INTD 504 -Project Management
Lecture: Week 5
Reading for this week: Chapters 6 and 7
Homework: p. 273, question 2, 6, 10; p. 318, questions 4,5,6,7and 17
TOPIC for this week:Cost estimates; Budget Reports
Purpose:Tracking tools to monitor costs at incremental spots in the project schedule
Used in Conjunction with:Project Budgets
Cost Control Reports
Other Budgeting tools
Project Schedules
Concept Development
Schematic Design
Design Development
Working Drawings, (Construction Documents)
Level of Accuracy:
Budget or conceptplus or minus 25%
Schematic Designplus or minus 15% to 20%
Design Developmentplus or Minus 7.5% to 10%
Construction Documentsplus or minus 2.5% to 5%
Elements of estimates:
1Soft Costs and Hard Costs
a)Soft Costs
Design Costs
Development costs
Permit Fees
Remediation
Land Purchase
Furniture
Equipment
Other non-Construction costs
b)Hard Costs
materials
labor
overhead
profit
design contingency
construction contingency
2Types of Estimates
a)Budget Estimates
Abatement Cost Allocation, (Remediation)
Percentage for "soft Cost"
Area costs for type of building and use
Design Contingency
Assumptions
b)Schematic Design
Abatement Cost
Soft Costs
A/E fees
CM and other fees
Percentage for remaining unknown soft costs
Building systems costs
Walls, Roofs, etc.
Contractor Profit & Overhead
Design Contingency – 15% - 20%
Construction Contingency 5% for new, higher for remodel
Assumptions & qualifications
c)Design Development
Abatement
Soft Costs
A/E Fees
CM and other Consultant Fees
Permits
Testing
Furniture
Equipment
Hard Costs
Detailed building Systems and components
Site Work
Landscape
Excavation
Foundations
Design Contingency 7.5%
Contractor Overhead and profit 12.5% varies with locale and job
Construction Contingency 5% varies with locale and job
d)Construction Documents Estimate
1)Soft Costs
A/E Fees
CM and other Consultant Fees
Permits
Testing
Furniture
Equipment
2)Hard Costs*
Detailed building Systems and components
– by division with labor & material breakdown
Site Work
Landscape
Excavation
Foundations...... thru Electrical
Design Contingency – 2.5%
Contractor Overhead and profit – 12.5% varies with locale and job
Construction Contingency - 5% varies with locale and job
*this is what shows up incontractor’s bid
3) Other potential costs – property purchase, development costs, rezoning, public relations
e)Contractor's bid Estimate
Permits
Testing that is done by Contractor
Detailed building Systems and components – by division with labor & material breakdown
Site Work
Landscape
Excavation
Foundations thru Electrical as defined in bidding documents
Design Contingency – 0%
Contractor Overhead and profit – 12.5% (varies by location and job)
Construction Contingency - 0% in Public Bid, can be negotiated in private work
Other Budgeting Tools
Work Breakdown Structure
Other reporting tools – Cost Control Reports
Company NameProgram Name
Projection of Costs
Monthly Costs
Hours / Dollars
EST'D / ACTUAL / DIFF / EST'D / ACTUAL / DIFF
Month
Jul-06 / 2020 / 1717 / (303) / $ 209,059.63 / $ 195,562.74 / (13,496.89)
Aug-06 / 2426 / 1497 / (929) / $ 221,495.79 / $ 171,361.78 / (50,134.01)
Sep-06 / 1649 / 1767 / 118 / $ 177,119.12 / $ 183,052.41 / 5,933.29
Oct-06 / 2020 / 1452 / (568) / $ 197,408.38 / $ 161,352.92 / (36,055.46)
Nov-06 / 2426 / 1402 / (1024) / $ 219,743.79 / $ 151,026.60 / (68,717.19)
Dec-06 / 1649 / 2068 / 419 / $ 167,367.11 / $ 202,959.48 / 35,592.37
2007
Jan-07 / 1649 / 1302 / (347) / $ 187,161.33 / $ 145,602.72 / (41,558.61)
