ITU Capital Projects Master Project List and Activities 09/28/2012

(Priority Action in Red) ( = New Information)

Campus Drive West Campus Connector RoadBrad Glatfelter______

IT Route meeting Friday

  • More segment design meetings in following weeks.
  • Scope includes construction of restrooms, maintenance building, tennis courts, pavilion and various athletic fields.
  • Plans on Facilities Docushare.
  • Site work likely to begin in the 4th quarter.

Conservation Studies Program Residence(Front Royal) Nancy Pickens Alt. Thursdays 10:30

  • Smithsonian partnership – 128 bed Housing, Dining Hall and Academic Building.
  • Waiting for schedule for OSP replacement.
  • Cable TV installed.

Fenwick Library Expansion Brian Snyder

  • Occupancy August 2014.

Weekly teleconference design meeting underway.

Future underground facilities location requirement are complicating duct bank planning

Updated IT infrastructure design drawings due today.

Net Eng developed scope of reconnection work.

IT wiring design to be managed by AE, work subbed to GC

Fine Arts Renovation Hieu Tran Alt. Wednesdays 10:00

  • Substantial completion is May 10, 2013. Construction schedules posted on Docushare.

Johnson Center loading dock security camera pathway installed, needs cabling and camera.

Some pathway revisions and clarifications needed

  • Awaiting cabling submittals. Will conduct a pre-construction meeting prior to cable work starting.
  • Site requirements: check in with Mason Inspector and wearing hardhat, neon vest, glasses and boots.

Housing VIIIB ShenandoahNancy Pickens

  • Construction start 01/13. 300 Freshman beds in Presidents Park area. Completion expected Summer 2014.
  • RFP respondent’s interviews two weeks ago.

PWC PPEA Life Sciences Building Micky Boeckl Alt. Wednesdays 10:00

  • January 2013 completion. 75,000 square feet, 3 stories, BSL II.
  • Second story pour underway.
  • 60% drawings on Docushare, they are responsive to our comments, details should be reviewed
  • OSP conduit installed.

PWC PPEA Graduate Dorm- Beacon HallMicky Boeckl Alt. Wednesdays 10:00

  • Planned building turnover of October 19 with move in on October 20.

OSP pulled this week, NET walkthrough

Will update the schedule Wednesday

  • TR work is underway, racks being installed,
  • Upper level student housing – 152 beds, 4 stories, above a floor of 10,000 GSF Mason space and 15,000 GSF retail space with 212 parking spaces.

Point of View Center Nancy Pickens______

  • Startup planned for September, completion in one year.
  • Network site provider connection proposal and costs needed.
  • County requirements for sewage treatment worked out.

Science and Tech II Addition/Renovation Alex Iszard Tuesdays 11:00

  • Substantial completion 3-23-2013. Classroom use in fall 2013. S&T II is now Exploratory Hall.
  • From Facilities “Project Partners” meeting, planned move is week of May 20, 2013.

Putting BAS network requirements together

  • Mason Proj. Manager called for General Contractor to have telecom rooms complete on January 15, 2013.
  • Telecom room termination in progress.
  • AV Scope nearly complete.
  • Site requiresSafety Orientation, helmet, vest, glasses, and hard shoes; access via trailer check in only.

SUB I Dining RenovationNancy Pickens Wednesdays 12:30

  • All University Card office (photo ID and Mason Money) moves in late October.

University Commons Renovation Hieu Tran Tuesdays 11:00

Hanover BCOM postponed.

Horizontal cabling finished next week.

Plan for switch/WAP install Tuesday 10/2 if the building is ready.

Farther Out and Smaller Projects

Shenandoah Dining ExpansionHieu Tran

  • Schematic closer to approval and completion. $8 million project. Construction likely concurrent with Housing VIIIB.
  • Possible Fall 2014 completion.

Housing VIIIB RappahannockNancy Pickens

  • Completion planned Fall 2015. Located north of Fenwick, partially on Lecture Hall site.

RFP being prepared.

  • Currently 210 beds, 13 classrooms. Mixed use of housing, classroom and academic center.
  • Ductbank relocation part of the plan.

Field House RenovationAlex Iszard

WAP installation completed.

University Hall Retail Fit-outKim Greene

  • Einstein Bagels construction underway. Anticipate October opening. Net Infrastructure will do assessment. Everlasting Café – possibly January.

Tyson’s Corner Leased Academic Space

Project on hold per VP of Facilities.

Belmont Bay Alex Iszard

  • Has been approved by DPB for PPEA. Land arrangement must be obtained.

ITU Project Engineering: A. Norcott/J. Callahan10/31/18