PROJECT INSPECTION CHECKLIST & ACCEPTANCE

(Include this Project Inspection Checklist & Acceptance Form with the Final Report)

Project Name:______

Owning Agency:NC DENR – Ecosystem Enhancement Program

Project Manager:______

Review Coordinator:______

Design Firm:______

Onsite Manager:______

SCO Monitor: ______

Contract Dates: Start:______End: ______

SUBSTANTIAL COMPLETION

1. The Substantial Completion Walk Through was held by the designer and contractor.______

Date

2. The designer accepted the project as substantially complete.______

Date

PRELIMINARY FINAL INSPECTIONCHECKLIST – Designer, Contractor & Owning Agency

1. The as-built survey was submitted to the designer by the contractor for a review______

of accuracy and compliance to contractual requirements.Date

2. The contractor’s statement of project completion, and a request for an inspection______

was received by the designer.(attach copy) Date

3.A Preliminary Final Inspection was led by the designer and attended by the contractor______

and Owning Agency.Date

4. The PreliminaryFinal Inspection punch list was generated by the designer and copies ______

were distributed to thecontractor and the Owning Agency. (attach copy) Date

5. The contractor’s statementof punch list completion and a final inspection request______

was received by the designer. (attach copy) Date

6. The final as-built survey wasreviewed and accepted by the designer and Owning Agency.______

Date

Designer’s Statement:

______(design firm)affirms that all construction has beeninspected, the as-built

survey has beenverified, the project meets the contract requirements,the project is substantially complete,

and a final inspection will be scheduled.

______

Designer Representative SignatureDate

Page 1 of 2

FINAL INSPECTION – Designer, Contractor, Owning Agency & SCO

DISAPPROVAL – if applicable

The project cannot be accepted as complete for the following reason(s):

______

Designer Representative SignatureDate

______

Owner Representative SignatureDate

______

SCO Representative SignatureDate

Designer’s Statement:

______(design firm) affirms that the delinquencies above have been corrected, the

site has been re-inspected, the as-built survey has been verified, the project meets the contract requirements,

andthe project is ready for a Final Inspection.

______

Designer Representative SignatureDate

ACCEPTANCE

A Final Inspection was led by the designer and was attended by the Contractor, Owning Agency & SCO.______Date

The established date for guarantees and warranties to commence is:______

Date

The date that insurance coverage (required by Article 34 of the General Conditions) may be cancelled is: ______

Date

Comments:

Designer Approval:______

Representative SignatureDate

Owner Approval:______

Representative SignatureDate

SCO Acceptance:______

Representative SignatureDate

Page 1 of 2