Contents

1Introduction......

1.1Project Background......

1.2Project Component and Its Main Technical Specifications......

1.3Objective of the Environmental Management Plan......

1.4Basis of the Compilation......

1.5Assessment Standards......

1.6Environment Action Plan Composition......

2Environment Impact Assessment......

2.1Environmental Protection Objectives......

2.2Conclusions of EIA......

3Environment Management Plan......

3.1Environment management organizations......

3.2Environment Protection Measures......

3.3The Management to the Contractor......

4Environment Supervision Plan......

4.1Environmental Supervision Plan......

4.2Environmental Supervision......

5Environmental Monitoring Plan......

5.1Objectives......

5.2Monitoring plan......

6Personnel Training......

6.1Training for Full-time and Part-time Staff during Construction Phase......

6.2Training for Full-time and Part-time Environmental Staff in Operation Phase......

7Cost Estimation for EMP Implementation......

8Information Communion......

9Register......

10Report

Attached Figures:

Figure 1: Geographic Location of the Project

Figure2: Sketch Map of the Project Surroundings

Figure3: Photographs of Some Environmental Sensitive Spots

Figure4: Arrangement Map of Monitoring Sites

Figure5: Layoutof EnvironmentalImpact MitigationMeasures

1

1Introduction

1.1Project Background

The Environmental Improvement Project in YibinCity, SichuanProvinceis also named as Yibin Binjiang ring road project (YBRRP). It consists of road project, bridge and culvert project, protective project, landscape project and drainage project.

The construction of the proposed project will facilitate the swift connection among the districts and to achieve the ordered and smooth flow of passengers, freights and automobiles.It can activate the urban structure adjustment and improve the urban functions as well.Theproposed project will also play an active role in furnishing the corresponding municipal supporting facilities, strengthening the urban serving function and expanding the urban scale.

Moreover,the proposed project is located at the important characteristic area (called Binjiang) of Yibin. The proposed project on the riverside will provide the residents with a sound entertainment and leisure space and sightseeing along rivers. On the other hand, as a result of the smoother traffic and faster vehicle speed, the total exhaust emissions may be reduced and cause improvement on the ambient air and acoustic environment quality.

1.2Project Component and Its Main Technical Specifications

Theproposed Project is located in YibinCity, SichuanProvince,consisting of road project, bridge and culvert project, protective project, landscape project and drainage project. And it is divided into two parts, namely Line A and Line B. LineA belongs to reconstruction and extension project,laying along the left banks of the MinRiver and the Yangtze River from the MinRiverBridge at Jiuzhou Group, with a total length of 6688.51meters. Line B isa new road, arranged along the right bank of the JinshaRiver from the Cultural Square at the east district of Nan’an to No.4 Water Supply Works, with a total length of 3521.21 meters.The main functions of the project are transportation and relaxation. The total investment is RMB 574.06 million, of which USD 28.5 million is financed by the World Bank.

The project components of YBRERP are shown in Table 1-1. The main technical specifications of recommended scheme ofYBRERP are shown in Table 1-2.

Table 1-1 Project Components

Project component / Content and Scale
RoadEngineering / The total length of the road is 10.21 km, with Line A of 6688m, and Line B of 3521m
Bridge Culverts
Engineering / There are ten bridges and culverts on Line A, while three onLine B.
Retaining wall / The retaining wall is set along the left bank of the Min River from A0+780~A3+690, with the length of 2910m, and the right bank of the Jinsha River from B0+000.00 to B3+521.21, with the length of 3521m.
Landscape Engineering / Fourlandscape pitch points,greening belt, relaxing chairs, etc.are designed.
Drainage Works / The length ofthe drainage pipe is 148340m; The length ofthe waste pipe is 8170m

