Minutes of the meeting held on 23rd May 2017
Chair: Charl Roberts (CR)
Present: Khulisujobe Sithole (KS)
Sipho Dache (SID)
Eric Skosana (ES)
Lewatle Phaladi (LP)
Senzo Nkosi (SN)
Lehlohonolo Ngema (LN)
Simon Mofokeng (SM)
Apologies:
Minutes: Sherperd Dube (SD)
Adopted by: Khulisujobe Sithole (KS)
Eric Skosana (ES)
Agenda points / Discussions / Decisions / Attention / DeadlineWelcome and introductions / · Welcomed LCS Staff members to the meeting / CR
Meetings Report back
SMT Report back
Next Meeting 22-05-2017 / · Cancelled
· Next Meeting 5th June / CR / Next Meeting
CAB Report back
Change Advisory Board / · CAB will be split into 2, Technical and the Normal CAB - Documentation will be sent / SM / ES / Every Tuesday
Client Services – meeting dates: / · Next date to be adviced / CR/SM/KS/ES / Next Meeting
Projects
KCs / · Management PCs are pulling 8 print queues
· IP Camera rollouts need to be escalated – a meeting has been scheduled
o Meeting was held with protection services who recommended 26 cameras be installed at Wartenweiler and also that the library pay carry part of the cost
· There is network problems at Education KCs, SM has logged a call with service provider (3 Computers) – quotation received and approved – Morewa visited the Education Library, there is need for switch replacement. SM will follow up with him / SN/SD/LN / 2017
ECRs - EDUC ,COMMS & WCL / · Computer upgrades pending
o SM requested an updated quote
PC Rollout / · No Issues
Digital Signage Upgrade
When uploading a presentation edit the playlist do not change the schedule / · No issues / SM/SID / 2017
LIBGUIDES / · For more LibGuides issues see web team meeting minutes on Zendesk
Managed Print Services – Minolta / · Signage required regarding print queues for students and pricing, signage to be placed near computers, to be escalated to Minolta
o Waiting for Wits and Minolta for Pricing, still using 2016 pricing
o New signage and pricing between June/July
o Complaint received regarding removal of the machines
· Minolta has visited the Historical Paper regarding the charging of prints – the Minolta have taken the A# paper out and monitoring the situation for a month
· Gugu’s machine prints double everytime he sends a print job – SN has attended to the issue and discovered a corrupt Java instance, he has formatted the machine and re imaged the PC
o Reimaged and tested, machine working fine / SM
LN,SD,SN / Ongoing
Next week
WIREDSPACE / · Ongoing: Report on Web Team Meeting
· WireDspace new link to be circulated - pending / CR, LP, SM / Ongoing
Self-check / · No issues / ES, KS, SM / Ongoing
Wits Digitization Center / · NRF project approved
o Waiting for NRF to sign off
· Request for expansion of storage – issue to be raised in a meeting with new CIO
· SD to check the prices for HDMI expenstion cables – the set up requires an extra high capacity machine and the HDMI will not help solve the problem. CR to discuss with Gabi
· ATOM is not working, LP to check / CR,LP,SD / Next meeting
Content Management System Project / · To see Web Team notes / SID / 2017
Science Library / · The University will build science Library, not confirmed when / CR,SM / On going
Workgroups / Committees LCS participates in
Wits Digital Library & Archives Committee / · Paiki to appoint Chairsperson – Pending date – new chairperson is Nkemeleng Lesejane
· Meeting date still to be given
Network Upgrade Tender (NUT) / · Work has already started UPS installations are being done
Institutional ICT Committee / · The new CIO will be in charge of the meeting / CR
Sierra/LMS
Library Platform / LMS/Sierra / · EDS/Encore
o Quote have been received for Encore Duet, without VAT number – this issue was resolved. A new invoice including VAT was received / ES, CR, KS / Ongoing
General / · Oracle Integration
o ES to send Sierra information (version, workflows) and Oracle information to Daniel (Dimension Data [Brighthouse]) – LCS working on a problem statement that will be presented to Dimension Data for a quote
· Issue about Sierra not handling funds bigger tha 21 million
o Call was logged with Sierra, Sierra do not have a solution for the problem yet
o Escalated to the technical team – to follow up. (pending)
· SM was invited for a meeting, KPMG want to audit the process in terms of Sierra Payments – KPMG now having separate meeting with different stakeholders in the library / ES / CR
ES/KS / Ongoing
Branches
Branches / WCL
· UPS on the 1st floor was not installed due to safety and health issues / Next meeting
LAW
· No issues
· SD: to visit every Tuesday and log a ticket for visit / LN / Next meeting
ARCH
· CR will confirm with Paiki about PC request from Janie / SM / Next meeting
MGMT
· Extra print queues need to be removed / SN/LN/SD / Next meeting
EDUC
· Cameras are ON, campus control will shows us how to get stats report / LN/SD
BIOPHY
· No Issues / LN / Next meeting
WHSL
· Sierra on the overnight section not working / SD
GEOMATHS
· Meeting about the library expanding to Audio/Visual – waiting for first meeting - floor plans received from PIMD – Pending / SN/LN/SD
ENGIN
· Gun scanner not working at the desk / LN / Next meeting
COMM
· New ip camera quotations
o SM : received quote and not happy with it
o Initial agreement was for 3 cameras, now it is including 7 cameras
o Library doesn’t have to pay for other department / SD/SN/LN
WWL
· Neliswa requested two screens for cataloguing staff: Pending, SM to discuss with CR – the screens will be bought
· Data point at ground floor student printers – quote signed, waiting for it to be actioned / LN
SD
SN
SD/SM
General
General Issues / · LCS leave & workshops / training
o KS 25th May
• Storeroom and Workshop
o SD: from May 2017 – Aug 2017
o Any colleague responsible for workroom should ask cleaner to come and vacuum the carpet after staff birthday party or when the carpet is untidy
o Please do not leave wet waste (bones, food, etc.) in the bin in the Workshop, all wet waste must be placed in the kitchen bins
· Help Desk Zendesk:
o Everyone should be checking tickets on the Helpdesk-LCS is short staffed
o Upgrade in text formatting
o Also check the suspended tickets
o CR requested LCS to communicate in a professional and friendly way on Zendesk tickets
o Correspondence needs to be done via helpdesk
o Helpdesk will be audited
o SID to updated Zendesk to show the dates the university was closed
o Customer Relations Management - Awaiting new dates
o If you are going on leave you can transfer your tickets to available agents
o Technicians should close long standing tickets
· 4 LCS reference books have been received and 2 are still outstanding
· There is ants in the bathroom and workshop room. SD to take it up to the OHS&E meeting / SD
SN/SD/LN
SN, SD, LN, ES
Staff Report backs
CR / 02: Tickets
LP / 10: Tickets
KS / 08: Tickets
SM / 04: Tickets
SN / 04: Tickets
SID / 13: Tickets
LN / 12: Tickets
SD / 10: Tickets
ES / 05: Tickets
Next Meeting
LCS minutes scribes: / 30th May 2017
LN _ Feb
SID _ Mar
LP _ Apr
SD _ May
SN _ Jun
KS _ Jul
ES_Aug