III.Executive Summary

The Public Education Capital Outlay (PECO) USF Polytechnic Phase I project is being augmented by other funding sources. Those funds include the Capital Improvement Trust Fund (CITF) which is allocated to the students at State Universities, privately raised funds, and the related matching funds from the Facility Enhancement Challenge Grant (FECG). The campus Master Plan called for Phase I to consist of 150,000 gross square feet (100,000 net square feet) of academic, teaching, student support, research, and administrative spaces. The approved state funding allocated to USF Polytechnic for Phase I was reduced from the requested $65 million to $35 million, therefore reducing the square footage to approximately 90,000 gross square feet (60,000 net square feet). Utilizing the additional resources outlined above, gives the project the potential to increase the square footage of the project as well as augment specific elements beyond those dictated by formulae for the PECO funds.

The USF Polytechnic is expected to be a significant generator of economic growth and development in the central Florida region. Community interest in the impact of this synergistic engine has resulted in several private gifts being received for the enhancement of the Phase I project. These contributions qualify for matching funds through the FECG. As of July 2008, a total of $10.5 million has been received or pledged and what has been received has been submitted for match. Several other gifts are anticipated with all of them qualifying to apply for match. It is anticipated that the campus will have approximately $25 million available to support the special needs of the project.

The location of the new campus site places it in a pivotal position to provide the “front door” to both Orlando and Tampa Bay for those traveling either eastbound or westbound (respectively) on Interstate 4 in addition to providing the “face” for USF Polytechnic’s community service area as well as all of Central Florida. Designing a facility that speaks to this unique opportunity is critical to portraying this message. It is a goal of the project to engage a signature architect (“starchitect”) to create this icon. The costs associated with such an endeavor are not able to be borne by the limitations of the formulae that dictate the use of PECO funds. Therefore, the private funds can provide the avenue by which this goal can be accomplished. In addition, it is hoped that the project can yield a facility more in line with the sizes proposed in the original plan.

The Facilities Program Subcommittee (the Facility Program Workgroup) worked to determine the needs for academic, teaching, student support, research and administrative spaces beyond the limits presented by the PECO funding but necessary to develop a viable polytechnic campus.

This supplemental document outlines those additional spaces to include the types and numbers of spaces desired, purposes for the spaces, the sizes of the spaces, special needs or requests, technology, and any other information pertinent to a potential vendor.

This document, Facilities Program Phase IB, provides supplemental information for Sections 3, 9, 14 and 15 of the Facilities Program Phase IA. The information outlined in the other Sections of the Facilities Program Phase IA (summarized below) also applies to this supplemental document.

  • Section 2 – The Facilities Program Steering Committee is comprised of faculty, administration and staff from both the Tampa and Polytechnic campuses as well as the community; the Workgroup membership is also identified.
  • Section 3 – Executive Summary.
  • Section 4 – The Introduction reviews background of both the University and the campus, the project history; a description of the “Commons” concept is presented; information about the project, goals and objectives, construction delivery method.
  • Section 5 – This section provides a review of the programs that will be resident on the new campus once completed as well as those that will remain housed on the current USF/PCC campus.
  • Section 6 – The Space Needs Assessment provides the Construction Improvement Plan (CIP) documents submitted by the University that show their priority of projects.
  • Section 7 – The Facilities Program must reflect consistency with the Master Plans of both the University and of the Campus; it must also align with the Campus Development Agreement and the Campus Strategic Plan.
  • Section 8 – The information needed to provide site conditions including maps gives the potential professional teams clear and detailed data from which to work.
  • Section 9 – Spaces are outlined in detail so as to reflect the needs and requirements for each space type; these include academic, student services, learning and classroom commons areas beyond those reflected in the Facilities Program Phase IA.
  • Section 10 – Utilities impacts are outlined and analyzed; maps are provided to further assure accuracy.
  • Section 11 – Information is provided to assure that university standards are met.
  • Section 12 – The identification of building code, fire code, life safety, etc. are provided for clear information.
  • Section 13 – The schedule of critical tasks is updated as new information becomes available.

Section 14 – The schedule of sources of funding for the project.

  • Section 15 – Actual budget for the Private and FECG funding is defined in terms of the overall anticipated dollars available.