Table 1-2 Main Technical Specifications

No. / Name / Unit / Quantity / Remarks
Line A / Line B
Basic specifications
1 / Highway Grade / Grade II of Urban Sub-Artery / Grade II of Urban Sub-Artery
2 / Designed Speed Vehicles / km/h / 40 / 40
3 / The average costper meter / RMB10,000 / 2.156 / 3.389
Route
4 / Maximumlongitudinal slope / % / 5.62 / 1.0
Roadbed, Road surface
5 / Roadbed width / m / 15~20 / 20~24
6 / Filling / m3 / 380620 / 352628
7 / Excavation / m3 / 214954 / 27678
8 / Protective engineering / m2 / 18880 / 16500
9 / Asphalt concreteroad surface / m / 6688.51 / 3521.21
Bridge, Culverts
10 / Grade of Bridge’s Bearing Capability / Grade City- B and 3.5kN/m2 (crowd) / Grade City- B and 3.5kN/m2 (crowd)
11 / Bridge width / m / Identical to the width of the roadbed / Identical to the width of the roadbed
12 / Medium-small-sizedbridge / m/number / 200/4 / 125/1 / Simply supported “T” beam
13 / Culverts / 2 / 9
Drainage works
14 / Rainwater pipe / m / 10975 / 3859
15 / Sewage pipe / m / 4720 / 3450
Road crossing
16 / Level crossing / 11 / 6
17 / Flyovercrossing / 1 / /
18 / Virescence / m2 / 8556 / 17771
Others
19 / Land expropriation / Ha. / 18.14 / 8.56
20 / Retaining wall / m / 2910 / 3521.21

1.3Objective of the Environmental Management Plan

The World Bank financed Environment Improvement Project in Yinbin Cityis of high grade design and strict environmental assessment, in order to minimize the social and environmental reverse impact as far as possible, and solve the left environmental problems through the environmentalreduction measures.

As to the inevitable environmental impact of the project, a main objective of the environment assessment is to determine the potential impact of the project, and make a set of measures which is feasible in technology, sustainable in financial affairs and operable during construction and operation phase. The mitigation measure has been determined in the environmental assessment report, and will be put forward reasonablyin the environment management plan, which is suitable for the construction and the operation phase.

The function of EMP is to list the measures during construction and operation phase, the measure for monitoring and organizations, to avoid or control the reverse environmental impact of the project, and to provide the specific activity for the implement of the measures. The EMP will be the important connection between the environmental counter-measures and the environmental mitigation measures determined by EIA.

1.4Basis of the Compilation

The environmental assessment report is prepared in compliance with the relevant environmentalprotection law, regulations and standards of the People's Republic of China (PRC) , safeguardpolicies of the World Bank, relevant regulations and planning documents of Sichuan Provinceand Yibin city, project design documents, technical specifications and internationalenvironmental agreements signed by China, etc.More specifically, the basis of the EIA is as follows.

1.4.1Laws and regulations of the PRC

(1) Law of Environmental Protection of the People’s Republic of China (1989.12.26);

(2) Law of the People’s Republic of China on the Environment Impact Assessment (2003.9);

(3) Law of City Planning of the People’s Republic of China (1989);

(4) Prevention and Control Law of Water Pollution of the People's Republic of China (1996);

(5) Prevention and Control Law of Atmospheric Pollution of the People's Republic ofChina (1995);

(6) Prevention and Control Law of Environmental Noise Pollution of the People's Republicof China (1996.10.29);

(7) Prevention and Control Law of Solid Waste Pollution of the People’s Republic of China (2005.4.1);

(8) Law of Water of the People’s Republic of China (2002.8.29);

(9) Law of Water and Soil Conservation of the People’s Republic of China(1991.6.29);

(10) Law of Land Management of the People’s Republic of China(1998.8.29);

(11) Law of Highways of the People’s Republic of China (1997.3);

(12) Prevent and Control Flood Law of the People’s Republic of China (1997);

(13) Management Regulations on Environmental Protection forConstruction Projects (1998);

(14) Notice on Strengthening the ManagementWork of Environmental Impact Assessment for the Construction Projects Using InternationalFinancial Institutions Loan (jointly issued by the National Environmental Protection Bureau,State Planning Commission, Ministry of Finance and the People's Bank of China, 1993) .

1.4.2Requirements of the world bank

The requirements of the World Bank are included in ten safeguard policies, procedure andoperational guidance. They are:

(1) Environment Assessment (OP/BP/GP 4.01)

(2) Forestry (OP/GP 4.36)

(3) Natural Habitats (OP/BP 4.04)

(4) Safety of Dams (OP/BP 4.37)

(5) Pest management (OP 4.09)

(6) Involuntary Resettlement (OD 4.30)

(7) Indigenous people (OD 4.20)

(8) Cultural Property (OP 4.11)

(9) Projects in Disputed Areas (OP/BP/GP 7.60)

(10) Projects on International Waterways (OP/BP/GP 7.50)

1.4.3Environmental planning documents of Sichuan province and Yibin city

(1) Regulations of Natural Reserve of Sichuan Province (approved by meeting of theStanding Committee of People's Congress of Sichuan Province in 2000);

(2) Regulations of Drinking Water Source Protection of Sichuan Province (approved by meeting of theStanding Committee of People's Congress of Sichuan Province in 2004);

(3) Yibin Urban Master Plan 1997 and Implementation Opinions;

(4) Framework of Yibin Urban Master Plan 2005(To be reviewed);

(5) Detailed Controlling Layout of Yibin Urban Districts including Jiuzhou, Basha, East District of Nan’an, West District of Nan’an, and Zhaochang;

(6) Master Plan of LiubeichiPark;

(7) Master Plan of the WhitePagdaHillPark.

1.4.4Technical specifications

(1) Technical Guidelines for EIA - General Principles, Air Environmental, Surface WaterEnvironment(HJ/T 2.1-2.3-93).

(2) Technical Guidelines for EIA- Acoustic Environment(HJ/T 2.4-95).

(3) TechnicalGuidelines for EIA-Non-Pollution Ecological Impact(HJ/T19-1997).

(4) Technical Specifications on EIA for Highway Construction Projects (on trial) (JTJ 005-96).

(5) Standard of the Environmental Inspection (1986).

(6) Code of Water and Soil Conservational Methods for Developing and Constructing project (SL 204-98).

1.4.5Relevant study reports and literatures

(1) Environmental protection declaration registration table;

(2) The letter about related question to Binjiang Ring Road;

(3) Feasibility Study Report of YibinBinjiangRiver Encircling Road Project;

(4) The Resettlement Action Plan of the proposed project (RAP);

(5) The revised EIA TOR of the proposed project andthe official approval of theTOR given by SEPBon September, 2005;

(6) The Master plan of the National Natural Reserve of Rare and Specific Fish in the Upper Reaches of the Yangtze River;

(7) Investigation report of the National Natural Reserve of Rare and Specific Fish in the Upper Reaches of the Yangtze River completed by AgricultureDepartment of PRC, July, 2007;

(8) The basic information about the social, economic,climatic, hydrological,geological conditions, etc. in the construction area.

1.5Assessment Standards

According to the environmental condition and function in the construction area, as wellas the official letter titled“ Confirmed the execution standards of Yibin Binjiang River Encircling Road Project Environment Impact Assessment” issued by of Yibin Environmental Protection Bureau, the environmental standards applied for this assessment are determined as below:

1.5.1Environmental Quality Standards

●Surface Water

The ClassⅢstandard of“Environmental Quality Standards for Surface Water”GB3838-2002 is executedin the project region as showing in Table 1-3.

