Activities/Progress/Travel During this Period

1. In our last report, we stated that the University of Maryland MIPS contract had been signed. Sorry this was not correct. Actually, UMD has not signed the contract because we are still negotiating the inclusion of flow down clauses.

In the appendix are the list of changes that UMD would like us to make before they will accept our flow down clauses. A list of the flow down clauses from the contract is also included in the appendix as well as the Disclosure Limitation clause that will also be flowed down.
Can you please approve these changes? Also if there is anything else we need to include, please let us know.

2. Integrated Positioning: This month we have focused ourefforts on the development of the active radar and orthogonal signal phase delay positioning.

a. Orthogonal Signal Phase Delay Positioning

i. Preliminary tests early in August with some off the shelf components showed that the phase difference of the signal return was measurable on the scale of interest.

ii. We have now completed the theoretical and hardware design for the extraction of the phase difference information.

iii. A key feature of our design is that it does not require clock synchronization and therefore can use less expensive electronics. This is because the signal is sent from the base station (on the fire truck) to the individual unit (on the fire fighter) and then actively sent back. Because the signal makes a round trip there is no need for clock synchronization. In GPS systems, where the signal is sent only in one direction, clock synchronization is an important issue and it increases the price of the electronics.

b. Active Radar

i. We have completed design of output power amplifier and impedance matching networks for the radar transmitter and have begun implementation. We have fabricated the boards and are populating them. We expect to test the boards this week.

ii. We are experimenting with the design systems using ultra wideband Gaussian and wide band chirped signals.

iii. We have also designed and tested in simulation the algorithms for extracting the wide band chirped signal pulse information in the presence of high background noise floor and multipath interference. The simulations give good results.

iv. We have starting to design low noise amplifier and matching networks for the radar receiver.

Plans for Next Reporting Period

1. Continue work on indoor location problem and the Integrated Positioning Technology.

a. Active Radar

i. Continue hardware design and complete implementation of low noise amplifier electronics to send radar pulse.

ii. Continue simulations of the signal properties to maximize range and penetration through building walls.

iii. Continued working on signal processing algorithms to extract radar pulse information in the presence ofhigh background noise floor and multipath interference.

b. Orthogonal Signal Phase Delay Positioning

i. Begin implementation of phase detection methodology.

c. Received Signal Strength

i. Continue working theory for implementation of this location method.

d. Continue work on Biometric Signal Monitoring.

i. Continue development processing algorithms for sensor data.

e. Experiment with patch antenna that will have smaller profile and thus be better suited for the portable units carried by the firefighters. Current antennae are about 15 cm. We need move to a smaller nondescript surface mount profile which will facilitate unencumbered use in the portable transceivers.

f. Prepare for semiannual review.

Issues, Actions, and Recommendations

We need approval from TSWG of the modifications to the flow down clauses before we can put the MIPS contract in place finally.

Financial Summary

See Attachment 1: Financial Status Report (Monthly Expenditures Chart)

Project Schedule Summary

Overall progress to date is AS SCHEDULED in the Project Plan.

Task / Description / Apr / May / Jun / Jul / Aug / Sept / Oct / Nov / Dec / Jan / Feb / Mar / Apr / May / Jun / Jul / Aug / Sept
1 / Indoor location / M11 / M12 / M13 / M14
2 / Biometric signals / M21 / M22 / M23
3 / Multipath / M31 / M32
4 / Communications / M41 / M42 / M43
5 / Modeling / M51 / M52
6 / Scanning locator / M61 / M62
7 / Testing / M71 / M72 / M73 / M74 / M75

Appendix

Changes Requested to MIPs Contract Flow Down Clauses

a.10. FAR 52.204-2, Security Requirements. Please incorporate
Alternate I, appropriate for contracts with educational institutions.
a.15. FAR 52.215-2, Audit and Records - Negotiation. Please
incorporate Alternate II, appropriate for contracts with educational
institutions.
a.48. FAR 52.249-6, Termination. Please delete and replace with FAR
52.249-5, Termination for Convenience of the Governments (Educational
and Other Nonprofit Institutions).
b.2. DFARS 252.204-7000, Disclosure of Information. Please delete
entirely and replace with the TSWG public release language attached.
b.5. DFARS 252-204-7005, Oral Attestation of Security
Responsibilities. Please delete as the University does not conduct
classified research on its campus.

