NOSA INTEGRATED FIVE STAR SYSTEM | VERSION 3
EQUIPMENT PRESSURE
1. INTRODUCTION
All pressure equipment should be suitably identified and recorded in a NOSA or similar Pressure Equipment Register. Inspections and tests should be carried out on a due date in accordance with legal/standard requirements and should include pressure test, safety valve, gauges and cylinders.
NB: Adhere to manufacturer’s specifications/requirements.
2. REQUIREMENTS OF THE NOSA SYSTEM STANDARD
4.4.6.1ELEMENT 4.4.6.17 PRESSURE EQUIPMENT AND COMPRESSED GAS CYLINDERS
INTENT:HSE risks associated with pressurised systems, equipment, vessels and portable gas containers are identified, assessed and managed.
- PRESSURE EQUIPMENT ON REGISTER, TESTS AND INSPECTIONS CARRIED OUT
- All pressure equipment identified by means of manufacturer's plate and/or company identification
- All pressure equipment constructed, maintained and operated within set standards
- All pressure equipment on register with appropriate certificates available
- All inspections and tests to be carried out on due date and in accordance with standards by appropriately qualified and approved person where applicable
- TESTING
- Testing requirements identified and adhered to
- Records of tests maintained
- RELIEF VALVES LOCKED OR SEALED
- Relief valves set to required pressure before installation
- Relief valves on register with serial number and location where required
- All relief (safety) valves physically locked or sealed
- Safety valves vent to safe area
- RED LINE ON PRESSURE GAUGES
- All pressure gauges marked with a red line on the dial of the pressure gauge (to correspond with manufacturer’s plate and certificate) as required
- Maximum work pressure known and alarm system in place to notify/warn as required
- Equipment calibrated and displayed (stickers/tags)
- GAS INSTALLATIONS AND CYLINDERS
- All portable gas cylinders correctly stored
- All pressure equipment (including pipe work) securely installed and protected from damage caused by elements or processes
- All gas installations and equipment in a safe condition and on register (e.g. portable oxy-acetylene welding trolleys, refrigeration units and CO2 installations)
- Operators trained in the correct and safe use of equipment
- Register correctly completed and kept up-to-date
- All flame cutting sets fitted with flashback arrestors
- Drawings for gas plant/installation updated when required
- PNEUMATIC MACHINES: USAGE, STORAGE and REGISTER
- All pneumatic tools on register and checked regularly
- Health risks pertaining to pneumatic tools been identified, assessed and actioned
- HYDRAULIC SYSTEMS
- Risks associated with hydraulic systems identified and assessed
- Monitoring and maintenance requirements identified and complied with
HSE/REG/4.4.6.17/108/REV 032015 © NOSA (PTY) LTD