Table1-3 Environmental Quality Standards of Surface Water

Item / Standard Value
(GB3838-2002) Class Ⅲ / Item / Standard Value
(GB3838-2002) Class Ⅲ
PH / 6~9 / Coliformbacteria / ≤10000 per L
COD / ≤20 mg/L / Cd / ≤0.005 mg/L
BOD5 / ≤4 mg/L / As / ≤0.05 mg/L
DO / ≥5 mg/L / Cr / ≤0.05 mg/L
Non-ionic Ammonia / ≤0.02 mg/L / Pb / ≤0.05 mg/L
Nitrate / ≤20 mg/L / Hg / ≤0.0001 mg/L
Nitrite / ≤0.15 mg/L / Cyanide / ≤0.2 mg/L
Oil Substance / ≤0.05 mg/L / Total Phosphorus / ≤0.1 mg/L
Volatile Phenols / ≤0.005 mg/L / Ammonia Nitrogen / ≤1.0 mg/L

●Air Environmental Quality Standard

The ClassⅡstandard of “Ambient Air Quality Standard”(GB3095-1996) is executed in the construction area. Specially, because the main pollutant of Yibin Tianyuan Co.Ltd is Cl2, the highest permission value of deleterious substance concentrationin residential areaof"Industrial EnterpriseDesign Hygienic Standard "(TJ36-79)is executed in the factory district.The detailed standard values are shown in Table1-4.

Table 1-4 Air Environmental Quality Standard

Unit:mg/m3

Pollutant
Sampling time / Construction area / Factory district of TianyuanCo. Ltd
TSP / PM10 / SO2 / NO2 / Cl2
Annual Average / 0.2 / 0.10 / 0.06 / 0.04
Daily Average / 0.3 / 0.15 / 0.15 / 0.08 / 0.03
Hour Average / 0.50 / 0.12
Once Let / 0.10

●Acoustic Environmental Quality

The Class Ⅳstandard of “ Environmental Noise Standard of Urban Area” is executed in the non-sensitive region within30m±5m both sides of the redline of road. Specially, ClassⅠstandard is executed to the noise sensitivity points, such asschool, hospital and sanatorium, and ClassⅡstandard to the other assessment scope. Details are shown in Table 1-5.

Table 1-5 Acoustic Environmental Quality Standard

Standard / Implementscope or objects / LAeq(dB)
Daytime / Nighttime
“Standard of Environmental Noise of Urban Area” (GB3096-93) Class Ⅳ / Non- sensitive region within30m±5m both sides of the redline of road / 70 / 55
“Standard of Environmental Noise of Urban Area” (GB3096-93) ClassⅠ / School, hospital and sanatorium along the line / 55 / 45
“Standard of Environmental Noise of Urban Area” (GB3096-93) Class Ⅱ / Other assessment scope / 60 / 50

●Ecological Environment

Terricolous ecosystem: Water and soil loss assessment shall take the background value and the related professional standards as reference to protect the terraneouslife-form.

Hydrophytic ecosystem:The function of the “State Natural Reserve of Rare and Peculiar Fish in the Upper of the YangtseRiver”, as well as the main living condition of rare fish and the biologicvariety are not destroyed during or after the project construction.

1.5.2Standards of Pollutant Discharge

●Sewage: ClassⅠstandard of“Sewage Comprehensive Discharge Standard ”(GB 8978-1996) is executed. The detailed standard values are shown in Table 1-6.

Table 1-6 Sewage Discharge Standard

Item / Standard Value (GB8978-1996) ClassⅠ
pH / 6~9
SS / 70 mg/L
BOD5 / 20 mg/L
CODcr / 100 mg/L
Petroleum Category / 5 mg/L

● Air Pollutants

ClassⅡstandard of “Air Pollutants Comprehensive Discharge Standard” GB16279-1996 is executed during construction period. The detailed standard values are shown in Table 1-7.

Table 1-7 Air Pollutant Discharge Standard11

Unit mg/m3

Standard / NOx / PM10 / SO2 / TSP
“Air Pollutants Comprehensive Discharge Standard”(GB16297-1996) Class Ⅱ / 240 / 120 / 550 / 1.0

● Noise

The correlative items of “Noise Limits for Construction Site” GB12523-90 are executed during construction period, seeing Table 1-8.