MIPS ContractFlow DownClauses

The following FAR and DFARS clauses are hereby incorporated by reference into this contract.

a. The following contract clauses of the Federal Acquisition Regulation (FAR) (2001 Edition), the full text of which will be made available upon request, are hereby incorporated in this contract by reference with the same force and effect as if set forth in full:

Clause No. /

Title and Date

/ FAR
1 / Definitions (DEC 2001)
( ) Alternate I (MAY 2001) / 52.202-1
2 / Gratuities (APR 1984) / 52.203-3
3 / Covenant Against Contingent Fees (APR 1984) / 52.203-5
4 / Restrictions on Subcontractor Sales to the Government (JUL 1995) / 52.203-6
5 / Anti-Kickback Procedures (JUL 1995) / 52.203-7
6 / Cancellation, Recission and Recovery of Funds for Illegal or Improper Activity (JAN 1997) / 52.203-8
7 / Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) / 52.203-10
8 / Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (APR 1991) / 52.203-11
9 / Limitation on Payments to Influence Certain Federal Transactions (JUN 1997) / 52.203-12
10 / Security Requirements (APR 1996)
( ) Alternate I (APR 1984)
( ) Alternate II (APR 1984) / 52.204-2
11 / Printing/Copying Double-Sided on Recycled Paper (AUG 2000) / 52.204-4
12 / Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended or Proposed for Debarment (JUL 1995) / 52.209-6
13 / Material Requirements (AUG 2000) / 52.211-5
14 / Defense Priority and Allocation Requirements (SEP 1990) / 52.211-15
15 / Audit and Records – Negotiation(JUN 1999)
( ) Alternate I (JAN 1997)
( ) Alternate II (APR 1998)
( ) Alternate III (JUN 1999) / 52.215-2
16 / Order of Precedence—Uniform Contract Format (OCT 1997) / 52.215-8
17 / Allowable Cost and Payment (FEB 2002)
Educational Institutions – change “31.2” to “31.3”
State and Local Governments – change “31.2” to “31.4”
For All Other Nonprofits – change “31.2” to “31.7”
( ) Alternate I (FEB 1997) / 52.216-7
18 / Utilization of Small Business Concerns (OCT 2000) / 52.219-8
19 / Notice to the Government of Labor Disputes (FEB 1997) / 52.222-1
20 / Contract Work Hours and Safety Standards Act—Overtime Compensation (SEP 2000) / 52.222-4
21 / WalshHealey Public Contracts Act (DEC 1996) / 52.222-20
22 / Prohibition of Segregated Facilities (FEB 1999) / 52.222-21
23 / Equal Opportunity (APR 2002)
( ) Alternate I (FEB 1999) / 52.222-26
24 / Affirmative Action for Disabled Veterans and Veterans of the Vietnam Era (DEC 2001) / 52.222-35
25 / Affirmative Action for Workers with Disabilities (JUN 1998) / 52.222-36
26 / Employment Reports on Disabled Veterans and Veterans of the Vietnam Era (DEC 2001) / 52.222-37
27 / Drug-Free Workplace (MAY 2001) / 52.223-6
28 / Toxic Chemical Release Reporting (OCT 2000) / 52.223-14
29 / Restrictions on Certain Foreign Purchases (JUL 2000) / 52.225-13
30 / Notice and Assistance Regarding Patent Copyright Infringement (AUG 1996) / 52.227-2
31 / Filing of Patent Applications—Classified Subject Matter (APR 1984) / 52.227-10
32 / Insurance—Liability to Third Persons (MAR 1996) / 52.228-7
33 / Limitation on Withholding of Payments (APR 1984) / 52.232-9
34 / Interest (JUN 1996) / 52.232-17
35 / Assignment of Claims (JAN 1986)
( ) Alternate I (APR 1984) / 52.232-23
36 / Prompt Payment (FEB 2002) / 52.232-25
37 / Disputes (JUL 2002)
(X) Alternate I (DEC 1991) / 52.233-1
38 / Protest After Award (AUG 1996)
(X) Alternate I (JUN 1985) / 52.233-3
39 / Notice of Intent to Disallow Costs (APR 1984) / 52.242-1
40 / Bankruptcy (JUL 1995) / 52.242-13
41 / Stop-Work Order (AUG 1989)
(X) Alternate I (APR 1984) / 52.242-15
42 / Subcontracts (AUG 1998)
(X) Alternate I (AUG 1998)
( ) Alternate II (AUG 1998) / 52.244-2
43 / Competition in Subcontracting (DEC 1996) / 52.244-5
44 / Government Property (Cost-Reimbursement, Time and Material, or Labor Hour Contracts) (DEVIATION) (JAN 1986)
( ) Alternate I (JUL 1985) / 52.245-5
45 / Use and Charges (DEVIATION) (APR 1984) / 52.245-9
46 / Commercial Bill of Lading Notations (APR 1984) / 52.247-1
47 / Preference for U.S.-Flag Air Carriers (JAN 1997) / 52.247-63
48 / Termination (Cost Reimbursement) (SEP 1996)
( ) Alternate I (SEP 1996) (construction)
( ) Alternate II (SEP 1996) (contract with fed agency/S/L govt)
( ) Alternate III (SEP 1996) (fed agency/S/L govt – construction)
( ) Alternate IV (SEP 1996) (T&M/LH only)
( ) Alternate V (SEP 1996) (T&M/LH with fed agency/S/L govt) / 52.249-6
49 / Excusable Delays (APR 1984) / 52.249-14
50 / Solicitation Provisions Incorporated by Reference (FEB 1998) ( / 52.252-1
51 / Clauses Incorporated by Reference (FEB 1998) / 52.252-2
52 / Computer Generated Forms (JAN 1991) / 52.253-1

