STATUS REPORT (AMRUT) AS ON 29.05.2017

SAAP 2015-16 Projects (Summary)
S.No. / Sector / Project Cost
(In Cr.) / Total Projects / Tenders Floated / Tenders Received / Tenders Evaluated / COT Approved / COM II Approved / GO Issued / Awarded / Awarded Cost
(In Cr.) / Awarded %
(Cost) / Awarded %
(Numbers)
1 / Water Supply / 797.43 / 26 / 24 / 23 / 22 / 7 / 14 / 14 / 19 / 412.65 / 51.75 / 73.08
Status / Remarks / Comments
DPR Design Stage(1): Nellore
Evaluation Stage(1): GVMC
Tender/Re-Tender Stage(2):Vijayawada,Chittoor
2 / Parks & Green Spaces / 16.07 / 34 / 34 / 34 / 31 / 30 / 0 / 0 / 29 / 10.19 / 63.41 / 85.29
Status / Remarks / Comments
Evaluation Stage(3):GVMC,Kakinada,Tirupathi
Total / 813.50 / 60 / 58 / 57 / 53 / 37 / 14 / 14 / 48 / 422.84 / 51.98 / 80
1. Status of Water Supply Projects (2015-16)
S.No. / ULB Name / Project Cost
(In Cr.) / Tenders Floated / Tenders Received / Tenders Evaluated / COT Approved / COM II Approved / GO Issued / Awarded / Remarks
1 / Srikakulam / 10.73 / 20.08.2016
Yes / Yes / Yes / Yes / 30.12.2016
Yes / 1. Pipe procurement for 38.00Km completed
2. Laying completed upto 9.00KM
3. 80 nos of HSC completed.
2 / Vizianagaram / 5.85 / 26.09.2016
Yes / Yes / Yes / Yes / 24.04.2017
Yes / LOA ISSUED DATE ON 24/04/2017, AND CR NUMBER- 8 DATE ON 18/04/2017.
3 / GVMC / 153.18 / 13.03.2017
Yes / Yes / No / No / Date: 26-05-17
Procurement tender notice No.- 15/2016-17/CE/SE/(P-II)/EE II(WSP)
Number of works : 1 No. (2 nd call)
Technical bid opening date(online) : 18-04-2017
Bid was opened. 3 member of Bidders participated.
1. N.C.C. Limited
2. AYYAPPA Constructions
3. VELCO Company Ltd.
Note:
Technical bid Evaluation was completed. Now, awaiting for Price bid opening
4 / Rajahmundry / 2.83 / 07.10.2016
Yes / Yes / Yes / Yes / 09.02.2017
Yes / HH Survey & field studies are in progress. Material received for HSC's and laying of HSCs are in progress. (50 No given out of 24,419)
5 / Kakinada / 41.44 / 29.09.2016
Yes / Yes / Yes / Yes / Yes / 28.04.2017
Yes / LoA issued on 28.04.2017
6 / Tadepalligudem / 15.40 / 27.09.2016
Yes / Yes / Yes / Yes / 02.03.2017
Yes / HH Survey, field studies & Network designs are in progress. Soil testing completed.
7 / Bhimavaram / 47.29 / 28.09.2016
Yes / Yes / Yes / Yes / Yes / 01.05.2017
Yes / Council approval completed and waiting for work order.
8 / ELURU / 2.96 / 07.11.2016
Yes / Yes / Yes / Yes / 14.02.2017
Yes / HH Survey & field studies are in progress. Material received for HSC's and laying of HSCs are in progress. (50 No given out of 6482)
9 / Vijayawada / 87.43 / No / No / No / No / APUIAML is preparing the DPR, feasibility on PPP and Finance mode.
10 / Machilipatnam / 36.75 / 30.09.2016
Yes / Yes / Yes / Yes / Yes / 09.01.2017
Yes / ELSRs Designs submitted for approval.
