheast.
Next Week’s Planned Activities
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
MOBILIZATION:
- This period no work was performed on this aspect of the project.
PAVING ITEMS: AAA Paving
JAMESTOWN ROAD
- This period no work was is planned on this aspect of the project.
CALICO LANE
- Placement for the sod grass weather permitting.
JAN KELLY LANE
- Placement for the sod grass weather permitting.
GINGHAM DRIVE
- Placement for the sod grass weather permitting.
GREEN OAK DRIVE
- Completed
WENDOVER
- Placement for the sod grass weather permitting.
DRAINAGE ITEMS: AAA Paving
JAMESTOWN ROAD
- On hold.
CALICO LANE
- Completed.
Next Week’s Planned Activities
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
Clean and dress up the south side of Calico after the asphalt has been placed. View to the west.
DRAINAGE ITEMS: AAA Paving (cont.)
JAN KELLY LANE
- Completed
GINGHAM DRIVE
- Completed
WENDOVER LANE
- Dressing up the area and complete the placement of the sod grass.
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- Completed
Next Week’s Planned Activities
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
WATER ITEMS:
JAMESTOWN ROAD
- This period no work is planned on this aspect of the project.
CALICO LANE
- None required
JAN KELLY LANE
- Completed
GINGHAM DRIVE
- None required
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- None required
TREE PROTECTION:
JAMESTOWN ROAD
- This period no work is planned on this aspect of the project.
CALICO LANE
- This period no work is planned on this aspect of the project.
JAN KELLY LANE
- This period no work is planned on this aspect of the project.
GINGHAM DRIVE
- This period no work is planned on this aspect of the project.
Next Week’s Planned Activities (cont.)
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
TREE PROTECTION: (cont.)
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- Completed.
SUPPLEMENTAL ITEMS:
JAMESTOWN ROAD
- This period no work is planned on this aspect of the project.
CALICO LANE
- This period no work is planned on this aspect of the project.
JAN KELLY LANE
- This period no work is planned on this aspect of the project.
GINGHAM DRIVE
- This period no work is planned on this aspect of the project
GREEN OAK DRIVE/HABERSHAM DITCH OUTFALL
- This period no work is planned on this aspect of the project.
Next Week’s Planned Activities (cont.)
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
Laid out to cut the old asphalt for tying in the new pavement view to the east.
Placed concrete back on a Wendover driveway. View to the north.
Next Week’s Planned Activities (cont.)
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
Placed concrete for the driveways on Wendover. View to the north.
Graded the ditch out at Jan Kelly and Calico. View to the south
Next Week’s Planned Activities (cont.)
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
View of the regarding of the ditches on Calico after the asphalt placement had been placed. removed from the drain line running between Tynebridge and Jamestown. View to the east.
Next Week’s Planned Activities (cont.)
April 13, 2014 to April 19, 2014
Batch # 1 Paving & Drainage IMPROVEMENTS
View of the regarding of the ditches on Calico after the asphalt placement had been placed. removed from the drain line running between Tynebridge and Jamestown. View to the east.
Page 1 of 8