USF Polytechnic – Phase IB7/28/08

SECTION III

1

Facilities Program – PHASE IB / USF Polytechnic

IX.Program Tabulation and Description

Phase IB - Private & Matching Grant Funding

  1. Program Table Summary

Area / Name / Estimated
NSF (+/-)
CR / Classroom / 0
TL / Teaching Lab / 0
SY / Study / 6,980
RL / Research Lab / 0
OC / Office/Computer / 15,034
IM / Instructional Media / 3,330
CS / Campus Support / 1,300
OA / Other Assignable / 3,205
Student / Student Areas / 0
SUBTOTAL / 29,849
Shell / Shell Space / 20,000
GRAND TOTAL / 49,849
  1. Space Description Forms

Space Description Form _SY-8__

SPACE NUMBER
Department: / Shared Library/ERDC/TLT
Area: / Academic
Space Name: / STUDENT PROJECT LAB
Description / Use:
SUS Space Category: / Study / Room Use Code: / 420
Personnel Assigned / Max.: / 10
Dimension / Area: / +/- 500 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Learning Commons
Secondary:
ARCHITECTURAL CRITERIA
Floors: / Carpet; 6” raised flooring
Walls: / Glass (partitions)
Ceilings: / Acoustical tile
Doors: / Glass
Windows: / Natural light; treatment
Lighting: / Indirect, uniform, controlled/flexible; some spot; low energy fixtures
Acoustical: / Controlled
MECHANICAL CRITERIA
HVAC: / Additional capacity due to computers and equipment
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110V wall and floor (recessed) mounted
FURNITURE/EQUIPMENT
Furniture (Owner): / Work station (10) and chairs
Equipment (Owner): /
  • Computers (10)
  • Scanners
  • Image/video editing software

Furniture (Contractor): /
  • PC & MACs
  • Plasma
  • Headphones

Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS
Enclosed room

Space Description Form _SY-9__

SPACE NUMBER
Department: / Library
Area: / Academic
Space Name: / GROUP STUDY ROOM
Description / Use: / Group Study Room/presentation practice rooms
SUS Space Category: / Study / Room Use Code: / 410
Personnel Assigned / Max.: / 6
Dimension / Area: / +/- 120 NSF
Number Required: / 3
RELATIONSHIP TO OTHER AREAS
Primary: / Learning Commons
Secondary:
ARCHITECTURAL CRITERIA
Floors: / Carpet; 6” raised flooring
Walls: / Glass and painted sheetrock
Ceilings: / Acoustical tile
Doors: / Glass
Windows:
Lighting: / Indirect, uniform, controlled/flexible; some spot; low energy fixtures
Acoustical: / Controlled
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110V wall and floor (recessed) mounted
FURNITURE/EQUIPMENT
Furniture (Owner): /
  • Table
  • 4 chairs

Equipment (Owner): /
  • Whiteboard
  • Projector/computer or Plasma
  • Podium

Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _SY-10____

SPACE NUMBER
Department: / Library
Area: / Academic
Space Name: / QUIET STUDY
Description / Use: / Quiet Study area
SUS Space Category: / Study / Room Use Code: / 410
Personnel Assigned / Max.: / 18
Dimension / Area: / +/- 720 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Learning Commons
Secondary:
ARCHITECTURAL CRITERIA
Floors: / Carpet; 6” raised flooring
Walls: / Glass
Ceilings: / Acoustical tile
Doors: / Glass
Windows: / Natural light; treatment
Lighting: / Indirect, uniform, controlled/flexible; some spot; low energy fixtures
Acoustical: / Very good – controlled
MECHANICAL CRITERIA
HVAC: / yes
Plumbing: / no
Data/Communications: / Wired and wireless data/phone
Electrical: / 110V wall and floor (recessed) mounted
FURNITURE/EQUIPMENT
Furniture (Owner): /
  • Tables and chairs (3)
  • Lounge chairs (6)
  • Corner tables (3)

Equipment (Owner): / Computer (2)
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS
Long tables or carrels
Closed off