b. The following contract clauses of the Department of Defense FAR Supplement (1998 Edition), the full text of which will be made available upon request, are hereby incorporated in this contract by reference with the same force and effect as if set forth in full:

Clause No. / Title and Date / DFARS
1 / Prohibition on Persons Convicted of Fraud or Other Defense Contract Related Felonies (MAR 1999) / 252.203-7001
2 / Disclosure of Information (DEC 1991) / 252.204-7000
3 / Control of Government Personnel Work Product (APR 1992) / 252.204-7003
4 / Required Central Contractor Registration (NOV 2001) / 252.204-7004
5 / Oral Attestation of Security Responsibilities (NOV 2001) / 252.204-7005
6 / Acquisition From Subcontractors Subject to On-Site Inspection Under the Intermediate-Range Nuclear Forces (INF) Treaty (NOV 1995) / 252.209-7000
7 / Subcontracting With Firms That Are Owned or Controlled by the Government of a Terrorist Country (MAR 1998) / 252.209-7004
8 / Preference for Certain Domestic Commodities (FEB 2003) / 252.225-7012
9 / Secondary Arab Boycott of Israel (APR 2003) / 252.225-7031
10 / Utilization of Indian Organizations and Indian-Owned Economic Enterprises—DoD Contracts (SEP 2001) / 252.226-7001
11 / Rights in Technical Data—Noncommercial Items (NOV 1995) / 252.227-7013
12 / Rights in Noncommercial Computer Software and Noncommercial Computer Software Documentation (JUN 1995)
( ) Alternate I (JUN 1995) / 252.227-7014
13 / Rights in Bid or Proposal Information (JUN 1995) / 252.227-7016
14 / Identification and Assertion of Use, Release, or Disclosure Restrictions (JUN 1995) / 252.227-7017
15 / Validation of Asserted Restrictions—Computer Software (JUN 1995) / 252.227-7019
16 / Limitations on the Use or Disclosure of Government-Furnished Information (JUN 1995) / 252.227-7025
17 / Deferred Delivery of Technical Data or Computer Software (APR 1988) / 252.227-7026
18 / Deferred Ordering of Technical Data or Computer Software (APR 1988) / 252.227-7027
19 / Technical Data or Computer Software Previously Delivered to the Government (JUN 1995) / 252.227-7028
20 / Technical Data - Withholding of Payment (MAR 2000) / 252.227-7030
21 / Declaration of Technical Data Conformity (JAN 1997) / 252.227-7036
22 / Validation of Restrictive Markings on Technical Data (SEP 1999) / 252.227-7037
23 / Supplemental Cost Principles (DEC 1991) / 252.231-7000
24 / Post Award Conference (DEC 1991) / 252.242-7000
25 / Requests for Equitable Adjustment (MAR 1998) / 252.243-7002
26 / Reports of Government Property (MAY 1994) / 252.245-7001
27 / Material Inspection and Receiving Report (DEC 1991) / 252.246-7000

c. The following contract clauses of the Federal Acquisition Regulation (FAR) (2001 Edition), the full text of which will be made available upon request, are hereby incorporated in this contract by reference with the same force and effect as if set forth in full when the clause is preceded by an "X" in the "Effect" column (clauses preceded by "N/A" are inapplicable to this acquisition):

