CHAPTER 5
5.4See file Problem 5-4.xls
b.
Expected completion time = 89 days
5.7See file Problem 5-7.xls
P(Finish within 90 days) = .590439
Thus P(Finish later than 90 days) = 1 - .590439 = .409561
5.8See files Problem 5-8a.xls and Problem 5-8b.xls
a.28 weeks
b. Crash A 4 weeks, B 3 weeks, E 2 weeks, F 5 weeks, G 4 weeks; additional cost = $29,950 - $24,600 = $5,350
5.9See file Problem 5-9.xls
Switching to Glidestone would cost $28,750. So Keith should switch to Glidestone.
Now, crash A 4 weeks, B 3 weeks, E 2 weeks, F 7 weeks, G 1 week.
5.11See file Problem 5-11.xls
a.
From the output convert times beginning at 10:00PM.
Activity ES EF LS LF SLACK
A10:00PM11:20PM10:00PM11:20PM0
B10:00PM11:00PM12:00AM 1:00AM 2 hours
C11:20PM 1:00AM11:20PM 1:00AM0
D11:20PM 1:00AM 3:40AM 5:20AM 2 hours, 20 min.
E11:20PM12:20AM12:40AM 1:40AM 1 hour, 20 min.
F 1:00AM 1:40AM 1:00AM 1:40AM0
G 1:00AM 1:20AM 3:00AM 3:20AM 2 hours
H 1:40AM 2:20AM 4:40AM 5:20AM 3 hours
I 1:40AM 2:40AM 4:40AM 5:40AM 3 hours
J 1:40AM 3:20AM 1:40AM 3:20AM0
K 2:20AM 2:40AM 5:20AM 5:40AM 3 hours
L 3:20AM 5:40AM 3:20AM 5:40AM0
b.A schedule must have no job started before its ES or finished after its LF. If Worker 1 does only the activities on the critical path then one such schedule is:
Schedule for Worker 1Schedule for Worker 2
A 10:00PM - 11:20PMB 10:00PM - 11:00PM
C 11:20PM - 1:00AME 11:20PM - 12:20AM
F 1:00AM - 1:40AMD 12:20AM - 2:00AM
J 1:40AM - 3:20AMG 2:00AM - 2:20AM
L 3:20AM - 5:40AMH 2:20AM - 3:00AM
I 3:00AM - 4:00AM
K 4:00AM - 4:20AM
5.12See file Problem 5-12.xls
a.
104 months
b.(i) 5 months (ii) 3 months
c.(i) .000173 (shown); (ii) .012674; (iii) .185547; (iv) .672640
5.16See file Problem 5-16.xls
a.21 weeks
b. G (Lodging and Transportation) has 11; C (Hire Security) and J (Concessions) have 5 weeks slack each.
c..000023 (not shown)
d.By trial and error on the template --- 26.144 weeks (shown)
For those familiar with the Goal Seek option in the Tools menu of Excel, one can generate a solution as follows:
5.17See files Problem 5-17Boeing.xls and Problem 5.17MDD.xls
BOEING
MCDONNELL-DOUGLAS
a. McDonnell-Douglas (Prob. = .960423 vs. .947353 for Boeing)
b.Boeing (Expected completion time = 54 vs. 55 for McDonnell-Douglas)
5.18See file Problem 5-18.xls
a.40days; The sum of the activity costs is $356,100
Total Delay
b.(i)H is on the critical path2 days
(ii)C has 3 days slack0 days
(iii)F has 10 days slack1 day
(iv)F has 10 days slack4 days
(v)G has 3 days slack0 days
(vi)C has 3 days slack, F has 10 days slack, not on same path1 day
(vii)C and G are on same path with a total of 3 days slack1 day
5.20See files Problem 5-20ab.xls and Problem 5-20c.xls
a.Expected completion = 89 days; critical path = C-D-F-G-I-K
Earliest/latest start/completion dates:
Earliest EarliestLatestLatest
ActivityStartFinishStartFinish
AJune 1June 4June 6June 9
BJune 1June 6June 10June 15
CJune 1June 7June 1June 7
DJune 7June 15June 7June 15
EJune 4June 10June 9June 15
FJune 15July 17June 15July 17
GJuly 17August 8July 17August 8
HJuly 17 July 28July 23 August 4
IAugust 8August 24August 8August 24
JJuly 28August 17August 4August 24
KAugust 24August 29August 24August 29
b..924136
c.See file Problem 5-20c to find the probability of completing in 99 days if the $3500 is spent.
