INSTRUCTIONSFOR THETIME EXTENSIONREQUEST (Pre-Construction)
ThepurposeoftheDepartmentofTransportation’sTime Extension Requestform(Form)istostandardizeandstreamlinethetime extensionrequestprocessfor requesting additional time needed to start or complete allocated COS (PA&ED,PS&E,andRight-of-WaySupport) phases.TheFormwillbecomprisedofasingle page,dividedintofoursections,withsupportingdocumentationtobeattachedasnoted.
WhenisaTime ExtensionRequestFormneeded?
TheFormisrequiredforallStateHighwayOperationandProtectionProgram(SHOPP)projectsonthestatehighwaysystemfor COSphases/activitieswhen additional time is needed due to unforeseen reason(s).
SECTION 1–RequestInformation
Component
Designatesthephase(s)requested.Selectoneofthefollowing:
•PA&ED
•PS&E
•R/W Support
Original Deadline
Deadline to “Start” a Pre-Construction phase: Allocation plus six months. Deadline to “End” a Pre-Construction phase: “Start” date plus 36 months. Date(s) entered in MM/DD/YY format are required.
Months
Enter the number of months requested for each phase.
Extended Deadline
The original deadline plus the number of months requested for the time extension.
Last Saved
Enter the date(in mm/dd/yy format) when this form is last saved or revised. The default is the date of entry.
SECTION 2– ProjectInformation
ProjectID
Thisisthe10-digitCaltrans Project ID (also called EFIS) number.
District
TheDepartment’sDistricts.
County
Countywhereprojectislocated.Use“Various”whenaprojectcrossestwoormorecounties.
Program Code
Enter the Accounting / TRAMS Code for the project.
Route
Statehighwayorinterstateroutenumber. Useprimaryroutenumberwhenprojectaffectstwoormoreroutes.
PostMiles
Statehighwayroutepostmiles.
EA
TheDepartment’sExpenditureAuthorization(EA)number.LeaveblankifnotaStateHighwaySystemproject.
PPNO
ProjectPlanning(PPNO)number. SHOPPprojectsmusthaveaPPNO.ThisnumbercanbefoundinCTIPS.
Project Location/Description
ThisistheprojectlocationandscopeofworkasitiscurrentlyprogrammedinCTIPS.ThedescriptionenteredhereshouldbethesameasfoundinCTIPS.Evenifthescopeischanged,pleaserefertothescopeasiscurrentlyprogrammed.
SECTION 3–Reason for Delay
Thepurposeofthissectionistocaptureinformation regarding thecurrent disposition oftherequestingreaterdetail.This informationis importantfordiscussionofthemeritsoftherequestwiththeCTCwhenproceedingtowardtime extension. TheFORMisnotconsideredacompletesubmittalwithoutallnecessarysupportingdocumentationincluded.
1. Providetheassumptionmadeandthechangesthathavecausedthedelay.Explainwhytheoriginaldeadline(s) cannot be met.
2.Explainwhat changed since the allocation date.
SECTION 4–Approvals
Approvals:Name, title, and signature of the Project Manager and SFP are required prior to submittal.