Clause No. /

Effect

/ Title and Date / FAR
1 / N/A / Changes or Additions to Make-or-Buy Program (OCT 1997)
( ) Alternate I (OCT 1997)
( ) Alternate II (OCT 1997) / 52.215-9
2 / N/A / Price Reduction for Defective Cost or Pricing Data (OCT 1997) / 52.215-10
3 / N/A / Price Reduction for Defective Cost or Pricing Data—Modifications (OCT 1997) / 52.215-11
4 / N/A / Subcontractor Cost or Pricing Data (OCT 1997) / 52.215-12
5 / N/A / Subcontractor Cost or Pricing Data—Modifications (OCT 1997) / 52.215-13
6 / N/A / Integrity of Unit Prices (OCT 1997)
() Alternate I (OCT 1997) / 52.215-14
7 / N/A / Pension Adjustments and Asset Reversions (DEC 1998) / 52.215-15
8 / N/A / Facilities Capital Cost of Money (OCT 1997) / 52.215-16
9 / XX / Waiver of Facilities Capital Cost of Money (OCT 1997) / 52.215-17
10 / N/A / Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other than Pensions (OCT 1997) / 52.215-18
11 / XX / Notification of Ownership Changes (OCT 1997) / 52.215-19
12 / XX / Requirements for Cost or Pricing Data or Information Other than Cost or Pricing Data (OCT 1997)
( ) Alternate I (OCT 1997) (see proposal instructions for format)
( ) Alternate II (OCT 1997) (see instructions for ACO/Auditor addresses)
( ) Alternate III (OCT 1997) (applies if submission by electronic media is required)
( ) Alternate IV (OCT 1997) (SF1411 not required; information other than cost or pricing data is required) / 52.215-20
13 / XX / Requirements for Cost or Pricing Data or Information Other than Cost or Pricing Data—Modifications (OCT 1997)
( ) Alternate I (OCT 1997) (see proposal instructions for format)
( ) Alternate II (OCT 1997) (see instructions for ACO/Auditor addresses)
( ) Alternate III (OCT 1997) (applies if submission by electronic media is required)
( ) Alternate IV (OCT 1997) (SF1411 not required; information other than cost or pricing data is required) / 52.215-21
14 / XX / Fixed Fee (MAR 1997) / 52.216-8
15 / N/A / Incentive Fee (MAR 1997) / 52.216-10
16 / N/A / Cost Contract—No Fee (APR 1984) / 52.216-11
17 / N/A / Cost Sharing Contract—No Fee (APR 1984) / 52.216-12
18 / N/A / Small Business Subcontracting Plan (JAN 2002)
( ) Alternate I (OCT 2001)
( ) Alternate II (OCT 2001) / 52.219-9
19 / N/A / Liquidated Damages—Subcontracting Plan (JAN 1999) / 52.219-16
20 / N/A / Small Disadvantaged Business Participation Program—Disadvantaged Status and Reporting (OCT 1999) / 52.219-25
21 / XX / Payment for Overtime Premiums (JUL 1990)
The overtime premium is ZERO. / 52.222-2
22 / XX / Convict Labor (AUG 1996) / 52.222-3
23 / N/A / Notification of Visa Denial (FEB 1999) / 52.222-29
24 / XX / Pollution Prevention and Right-to-Know Information (APR 1998) / 52.223-5
