Are you constructing a dwelling or extension to your property?

Lodge your Commencement Notice with the Building Control Authority

  • Have you recently been granted Planning Permission and are about to commence the development?
  • If so, have you lodged your Commencement Notice?

What is a Commencement Notice?

Pursuant to 1997 Building Control Regulations, Commencement Notices must be lodged, subject to certain exemptions, to the Building Control Authority (Longford County Council) by any person who intends to carry out any works or change of use on their property. LongfordCounty Council is the statutory Building Control Authority for the administrative areas of both:

  • Longford Town Council and
  • Longford County Council.

When do I submit a Commencement Notice?

Notices should be submitted not less than 14 days and not more than 28 days before the commencement of such works - It is probably preferable to define works as the first physical act of construction.

What form should the Commencement Notice take?

Commencement Notice forms may be obtained from the Planning Departments at Longford County Council or Longford Town Council or can be downloaded from our websites.

What happens if I don’t submit a Commencement Notice to the Building Control Authority?

The primary responsibility for compliance rests with designers, builders and building owners. Building control authorities have power to inspect design documents and buildings, as well as powers of enforcement and prosecution, where breaches of the regulations occur.

There are heavy penalties, including fines and imprisonment, for breaches of the regulations. In addition, when it comes to selling your property, you may have difficulties if you cannot satisfy the purchaser's solicitor that the requirements of the regulations have been met.

Finally, there is no facility within the Building Control Regulations for a relaxation on the requirement to submit a Commencement Notice; therefore the Building Control Authority cannot accept a Commencement Notice after the required period.

For further details or information, please contact:

  • Planning Department, Longford Co. Council,

Aras an Chontae, Great Water St., Longford Tel.: 043-43427

  • Planning Department, LongfordTown Council,

Market Square, Longford Tel.: 043-46474

pril 2006

Commencement Notice for Development

(Notice to a Building Control Authority pursuant to Part II of the Building Control Regulations, 1997)

/

LONGFORD COUNTY COUNCIL

Aras an Chontae, Great Water Street, Longford

Tel: (043) 43427/46231 Fax: (043) 41233

Website:

Building Control Authority: LongfordCounty Council

1.

I, the undersigned, hereby give notice/give notice on behalf of the person(s) named below*, to the above Building Control Authority (in accordance with Part II of the Building Control Regulations) that) I/the persons named below* intend to carry out the development as described below. (* Cross out whichever is inappropriate)

Signature: ______Date: ______Tel: ______Fax:______

Name of person(s): ______Email: ______

Address: ______

Commencement date (of work): ______Fee payable (€): ______

2a. PROJECT PARTICULARS: (In addition, for Residential Developments, please complete Section 2b below)

Description of proposed development:

______

______

Planning permission No.: ______Date of grant: ______Date of expiry: ______

Fire Safety Certificate Number (if applicable): ______

Location of development: ______

2b. Residential Development Information:

Total number of dwelling units (all phases*): ______Total No. of phases*: ______

Phase for this Commencement Notice: ______No. of units for this phase/Commencement Notice**: ______

Commencement date for this phase: ______(Proposed) end-date for this phase: ______

* where applicable, i.e. phasing not relevant for single houses. ** include single house figure here also.

3. Builder:

Name: ______Tel: ______Fax: ______

Address: ______Email: ______

4. Building Owner Details: (if different from Section 1 above)

Name: ______Tel: ______Fax: ______

Address: ______Email: ______

5. Building Designer Details:

Name: ______Tel: ______Fax: ______

Address: ______Email: ______

______

6.Information: Person(s) from whom such plans, documents and any other information, as are necessary to show that the building or works will, if built in accordance with design, comply with the requirements of the Building Regulations, may be obtained.

Name: ______Tel: ______Fax: ______

Address: ______Email: ______

______

7. Drainage System Foundations: Person(s) from whom notifications of the pouring of any foundations and/or the covering up of any drainage systems may be obtained

Name: ______Tel: ______Fax: ______

Address: ______Email: ______

Second Schedule

Form of Commencement Notice for Residential Development

(Notice to a Building Control Authority pursuant to Part ll of the Building Control Regulations, 1997)

EXPLANATORY NOTE

Project Particulars

Total number of dwelling units (all phases):

The total number of units (houses and apartments) for the entire residential development, i.e. all phases. Include single houses.

Total number of phases (not relevant for single houses):

Give the total number of different phases of development for this project.

Phase for this commencement notice:

A commencement notice should be given at the start of each phase of development. Insert the number of the particular phase that this commencement notice is relevant to, e.g. 1st, 2nd.

Number of units for this phase/commencement notice:

The corresponding number of units (houses and apartments) for this particular phase. A single house should also be included here, as it will be commencing in the short/ medium term.

Commencement date for this phase:

Commencement date of works for this particular phase of development.

(Proposed) end-date for this phase:

Expected end-date for this particular phase of the development.

Additional Notes

Fee payable

A fee of €30 is payable for each unit of development (e.g. A residential development of 5 houses will require a fee of €150 to be paid the authority).

Submission date

A valid Commencement Notice must be submitted to the authority at least 14 days in advance of the commencement of any development work on site. The maximum period allowed for prior notification to the authority is 28 days.

Building Control Authority for Longford Town and County- Longford Co. Council is the Building Control Authority for the functional areas of Longford Town and County Councils.