Household survey for tap connections is in progress.
HH Survey & field studies are in progress.
11 / Gudivada / 32.47 / 26.09.2016
Yes / Yes / Yes / Yes / Yes / 01.02.2017
Yes / Survey work is in progress. All bench marks covered. Now Zone wise started for Distribution lines.
Soil testing conducted in proposed Reservoir site at Vasavi nagar and Soil testing conducted in proposed Reservoir site at Bantumilli Road.
Distribution lines survey is completed in Zone 10, 1,2 &3. (Dt: 18-3-2017).
Distribution lines survey is completed in Zone 4, 5, 6 &7. (Dt: 31-3-2017).
Distribution lines survey is completed in Zone 8 & 9. (Dt: 8-4-2017).
Agreement documents given by the Contractor, to verify the Municipal Officials on 19.04.2017
Submitted Population projection on 19-04-2017.
Commissioner gave the letter to the SE(PH) 20-04-2017,
Submit the Population projection to SE(PH) office.(21-04-2017)
1. Physical progress is Survey is completed, soil samples sent to lab for testing .(22-04-2017)
2. Financial progress is 1st installment 3.72 Cr., 2nd installment 3.08 Cr.
Contract Agreement has completed, copy had given to contractor (27-04-2017)
Population projections approved from SE. (2-05-2017)
12 / Tenali / 8.59 / 27.12.2016
Yes / Yes / Yes / Yes / 08.05.2017
Yes / LoA issued.
13 / Guntur / 22.02 / 26.09.2016
Yes / Yes / Yes / Yes / Yes / 01.02.2017
Yes / HH Survey & field studies are in progress. QAP approved, Material Inspection for procurement completed.
14 / Narasaraopeta / 13.03 / 22.09.2016
Yes / Yes / Yes / Yes / Yes / 06.05.2017
Yes / GO NO: 133 is Approved in the council and work order was issued on 06-05-2017 waiting for agreement.
Identification of house service connection work is in progress out of 34 wards 19 wards are completed.
15 / Chilakaluripeta / 8.82 / 17.08.2016
Yes / Yes / Yes / Yes / Yes / 02.12.2016
Yes / 1) 15.0KM HDPE Pipes procured. Soil Investigation completed.
2) Earth work excavation for pipe line laying work is in progress. As on 5/5/2017 pipe laying work of 200mm dia, 940mts completed which is of distribution network.
3) Inspection of HSC saddles and fittings with Department officials in Ahmadabad completed.
4) M/s Velko Infrastructure also taken a part Bill of Amount Rs.10500000/- with Bill number (BILL01/0281), MB Number: 307/2016-17.
5) As on 16/5/17, cc-road cutting work in progress for laying of 110mm dia HDPE Pipes in Zone-2 Area.
6) Council approval was given for 5 MLD capacity STP.
7) As on 28/5/17, laying of 110mm dia HDPE pipe line for distribution network 157mts completed in Zone-2 Area.
16 / Ongole / 2.88 / 18.08.2016
Yes / Yes / Yes / Yes / 10.04.2017
Yes / 1) LOA issued on 10.04.2017
2) Contractor yet to accept LOA
17 / Nellore / 10.00 / No / No / No / No / 1) DPR preparation yet to start
2) DPR Components to be finalised by ULB
18 / Tirupathi / 93.71 / 23.08.2016
Yes / Yes / Yes / Yes / Yes / 16.01.2017
Yes / 1. Designs submitted to Municipal Corporation Tirupati
2. Procurement of pipes in progress
1. PCC work for outer raft completed at Bhupal Housing colony ELSR (1000 KL) on Dt:: 21.05.2017
2. PCC work for outer raft completed at Padmavathi park ELSR (1500 KL) on Dt: 25.05.2017
3.PCC work for outer raft completed at Mahila University ELSR (1500 KL) on Dt: 28.05.2017
4. PCC work for outer raft started Auto Nagar-2 UDS office ELSR (600 KL) on Dt:29.05.2017
5.Earth work excavation started at Auto Nagar-1 for ELSR(1000 KL) on Dt:29.05.2017
6..Earth work excavation started at Rajeev Nagar for ELSR(1350 KL) on Dt:29.05.2017
19 / Chittoor / 2.38 / 27.03.2017
Yes / No / No / No / 4th time NIT to be initiated
20 / Madanapalli / 19.00 / 04.08.2016
Yes / Yes / Yes / Yes / Yes / 14.11.2016
Yes / 1) Earth work Excavation of 1000KL ELSR was Completed at A.V.Naidu Colony (SAAP 2015-16 Under AMRUT Scheme).