Space Description Form _SY-11__

SPACE NUMBER
Department: / Shared Learning Commons
Area: / Academic
Space Name: / LEARNING COMMONS
Description / Use: / Student Reading Room
SUS Space Category: / Study / Room Use Code: / 410
Personnel Assigned / Max.: / 150
Dimension / Area: / +/- 5400 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Work Commons
Secondary: / SGA
ARCHITECTURAL CRITERIA
Floors: / Carpet tile
Walls: / Glass
Ceilings: / Acoustical tile
Doors: / Glass – main double door is sliding
Windows: / Natural light; treatment; some view from offices into Learning Commons
Lighting: / Indirect, uniform, controlled/flexible; some spot; low energy fixtures
Acoustical: / controlled
MECHANICAL CRITERIA
HVAC: / Additional capacity due to computers and equipment
Plumbing: / Yes, for restroom
Data/Communications: / Wired and wireless data/phone. Showcased IDF closet w/ 2 rack capacity. Per tech recommendations & University IT Specifications
Electrical: / 110V wall and floor (recessed) mounted per code. Provide power for each workstation/seat. IDF requires 120/208V power access for UPSs and should be redundant via generator.
FURNITURE/EQUIPMENT
Furniture (Owner): / Computer pods, tables, chairs, lounge chairs, end tables
Equipment (Owner): / Staff computers (4), public computers), 4 printers (BW and color), photocopier/scanner, security gates, library stacks (compact). LAN equipment wireless equipment
Furniture (Contractor): / Custom desks w/ built-in wire management and power.
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS
  • Multi-use dynamic space with integrated technology (tables with computers, capacity for laptops, mobile laptop stations, mobile whiteboards)
  • Individual and group work space
  • Public access workstations (5 computers)
  • Info desk, (help desk), check out desk - 4 people – secure storage space (electronic access)
  • Book drop in wall behind circulation desk
  • One entrance point only – with other emergency-only exits, alarmed
  • Public restrooms – handicapped accessible
  • Lots of natural light
  • Glass wall to interior lobby/corridor for showcasing
  • Sightlines open from the help desk
  • 12” drop floor in lab area
  • PA System
  • Workstations (60) spread out in clusters/pods
  • Central will be copier/fax/scanner/printers

Space Description Form _OC-23__

SPACE NUMBER
Department: / Administration
Area: / Support
Space Name: / MEETING ROOM
Description / Use:
SUS Space Category: / Office Computer / Room Use Code: / 350
Personnel Assigned / Max.: / 20
Dimension / Area: / +/- 400 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Reception area
Secondary: / Lobby
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls: / Flat, even surfaces where possible, height TBD, acoustical treatment on upper areas, tack-able metal picture rail
Ceilings: / NRC 0.75, height TBD
Doors: / Solid
Windows: / Treatment and tinted
Lighting: / Indirect, uniform, controlled/flexible (multi-bank)
Acoustical: / Ambient noise 35 dBA
MECHANICAL CRITERIA
HVAC: / 15 CFM/ person outside air; standard 62-04 exhaust air
Plumbing: / No
Data/Communications: / (4) Wired and wireless data/phone
Electrical: / 1 quad and multiple duplex 110 V wall and floor (recessed) mounted
FURNITURE/EQUIPMENT
Furniture (Owner): / Lectern, 4 tables and stackable chairs (20) each “For Large”
Equipment (Owner): / Two digital display units
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _OC-24____

SPACE NUMBER
Department: / Administration
Area: / Support
Space Name: / Administrator/CEO
Description / Use:
SUS Space Category: / Office/Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 1
Dimension / Area: / +/- 400 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Small Meeting Room, Special Assistant
Secondary: / Receptionist, Large Meeting Room
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls: / Painted sheetrock
Ceilings: / Acoustical tile
Doors: / Solid core wood
Windows: / Solar control
Lighting: / Natural light and low energy light fixtures
Acoustical: / Good
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110 V
FURNITURE/EQUIPMENT
Furniture (Owner): / Desk with credenza; office chair; two side chairs; bookcase; file cabinet; love seat; two soft chairs; coffee table with 2 end tables
Equipment (Owner): / Computer, Laptop Computer, Phone, Printer
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _OC-25__

SPACE NUMBER
Department: / Administration
Area: / Support
Space Name: / AVP/ADMINISTRATOR
Description / Use:
SUS Space Category: / Office/Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 1
Dimension / Area: / +/- 250 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Special Assistant
Secondary: / Other Offices
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls: / Painted sheetrock
Ceilings: / Acoustical tile
Doors: / Solid core wood
Windows: / Solar control
Lighting: / Natural light and low energy light fixtures
Acoustical: / Good
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110 V
FURNITURE/EQUIPMENT
Furniture (Owner): / Desk with credenza; two side chairs; office chair, bookcase, file cabinet, small oblong table, 6 visitor chairs
Equipment (Owner): / Computer, Laptop Computer, Printer, Phone
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _OC-26__