Feb-07 / 2020 / 1574 / (446) / $ 198,174.46 / $ 161,605.79 / (36,568.67)
Mar-07 / 2426 / 1310 / (1117) / $ 226,693.74 / $ 159,102.53 / (67,591.21)
Apr-07 / 1649 / 1277 / (372) / $ 186,391.90 / $ 161,541.49 / (24,850.41)
May-07 / 2303 / 1298 / (1005) / $ 233,160.26 / $ 163,210.81 / (69,949.45)
Jun-07 / 1649 / 1146 / (504) / $ 242,625.04 / $ 165,494.88 / (77,130.16)
Jul-07 / 1737 / 1435 / (303) / $ 203,800.22 / $ 178,001.52 / (25,798.70)
Aug-07 / 1855 / 1214 / (641) / $ 196,576.31 / $ 173,074.62 / (23,501.69)
Sep-07 / 1737 / 1061 / (677) / $ 194,203.10 / $ 154,846.26 / (39,356.84)
Oct-07 / 1489 / 1092 / (397) / $ 179,690.73 / $ 154,517.05 / (25,173.68)
Nov-07 / 2103 / 1143 / (960) / $ 218,629.75 / $ 154,920.82 / (63,708.93)
Dec-07 / 1489 / 1394 / (96) / $ 171,737.57 / $ 178,867.14 / 7,129.57
2008
Jan-08 / 1489 / 1125 / (365) / $ 191,443.55 / $ 149,316.46 / (42,127.09)
Feb-08 / 1737 / 1161 / (576) / $ 194,432.55 / $ 154,934.09 / (39,498.46)
Mar-08 / 1855 / 1095 / (760) / $ 202,285.79 / $ 156,242.87 / (46,042.92)
Apr-08 / 1678 / 1678 / 0 / $ 199,723.97 / $ 199,723.97 / 0.00
May-08 / 1855 / 1855 / 0 / $ 209,056.19 / $ 209,056.19 / 0.00
Jun-08 / 1860 / 1860 / 0 / $ 266,354.97 / $ 266,354.97 / 0.00
Jul-08 / 1489 / 1489 / 0 / $ 187,027.47 / $ 187,027.47 / 0.00
Aug-08 / 2226 / 2226 / 0 / $ 224,789.20 / $ 224,789.20 / 0.00
Sep-08 / 1489 / 1489 / 0 / $ 174,008.67 / $ 174,008.67 / 0.00
Oct-08 / 1489 / 1489 / 0 / $ 167,676.83 / $ 167,676.83 / 0.00
Nov-08 / 1855 / 1855 / 0 / $ 195,120.19 / $ 195,120.19 / 0.00
Dec-08 / 1489 / 1489 / 0 / $ 163,387.87 / $ 163,387.87 / 0.00
2009
Jan-09 / 999 / 999 / 0 / $ 156,357.30 / $ 156,357.30 / 0.00
Feb-09 / 999 / 999 / 0 / $ 143,744.04 / $ 143,744.04 / 0.00
Mar-09 / 1205 / 1205 / 0 / $ 160,895.82 / $ 160,895.82 / 0.00
Apr-09 / 839 / 839 / 0 / $ 135,830.77 / $ 135,830.77 / 0.00
May-09 / 1045 / 1045 / 0 / $ 159,637.89 / $ 159,637.89 / 0.00
Jun-09 / 839 / 839 / 0 / $ 197,986.10 / $ 197,986.10 / 0.00
Jul-09 / 839 / 839 / 0 / $ 146,236.10 / $ 146,236.10 / 0.00
Aug-09 / 1045 / 1045 / 0 / $ 150,723.02 / $ 150,723.02 / 0.00
Sep-09 / 839 / 839 / 0 / $ 136,723.20 / $ 136,723.20 / 0.00
Oct-09 / 839 / 839 / 0 / $ 129,888.24 / $ 129,888.24 / 0.00
Nov-09 / 1045 / 1045 / 0 / $ 141,280.97 / $ 141,280.97 / 0.00
Dec-09 / 839 / 839 / 0 / $ 125,041.82 / $ 125,041.82 / 0.00
2010
Jan-10 / 519 / 519 / 0 / $ 113,944.60 / $ 113,944.60 / 0.00
Feb-10 / 519 / 519 / 0 / $ 100,131.32 / $ 100,131.32 / 0.00
Mar-10 / 645 / 645 / 0 / $ 114,486.15 / $ 114,486.15 / 0.00
Apr-10 / 519 / 519 / 0 / $ 104,071.38 / $ 104,071.38 / 0.00
May-10 / 645 / 645 / 0 / $ 170,150.41 / $ 170,150.41 / 0.00
Jun-10 / 519 / 519 / 0 / $ 112,406.25 / $ 112,406.25 / 0.00
Jul-10 / 519 / 519 / 0 / $ 110,656.25 / $ 110,656.25 / 0.00
Aug-10 / 645 / 645 / 0 / $ 112,146.15 / $ 112,146.15 / 0.00
Sep-10 / 519 / 519 / 0 / $ 103,428.38 / $ 103,428.38 / 0.00
Oct-10 / 519 / 519 / 0 / $ 93,027.80 / $ 93,027.80 / 0.00
Nov-10 / 645 / 645 / 0 / $ 104,731.43 / $ 104,731.43 / 0.00
Dec-10 / 519 / 519 / 0 / $ 92,135.66 / $ 92,135.66 / 0.00
2011
Jan-11 / 514 / 514 / 0 / $ 83,710.89 / $ 83,710.89 / 0.00
Feb-11 / 514 / 514 / 0 / $ 67,292.49 / $ 67,292.49 / 0.00
Mar-11 / 640 / 640 / 0 / $ 79,897.38 / $ 79,897.38 / 0.00
Apr-11 / 514 / 514 / 0 / $ 67,292.49 / $ 67,292.49 / 0.00
May-11 / 640 / 640 / 0 / $ 78,473.77 / $ 78,473.77 / 0.00
Jun-11 / 514 / 514 / 0 / $ 88,368.88 / $ 88,368.88 / 0.00
TOTALS / 76247 / 65396 / (10851) / $ 9,587,042.44 / $ 8,844,437.29 / (742,605.15)
(xxx.xx) is UNDER estimated hours or costs
125.74 / $ 135.24 / (9.51)
103166
(1467528)