SINGLE TRADE PERMIT APPLICATION PERMIT# ______

COST $ ______

DATE______Rcpt.#______

_____ Electrical _____ HVAC _____ Fire Sprinkler _____ Lawn Sprinkler

_____ Fire Alarm/Installation _____ Plumbing

Residential Job Address ______

Subdivision ______Block ______Lot ______

Owner Name ______

Commercial Job Address ______

Tenant/Business Name ______

Contractor: _____Owner _____Contractor (If owner, a Homeowner’s Homestead Affidavit must be completed)

Company Name ______License # ______

Address ______Phone No. ______

Contractor Registered w/ City? _____ Yes ______No

Check if Applicabable: ______New Construction ______Remodeling ______Isolated Repair

Cost of Work Being Done: $______Square Footage if Applicable ______

Select Work Description:

Electric HVAC Plumbing Lawn Sprinkler

___Add Circuits ___AC/Heat ___Additional Fixtures ___Boring under street

___New Fixtures ___Addition ___Gas Relay ___Commercial

___New Service ___Duct Work ___Grease Interceptor ___Residential

___Outlets ___New ___New ___R.O.W.

___Service Change ___Remodel ___Replacement

___Sub Panel ___Replacement ___Sewer Relay

___Underground ___Water Heater

Fire Sprinkler Fire Alarm

___ 20 Heads or less ___Addition

___21 Heads or more ___Alteration

___Above Ground ___New System

___New System

___Underground

List Other Not Listed Above: Type: ______

Work Descriptions: ______

I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions of laws and ordinances governing this type of work will be complied with whether specified herein or not. The granting of a permit does not presume to give authority to violate or cancel the provisions of any state or local law regulating construction or the performance of construction. The issuance of a building permit neither exempts nor modifies any covenants, deed restrictions, city ordinances and/or state of federal laws, whether herein specified or not.

Applicant Printed Name ______Signature ______

Phone ______Cell Phone ______Fax ______

Email ______

_____Call When Ready ____Email when ready ____ Mail to: ______

**OFFICE USE ONLY: CASH ______CHECK# ______COMMENTS ______

CITY OF SILSBEE

BUILDING PERMIT PROCEDURE

CODE: The International Building Codes, 2015 editions, 2014 NEC have been adopted by the City of Silsbee. This includes the 2015 IECC, which require 3rd party inspections, and sufficiently detailed submittal documents as to assure compliance with the energy code.

BUILDING PERMIT REQUIRED:

Any person, firm, corporation, or agent (contractor) who desires to erect, construct, alter, move, or demolish any building or structure (including signs) SHALL FIRST MAKE APPLICATION to the City of Silsbee, 105 S 3rd St., Silsbee, Tx AND OBTAIN the required permit thereof, BEFORE COMMENCING.

DRAWINGS AND SPECIFICATIONS:

Are required by the Building Official, two copies of the specifications and drawings, drawn to scale with sufficient clarity and detail to indicate the nature and character of the work shall accompany the application. This includes rescheck or comcheck when required by 2015 IECC.

PLOT DIAGRAM:

The Building Official shall require drawings showing the location of the proposed building of structure and of every existing building or structure on the site or lot, and dimensions in relation to property lines. PROPERTY LINES AND BUILDING CORNERS MUST BE CLEARLY IDENTIFIED AND VISIBLE ON SITE BEFORE APPROVAL OF PLOT PLAN REVIEW.

PLANS REVIEW:

Plans will be reviewed to assure that they meet all requirements of The Building Code and all other pertinent laws or ordinances.

PERMIT ISSUANCE:

After plans are properly reviewed, the Building Permit will be issued, ordinarily, within 48 hours unless modifications are required. Commercial structures ordinarily, within one week unless modifications are required. 3rd party inspectors should be named and registered with the city, when required for construction, prior to permit issuance.

PLUMBING, ELECTRICAL AND MECHANICAL PERMITS:

In addition to the Building Permit, if any Plumbing, Electrical and Mechanical work is to be performed, a separate permit per each is required.

INSPECTIONS:

CONTRACTORS OR OWNERS are responsible for CALLING FORINSPECTIONS at (409) 385-2863 for the various stages of construction listed below. Twenty-four (24) hours notice is required on all inspections requested. (Inspection Hours are: 10:00 am to 12:00 pm3:00 pm to 5:00 pm8-5 pm Mon. thru Friday)

INSPECTIONS ARE REQUIRED FOR EACH OF THE FOLLOWING STAGES OF CONSTRUCTION:

(A)Temporary electrical pole hookups.

(B)Site Plan Evaluation.

(C)Foundation and rough-in of plumbing before concrete is poured.

(D)Framing, including the roof, fire blocking, and bracing is in place and completed. Also at this stage, the top-out inspection for plumbing will be made. Also rough-in electrical and rough-in mechanical inspection.

(E)Energy Conservation Inspection. 3rd party inspections should be coordinated with city inspector as to ensure proper retention of documents for code compliance.

(F)Final Inspection on of the building when completed and ready for occupancy including Plumbing, Electrical, Mechanical and Building and Energy compliance report.

FAILURE TO OBTAIN A PERMIT:

Where construction is commenced before a permit is obtained, the permit fees shall be DOUBLED.

If any person commences any work on a building or structure before obtaining the necessary permit from the applicable governing body, he shall be subject to the penalty prescribed herein.

FAILTURE TO OBTAIN FINAL INSPECTIONS OR CERTIFICATE OF OCCUPANCY:

Failure to obtain final inspections, certificate of occupancy, or certificate of compliance with 2015 energy requirements WILL RESULT IN TERMINATION of water service as per international codes adopted by the City of Silsbee. A copy of the certificate of compliance SHALL be posted as required by code in building and one copy kept on file with the city. Compliance certificate SHALL be obtained from 3rd party inspector that is registered with the city.

I, ______, have read and understand the plot plan review and inspection procedures for the City of Silsbee and understand failure to comply will result in termination of water service.

SIGNED ______DATE ______