Table 1-8 Standards for Noise at Boundaries of Construction Sites

Construction period / Main Noise Source / Noise Limits LAeq(dB)
Daytime / Nighttime
Excavating / Bulldozer、Excavator、Shovel loader / 75 / 55
Piling / Pile machine / 85 / Forbid constructing
Structuring / Concrete mixer、Vibrator、Electric saw / 70 / 55

1.6Environment Action Plan Composition

The environmental management plan was completedbased on the "Environmental Impact Assessment Report of Yinbin Binjiang River Encircling Road Project ". As an independent file, the plan contains all the environmental protection activity to be put into effect, providing guidance for the reduction measure, environmental management and environmental monitoring of the project in construction phase and operation phase. The environment action plan of the project is composed of the following parts:

1). Environment impact mitigation plan: refers to the managemiient activities to prevent or reducedisadvantageous impacts on1 environment;

2). Environment supervision plan: refers to the supervision activities to assure simultaneousimplementation of mitigation measures with the project;

3). Environment monitoring plan: refers to the monitoring activities to eliminate pollution duringconstruction and operation.

4).Personnel Training

2Environment Impact Assessment

2.1Environmental Protection Objectives

2.1.1Sensitive Objectsof Water Environment

The water environment sensitive objects in the project region are shown in Table 2-1.

Table 2-1 Water Environment Sensitive Objects of YBRERP

NO. / Item / The position relations with the proposed road
1 / The water quality of the JinshaRiver,MinRiver and YangzteRiveradjacentto the project / The proposed road are arranged along the JinshaRiver, MinRiver and YangzteRiver

2.1.2Sensitive Spots of Air Environment

Air environment sensitive spots in the assessment scope are shown in Table2-2.

Table 2-2-1 EnvironmentAir Sensitive Spots of Line A

No. / Name / Distanceto RoadAxes(m) / Household number / Environment characteristic
Line A / 1 / JiangbeiPark / 41 / \ / A000+000left side,
a space for amusement
2 / LiubeichiPark / 34 / \ / A000+040 left side, a city level scenery
3 / The roadside houses of XinjianVillage / 20 / 48 / A004+240left side, reinforced concrete structurebuildings
4 / The roadside houses of JiansheVillage / 20 / 160 / A004+400 left side, buildings of reinforced concrete structure
5 / The 799 Kinder Garden / 22 / 18 class rooms / A004+500 left side,buildings of reinforced concrete structure
6 / The NO. 17 Junior Middle School / 90 / 26 class rooms / A004+500 left side, reinforced concrete structurebuildings
7 / The roadside houses of JiefangVillage / 20 / 14 / A004+520right side, buildings of reinforced concrete structure
8 / Baishawan Police Station / 41 / about 10 people / A004+810 left side, buildings of reinforced concrete structure
9 / The roadside dormitoryof779 Plant / 40 / 96 / A005+000right side, buildings of reinforced concrete structure
10 / Electric Power Hotel / 12 / 120 / A005+680 left side, buildings of reinforced concrete structure
11 / The roadside dormitories of Yangtze River Paper Industry Co.Ltd / 12 / 166 / A006+480 left side, buildings of reinforced concrete structure
12 / The roadside dormitories of Yibin Tianyuan Co.Ltd / 11 / 304 / A006+610right side, buildings of reinforced concrete structure

Table2-2-2 AmbientAir Sensitive Spots of Line B

No. / Name / Distanceto the Axes of Road (m) / Household number / Environment characteristic
Line B / 1 / Nan’an Cultural Square / 20 / \ / B000-010 left side, a space for amusement
2 / The NO. 405 Hospital / 60 / 50 sickbeds / B000+040right side, buildings of reinforced concrete structure
3 / The roadside dormitories of Yibin Chemical Fiber Factory / 20 / 20 / B000+040right side, buildings of reinforced concrete structure
4 / The roadside dormitories of Yibin Construction Committee / 30 / 56 / B000+200right side, buildings of reinforced concrete structure
5 / The roadside residential houses / 35 / 36 / B000+200right side, buildings of reinforced concrete structure
6 / The roadside residential houses nearby the railroad / 15 / 48 / B000+720right side, buildings of reinforced concrete structure
7 / The roadside houses of Shangdukou community / 20 / 84 / B001+340right side, buildings of reinforced concrete structure

2.1.3Sensitive Spots ofAcoustic Environment

Acoustic environmentalsensitive spots in the assessment scope are shown in Table 2-3.