2) NVR layout association team opposed to construction of ELSR in the NVR park. For new location of ELSR, discussions are going on with PH team & ULB from 16.05.2017.
3) Local people opposed for construction of ELSR at Dhobi ghat. For new location of ELSR, discussions are going on with PH team & ULB from 16.05.2017.
21 / Dharamavaram / 17.57 / 22.09.2016
Yes / Yes / Yes / Yes / Yes / 01.05.2017
Yes / 1) G.O Issued to M/s. GPR Infra. G.O MS.No.140, Dated:03-04-2017
2) LOA dated on 24-04-2017, but issued by Commissioner on 01-05-2017 to GPR infra
22 / Guntakul / 16.45 / 04.10.2016
Yes / Yes / Yes / Yes / Yes / 09.05.2017
Yes / 1) GO issued (M/s. GPR Infra). G.O.MS. NO:139, Date:03-04-2017.
2) LOA issued by ULB, Date:09-05-2017.
23 / Kadapa / 43.32 / 10.09.2016
Yes / Yes / Yes / Yes / No / 1) Last date of bid submission was on 14.12.2016.
2) 3 bidders was participated.
3) Committee 2 approved.
24 / Kurnool / 68.25 / 30.07.2016
Yes / Yes / Yes / Yes / Yes / 07.12.2016
Yes / 1) Designs submitted for approval.
2) 100 HSC completed.
3) 2 KM pipes received.
4) Pipe laying started on 11.04.2017.
5) 110mmdia HDPE PN-6 laid - 8200rmts
6) 160mmdia HDPE PN-6 laid - 1527rmts
25 / Adoni / 12.54 / 01.10.2016
Yes / Yes / Yes / Yes / No / 1. Waiting for GO
26 / Nandyala / 22.54 / 27.08.2016
Yes / Yes / Yes / Yes / Yes / No / 1) GO Issued. GO no. dated - 03/04/2017.
2) LOA to be issued by ULB.
2. Status of Park Projects (2015-16)
S.No. / ULB Name / Project Cost
(In Cr.) / Tenders Floated / Tenders Received / Tenders Evaluated / COT Approved / COM II Approved / GO Issued / Awarded / Remarks
1 / Vizianagaram / 0.50 / 03.11.2016
Yes / Yes / Yes / Yes / 21.01.2017
Yes / Work under progress.
2 / GVMC / 1.07 / 05.07.2016
Yes / Yes / No / No / Two times tenders called for but no participation from bidders.
3 / Rajahmundry / 0.50 / 07.10.2016
Yes / Yes / Yes / Yes / 11.11.2016
Yes / Work under progress.
4 / Kakinada / 0.75 / 24.11.2016
Yes / Yes / No / No / Recalled tenders. Tenders disqualified.
5 / Tadepalligudem / 0.36 / 05.12.2016
Yes / Yes / Yes / Yes / 11.01.2017
Yes / Work order issued and yet to be started.
6 / Tadepalligudem / 0.14 / 05.12.2016
Yes / Yes / Yes / Yes / 11.01.2017
Yes / Work order issued and yet to be started.
7 / Bhimavaram / 0.50 / 19.11.2016
Yes / Yes / Yes / