FY2018 Redeploy Illinois NOFO Application – Appendix B
Redeploy Current/Former Provider Information
Service Area: Lee County
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 11
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 8.
Service Area: Macon County
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 51
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 38.
Service Area: Madison County
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 33
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 24.
Service Area: McLean County
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 23
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 17.
Service Area: LaSalle, Bureau and Grundy Counties (13th Judicial Circuit)
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 27
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 21.
Service Area: Winnebago County
Approved 3 Year Baseline: 78
Approved Project Period: Calendar Year
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 58.
Service Area: Kankakee and Iroquois Counties (21st Judicial Circuit)
Approved 3 Year Baseline: 16
Approved Project Period: Calendar Year
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 12.
Service Area: Sangamon County
Approved 3 Year Baseline: 20
Approved Project Period: Fiscal Year
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 15.
Service Area: Peoria County, Tazewell County
Approved Project Period: Fiscal Year
Approved 3 Year Baseline: 85
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 63.
Service Area: Union County, Jackson County, Johnson County, Massac County, Pope County, and Saline Counties
Approved 3 Year Baseline: 11
Approved Project Period: Calendar Year
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 8.
Service Area: Jefferson, Crawford, Lawrence, Richmond, Wayne, Edwards, Wabash, Franklin, Hamilton, White, Gallatin and Hardin Counties (Second Judicial Circuit).
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 40
Required Minimum Reduction: 25% - Penalties will be imposed on all commitments over 30.
Service Area: Montgomery, Christian, Shelby, Fayette, Effingham, Jasper, Clinton, Marion and Clay Counties (Fourth Judicial Circuit).
Approved Project Period: Calendar Year
Approved 3 Year Baseline: 47
Required minimum Reduction: 25% - Penalties will be imposed on all commitments over 35.
Service Area: St. Clair County, Washington, Monroe, Randolph and Perry Counties (20th Judicial Circuit)
Approved Project Period: Fiscal Year
Approved 3 Year Baseline: 83