Table 2-3 Sensitive spots ofacoustic environment along the proposed roads

Serial number / Name / Distanceto Road(m) / Altitudinal difference
to road (m) / Household number / Environmental
characteristic
Line A / 1 / The roadside houses of XinjianVillage / 20 / 0 / 48 / left side of A004+240, reinforced concrete structure buildings
2 / The roadside houses of JiansheVillage / 20 / -1 / 160 / left side of A004+400, reinforced concrete structure
3 / The 799 Kindergarten / 22 / 2 / 18
classrooms / left side of A004+500, reinforced concrete structure
4 / The NO. 17 Junior Middle School / 90 / 3 / 26
classrooms / left side of A004+500, reinforced concrete structure buildings
5 / The roadside houses of JiefangVillage / 20 / -1.5 / 14 / right side of A004+520, reinforced concrete structure
6 / The roadside dormitoryof779 Plant / 40 / -5 / 96 / right side of A005+000, reinforced concrete structure
7 / The roadside dormitories of Yibin Electric Power Co.Ltd / 12 / -2 / 166 / left side of A005+680, reinforced concrete structure
8 / Electric Power Hotel / 12 / -2 / 120 / A005+680 left side, reinforced concrete structure
9 / The roadside dormitories of Yangtze River Paper Industry Co.Ltd / 12 / -3 / 166 / left side of A006+480, reinforced concrete structure
10 / The roadside dormitories of Yibin Tianyuan Co.Ltd / 11 / 0 / 304 / right side A006+610, reinforced concrete structure
Line B / 1 / The NO. 405 Hospital / 60 / 5 / 50 hospital beds / right side of B000+040, reinforced concrete structure
2 / The roadside dormitories of Yibin Chemical Fiber Factory / 20 / -3 / 20 / right side of B000+040, reinforced concrete structure
3 / The roadside dormitories of Yibin Construction Committee / 30 / 0 / 56 / right side of B000+200, reinforced concrete structure
4 / The roadside residential houses / 35 / 0 / 36 / right side of B000+200, reinforced concrete structure
5 / The roadside residential houses nearby the railroad / 15 / 0 / 48 / right side of B000+720, reinforced concrete structure
6 / The roadside houses of Shangdukou community / 20 / 0 / 84 / right side of B001+340, reinforced concrete structure
7 / Residential building of No. 503 workshop of Wuliangye group Co.,Ltd. / 100 / 0 / 60 / right side of B001+600, reinforced concrete structure

2.1.4Sensitive Spots of Ecological Environment

According to the results of the spot investigation,in the assessment scope of proposed project the sensitive spots of ecological environment mainly is the spots border with the project such as "The national Natural Reserve of Rare and Peculiar Fish in the Upper of the YangtseRiver. The construction activitieswhich possibly affect to the environment sensitive spots mainly are the guard wall, bridge and culvert excavation, filling construction and so on.

2.1.5Sensitive Spots of Social Environment

The proposed construct pass through the Yibin city, the demolishing quantity along the route is bigger, the demolishing business, institution and inhabitant of this project are the social environment sensitive object;In addition,the business and institution which are affected by construction and operation along the route, such as Tianyuan chemical plant,Yibin generate electricity Co.Ltd and so on,are also the social environment sensitive object of the project. The LiuchibeiPark and the White Pagoda Hill Beauty Spot are not in the scope of expropriation and demolishing of project along the route of section A, and the project construction will not directly affect them.