25 / N/A / Utilization of Indian Organizations and Indian-Owned Economic Enterprises (JUN 2000) / 52.226-1
26 / N/A / Patent Indemnity (APR 1984) / 52.227-3
27 / XX / Patent Rights–Retention by the Contractor (Short Form) (JUN 1997) / 52.227-11
28 / N/A / Patent Rights–Retention by the Contractor (Long Form) (JAN 1997) / 52.227-12
29 / N/A / Patent Rights—Acquisition by the Government (JAN 1997) / 52.227-13
30 / N/A / Additional Bond Security (OCT 1997) / 52.228-2
31 / N/A / Workers' Compensation Insurance (Defense Base Act) (APR 1984) / 52.228-3
32 / N/A / Taxes—Foreign Cost-Reimbursement Contracts (MAR 1990) / 52.229-8
33 / N/A / Cost Accounting Standards (APR 1998) / 52.230-2
34 / N/A / Disclosure and Consistency of Cost Accounting Practices (APR 1998) / 52.230-3
35 / N/A / Consistency in Cost Accounting Practices (AUG 1992) / 52.230-4
36 / N/A / Cost Accounting Standards—Educational Institution (APR 1998) / 52.230-5
37 / N/A / Administration of Cost Accounting Standards (NOV 1999) / 52.230-6
38 / XX / Limitation of Cost (APR 1984) / 52.232-20
39 / N/A / Limitation of Funds (APR 1984) / 52.232-22
40 / XX / Payment by Electronic Funds Transfer—Central Contractor Registration (MAY 1999) / 52.232-33
41 / N/A / Payment by Electronic Funds Transfer—Other Than Central Contractor Registration (MAY 1999) / 52.232-34
42 / N/A / Protection of GovernmentBuildings, Equipment and Vegetation (APR 1984) / 52.237-2
43 / N/A / Privacy or Security Safeguards (AUG 1996) / 52.239-1
44 / XX / Penalties for Unallowable Costs (MAY 2001) / 52.242-3
45 / XX / Certification of Final Indirect Costs (JAN 1997) / 52.242-4
46 / N/A / F.O.B. Origin—Government Bills of Lading or Prepaid Postage (APR 1984) / 52.242-10
47 / N/A / F.O.B. Origin—Government Bills of Lading or Indicia Mail (FEB 1993) / 52.242-11
48 / N/A / Report of Shipment (REPSHIP) (JUL 1995) / 52.242-12
49 / XX / Subcontracts for Commercial Items (DEC 2000) / 52.244-6
50 / N/A / Special Test Equipment (FEB 1993) / 52.245-18
51 / N/A / Higher Level Contract Quality Requirement (FEB 1999) / 52.246-11
52 / N/A / Certificate of Conformance (APR 1984) / 52.246-15
53 / XX / Limitation of Liability (FEB 1997) / 52.246-23
54 / N/A / Preference for Privately Owned U.S. Flag Commercial Vessels (JUN 2000) / 52.247-64
55 / N/A / Value Engineering (FEB 2000)
( ) Alternate I (APR 1984)
( ) Alternate II (FEB 2000)
( ) Alternate III (APR 1984) / 52.248-1
56 / N/A / Termination for Convenience of the Government (Educational and Other Nonprofit Institutions) (SEP 1996) / 52.249-5
57 / XX / Government Supply Sources (APR 1984) / 52.251-1
58 / N/A / Interagency Fleet Management System Vehicles and Related Services (JAN 1991) / 52.251-2