If the $3500 is not spent (part (b)), the expected total cost is:
.924136(0) + .075864($120,000) =$9,103.68
If the $3500 is spent (part (c)), the expected total cost is:
.977912(0) + .022088($120,000) + $3,500 =$6,150.56
Yes -- Spend the $3,500
5.21See file Problem 5-21.xls
See schedule above that meets the deadline at a cost of $89,000.
5.23See files Problem 5-23a.xls and Problem 5-23b.xls
a.$476,500 -- see above for schedule
b.
It is infeasible -- the project cannot be completed in less than 18 weeks.
5.24See file Problem 5-24.xls
135.5833 days
5.27See file Problem 5-27a.xls and Problem 5-27c.xls
a. 36.33333 weeks; A-B-F-H-I
b..441705
c.Would not spend $1000 to move the files alone since move files (Activity G) is not on the critical path.
If $1000 was spent on moving equipment, the three time estimates for activity F are now 1, 2, and 3. In this case, from file Ch5.27c-equip (not shown), the new critical path is A-B-G-H-I and P(Finish in 36) = .556513.
Note that G is now on the critical path, so now it worth exploring spending another $1000 (for $2000 total) to also cut activity G's three time estimates to .5, 1, and 2.5. In this case, from file Ch5.27c-both (not shown), the critical path is once again A-B-F-H-I and P(Finish in 36) = .615351.
Expected Cost = Prob(Finish in 36)($0) + P(Not Finish in 36)($5000) + Hiring Costs
Expected Cost(Neither) = .441705($0) + .558295($5000) + $0 = $2791.48
Expected Cost(Equipment) = .556513($0) + .443487($5000) = $1000 = $3217.44
Expected Cost(Both) = .615351($0) + .384649($5000) + $2000 = $3923.25
DO NOT HIRE EITHER SET OF MOVERS.
5.30See file Problem 5-30.xls
a.Critical Path: A - C - E - G= 30 days = 4.333333 days
b.(i) 5 days (0 slack)
(ii)Project not delayed (8 days slack)
(iii)4 days (1 day slack)
(iv)4 days (1 day slack)
(v)4 days (B and D not on the same path)
(vi)9 days (D and F are on the same path)
5.33See file Problem 5-30.xls and Problem 5-33.xls
If Stacey does not spend the $3000
See file Ch5.30.xls and enter 35 into cell F6 (not shown)
P(finish in 35 days) = .875718
Thus the expected cost is (.875718)(0) + .124282(100,000) = $12,428.20
If Stacey does spend the $3000
If Stacey does spend the $3000
See file Ch5.33.xls and enter 35 into cell F6 (shown above)
P(finish in 35 days) = .933868
Thus the expected cost is (.933868)(0) + .066132(100,000) = $6,613.20
+ extra $3000 =$3,000.00
TOTAL =$9,613.20
$9,613.20 < $12,428.20, so Stacey should spend the extra $3000.
5.37See files Problem 5-37a.xls and Problem 5-37c.xls
a. See below.
b.36 weeks; B - I
c.(i) Activity H has 8 weeks slack; delaying it 10 weeks will delay the project 2 weeks.
Cost = $6,000 + 2($5,000) = $16,000
(ii)Since activity H has 8 weeks slack, an extra 4 weeks will not delay the project
Cost = $17,500
(iii)Change E to 11 and H to 6 and re-solve. The project now takes 37 weeks (not shown). Thus the cost of this option is: $4000 + $5500 + 1($5000) = $14,500.
The senior center should use its own landscaping crew.
5.38See file Problem 5-38.xls
a.No, the expected time = 17 weeks
b.H has 2 weeks slack; delaying it by 3 weeks will delay the project by 1 week.
c.D has 2 weeks slack; delaying it by 3 weeks will delay the project by 1 week.
d..339639
Chapter 5 - 1