SPACE NUMBER
Department: / Administration
Area: / Support
Space Name: / SPECIAL ASSISTANT
Description / Use:
SUS Space Category: / Office/Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 1
Dimension / Area: / +/- 130 NSF
Number Required: / 2
RELATIONSHIP TO OTHER AREAS
Primary: / Administrator/CEO and/or AVP/Administrator
Secondary: / Other Offices
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls: / Painted sheetrock
Ceilings: / Acoustical tile
Doors: / Solid core wood
Windows: / Solar control
Lighting: / Natural light and low energy light fixures
Acoustical: / Good
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110 V
FURNITURE/EQUIPMENT
Furniture (Owner): / Workstation (desk and table), chair, bookcase, file cabinet, small table, 2 visitor chairs
Equipment (Owner): / Computer, Printer, Scanner, Phone
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _OC-27___

SPACE NUMBER
Department: / Library
Area: / Administrative
Space Name: / LIBRARY OFFICE SUITE
Description / Use: / Offices
SUS Space Category: / Office Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 4
Dimension / Area: / +/- 500 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Work Commons
Secondary: / Learning Commons
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls:
Ceilings: / Acoustical tile
Doors: / Solid wood
Windows:
Lighting: / Controlled at entry; spot lighting on desks; low energy fixtures
Acoustical:
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / No
Data/Communications: / Wired and wireless data/phone
Electrical: / 110V
FURNITURE/EQUIPMENT
Furniture (Owner): / Director Faculty Staff
Desk, file cabinet, desk, file cabinet desk, file cabinet
Seating for 2, bookcase seating for 1, bookcase seating for 1
Single-face Library stack Single-face Library
stack
Equipment (Owner): / Phones, computers (5)
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS

Space Description Form _OC-28__

SPACE NUMBER
Department: / Teaching and Learning Technologies
Area: / Academic
Space Name: / TLT SUITE
Description / Use: / Faculty development, technology integration
SUS Space Category: / Office Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 4
Dimension / Area: / +/- 820 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Information/Learning Commons
Secondary:
ARCHITECTURAL CRITERIA
Floors: / Carpet
Walls: / Comply with University Standards
Ceilings: / Acoustical tile
Doors: / Solid Core Wood
Windows: / Aluminum Frame
Lighting: / Lighting shall be controlled at the entry to each space
Acoustical: / Per University Standard
MECHANICAL CRITERIA
HVAC: / Per code
Plumbing: / Per code
Data/Communications: / Wireless and hard wired data jacks (2 per each room)
Electrical: / Per code
FURNITURE/EQUIPMENT
Furniture (Owner): ? / Director’s space 2 – GA space 1- support
Desk, Files, bookcase Double seating desks Desk
Seating Bookcase File cabinet
File cabinet Bookcase
Equipment (Owner): ? / 6 – Laptops, 6 Phones, Scanners (desktop)
Furniture (Contractor):
Equipment (Contractor):
SUPPLEMENTAL INFORMATION/REQUIREMENTS
Appearance – open view between and amongst offices

Space Description Form _OC-29__

SPACE NUMBER
Department: / Multiple
Area: / Administrative
Space Name: / ACADEMIC COMMONS
Description / Use: / Office, meeting, support & collaborative space for academic functions
SUS Space Category: / Office/Computer / Room Use Code: / 310
Personnel Assigned / Max.: / 53 (49 plus 4 adjuncts)
Dimension / Area: / +/- 9434 NSF
Number Required: / 1
RELATIONSHIP TO OTHER AREAS
Primary: / Classroom and Information Commons
Secondary: / Research Laboratories
ARCHITECTURAL CRITERIA
Floors: / Carpeting
Walls: / Acoustically absorbent
Ceilings: / Acoustically absorbent
Doors: / See description
Windows: / See description
Lighting: / Piped sunlight / soft fluorescents
Acoustical: / Acoustically absorbent, non-reflective surface where possible
MECHANICAL CRITERIA
HVAC: / Yes
Plumbing: / Indoor
Data/Communications: / 10Gb wired; high data rate wireless, portable (wireless fallback) IP phones
Electrical: / Floor sockets for electrical and data. Wall sockets positioned for noninterference with sliding doors. Ceiling sockets in collaborative area for installation of wireless access points ands other electronic equipment
FURNITURE/EQUIPMENT
Furniture (Owner): / Chairs, meeting tables
Equipment (Owner): / Phones, computer systems, laptop docking stations, document storage/retrieval system, content preparation/delivery equipment suites, IP cameras, networking support equipment
Furniture (Contractor): / Built-in faculty/staff desks, permanent shades/blinds, built-in equipment desks for course preparation/delivery areas
Equipment (Contractor): / Lighting, data and electrical wiring, HVAC, plumbing
SUPPLEMENTAL INFORMATION/REQUIREMENTS
See Section IV – Introduction for descriptive narrative of Academic Commons space.

Space Description Form _OC - 30__