d. The following contract clauses of the Department of Defense FAR Supplement (1998

Edition), the full text of which will be made available upon request, are hereby incorporated in this contract by reference with the same force and effect as if set forth in full when the clause is preceded by an "X" in the "Effect" column (clauses preceded by "N/A" are inapplicable to this acquisition):

Clause No. /

Effect

/ Title and Date / DFARS
1 / N/A / Display of DOD Hotline Poster (DEC 1991) / 252.203-7002
2 / N/A / Payment for Subline Items Not Separately Priced (DEC 1991) / 252.204-7002
3 / N/A / Intent to Furnish Precious Metals as Government-Furnished Material (DEC 1991) / 252.208-7000
4 / XX / Reserve Officers Training Corps and Military Recruiting on Campus (JAN 2000) / 252.209-7005
5 / XX / Pricing Adjustments (DEC 1991) / 252.215-7000
6 / N/A / Cost Estimating System Requirements (OCT 1998) / 252.215-7002
7 / N/A / Small, Small Disadvantaged and Women-Owned Small Business Subcontracting Plan (DOD Contracts) (APR 1996) / 252.219-7003
8 / N/A / Hazard Warning Labels (DEC 1991) / 252.223-7001
9 / N/A / Safety Precautions for Ammunition and Explosives (MAY 1994) / 252.223-7002
10 / N/A / Change in Place of Performance—Ammunition and Explosives (DEC 1991) / 252.223-7003
11 / XX / Prohibition on Storage and Disposal of Toxic and Hazardous Materials (APR 1993) / 252.223-7006
12 / N/A / Safeguarding Sensitive Conventional Arms, Ammunition, and Explosives (SEP 1999) / 252.223-7007
13 / N/A / Buy American Act—Balance of Payments Program Certificate (SEP 1999) / 252.2257000
14 / N/A / Buy American Act—Balance of Payments Program (MAR 1998) / 252.225-7001
15 / N/A / Qualifying Country Sources as Subcontractors (DEC 1991) / 252.225-7002
16 / N/A / Buy American Act—Trade Agreements—Balance of Payments Program Certificate (MAR 1998) / 252.225-7006
17 / N/A / Buy American Act—Trade Agreements—Balance of Payments Program (SEP 2001) / 252.225-7007
18 / N/A / Supplies to be Accorded Duty-Free Entry (MAR 1998) / 252.225-7008
19 / N/A / Duty-Free Entry—Qualifying Country Supplies (End Products and Components) (AUG 2000) / 252.225-7009
20 / N/A / Duty-Free Entry—Additional Provisions (AUG 2000) / 252.225-7010
21 / N/A / Preference for Domestic Specialty Metals (MAR 1998)
( ) Alternate I (MAR 1998) / 252.225-7014
22 / N/A / Restriction on Acquisition of Ball and Roller Bearings (DEC 2000) / 252.225-7016
23 / N/A / Trade Agreements (SEP 2001) / 252.225-7021
24 / N/A / Restriction on Acquisition of Polyacrylonitrile (PAN) Carbon Fiber (JUN 1997) / 252.225-7022
25 / N/A / Restrictions on Acquisition of Forgings (JUN 1997) / 252.225-7025
26 / N/A / Reporting of Contract Performance Outside the United States (JUN 2000) / 252.225-7026
27 / N/A / Preference for United States or Canadian Air Circuit Breakers (AUG 1998) / 252.225-7029
28 / N/A / Restriction on Acquisition of Carbon, Alloy, and Armor Steel Plate (OCT 1992) / 252.225-7030
29 / N/A / Waiver of United Kingdom Levies (OCT 1992) / 252.225-7032
30 / N/A / Buy American Act—North American Free Trade Agreement Implementation Act—Balance of Payments Program Certificate (MAR 1998) / 252.225-7035
31 / N/A / Buy American Act—North American Free Trade Agreement Implementation Act—Balance of Payments Program (MAR 1998) / 252.225-7036
32 / N/A / Duty-Free Entry—Eligible End Products (AUG 2000) / 252.225-7037
33 / N/A / Antiterrorism/Force Protection for Defense Contractors Outside the United States (JUN 1998) / 252.225-7043
34 / N/A / Rights in Special Works (JUN 1995) / 252.227-7020
35 / N/A / Rights in Data - Existing Works (MAR 1979) / 252.227-7021
36 / XX / Patents—Subcontracts (APR 1984) / 252.227-7034
37 / XX / Patents—Reporting of Subject Inventions (APR 1990) / 252.227-7039
38 / N/A / Aircraft Flight Risk (SEP 1996) / 252.228-7002
39 / N/A / Accident Reporting and Investigation Involving Aircraft, Missiles and Space Launch Vehicles (DEC 1991) / 252.228-7005
40 / N/A / Notice of Earned Value Management System (MAR 1998) / 252.234-7000
41 / N/A / Earned Value Management System (MAR 1998) / 252.234-7001
42 / N/A / Indemnification Under 10 U.S.C. 2354—Cost Reimbursement (DEC 1991) / 252.235-7001
43 / N/A / Frequency Authorization (DEC 1991) / 252.235-7003
44 / N/A / Protection Against Compromising Emanations (DEC 1991) / 252.239-7000
45 / N/A / Telecommunications Security Equipment, Devices, Techniques and Services (DEC 1991) / 252.239-7016
46 / N/A / Material Management and Accounting System (DEC 2000) / 252.242-7004
47 / XX / Cost/Schedule Status Report (MAR 1998) / 252.242-7005
48 / N/A / Cost/Schedule Status Report Plans (MAR 1997) / 252.242.7006
49 / XX / Subcontracts for Commercial Items and Commercial Components (DoD Contracts) (MAR 2000) / 252.244-7000
50 / N/A / Government-Furnished Mapping, Charting and Geodesy Property (DEC 1991) / 252.245-7000
51 / N/A / Warranty of Data (DEC 1991) / 252.246-7001
52 / XX / Transportation of Supplies by Sea (MAR 2000) / 252.247-7023
53 / XX / Notification of Transportation of Supplies by Sea (MAR 2000) / 252.247-7024
54 / XX / Ordering From Government Supply Sources (MAY 1995) / 252.251.7000

Disclosure Limitation clause

Figure 1