Table of comparative confidentiality claims

This table sets out the comparative proportion of material in the regulatory proposal that is subject to any claim of confidentiality compared to that which is subject to claims of confidentiality in the regulatory proposals of other network service providers. This is a requirement of clauses 6.9.2A and 6A.11.2A of the National Electricity Rules.

Business name / Proposal or revised proposal / Date / Number of pages ofsubmission that includeinformation subject to a claim of confidentiality / Number of pages ofsubmission that do notincludeinformation subject toa claim of confidentiality / Total number of pagesof submission / Percentage of pages ofsubmission that includeinformation subject to a claimof confidentiality
Ausgrid / Proposal / June 2014 / 508 / 22092 / 22600 / 2.3%
Endeavour Energy / Proposal / June 2014 / 247 / 6333 / 6580 / 3.8%
Essential Energy / Proposal / June 2014 / 876 / 14333 / 15209 / 6%
ActewAGL / Proposal / June 2014 / 17.4%
TransGrid / Proposal / June 2014 / 1224 / 33809 / 35033 / 3%
TasNetworks / Proposal / June 2014 / 800 / 3900 / 4700 / 17%
Directlink / Proposal / June 2014 / 1 / 3368 / 3369 / 0.03%
Jemena Gas Networks / Proposal / June 2014 / 8037 / 15 292 / 23 329 / 34.5%
Ergon Energy / Proposal / November 2014 / 248 / 8301 / 8549 / 3%
Energex / Proposal / November 2014 / 64 / 2 633 / 2 697 / 3.5%
SA Power Networks / Proposal / November 2014 / 825 / 15982 / 16807 / 4.9%
Ausgrid / Revised proposal / January 2015 / 313 / 5 191 / 5 504 / 5.7%
Endeavour Energy / Revised proposal / January 2015 / 241 / 8 260 / 8 501 / 2.8%
Essential Energy / Revised proposal / January 2015 / 424 / 9 483 / 9 907 / 4.3%
ActewAGL / Revised proposal / January 2015 / 428 / 11 755 / 12 183 / 3.5%
TransGrid / Revised proposal / January 2015 / 143 / 1 018 / 1 161 / 12%
TasNetworks / Revised proposal / January 2015 / 0 / 9 / 9 / 0%
CitiPower / Proposal / April 2015 / 590 / 27 238 / 27 828 / 2%
Powercor / Proposal / April 2015 / 595 / 28329 / 28 924 / 2%
Jemena / Proposal / April 2015 / 3 086 / 27497 / 30583 / 10%
AusNet / Proposal / April 2015 / 666 / 4773 / 5439 / 12%
United Energy / Proposal / April 2015 / 158 / 31955 / 32113 / 1%
ActewAGL gas distribution / Proposal / June 2015 / 3194 / 8 346 / 11 540 / 28%
Australian gas networks / Proposal / July 2015 / 1 356 / 5 149 / 6 505 / 21%
SA Power Networks / Revised Proposal / July 2015 / 281 / 3 526 / 3 807 / 7.4%
Ergon / Revised Proposal / July 2015 / 351 / 17 725 / 18 076 / 1.9%
Energex / Revised proposal / July 2015 / 104 / 1306 / 1410 / 7.4%
Amadeus Gas Pipeline / Proposal / August 2015 / 90 / 11 248 / 11 158 / 0.8%
AusNet Services / Proposal / November 2015 / 679 / 2558 / 3237 / 21%
CitiPower / Revised proposal / January 2016 / 1 460 / 22974 / 24434 / 6.0%
Powercor / Revised proposal / January 2016 / 1 403 / 22575 / 23978 / 5.9%
Jemena / Revised proposal / January 2016 / 2 420 / 8 291 / 10711 / 23%
AusNet / Revised proposal / January 2016 / 3 / 393 / 396 / 0.8%
United Energy / Revised proposal / January 2016 / 23 / 11 234 / 11257 / 0.2%
ActewAGL gas distribution / Revised proposal / January 2016 / 111 / 2 396 / 2 507 / 4.4%
Australian Gas Networks / Revised proposal / January 2016 / 165 / 2 087 / 2252 / 7.3%
Amadeus Gas Pipeline / Revised proposal / January 2016 / 2 / 326 / 328 / 0.61%
TasNetworks / Proposal / January 2016 / 400 / 4779 / 5179 / 8%
Powerlink / Proposal / January 2016 / 460 / 2 568 / 3 028 / 15.2%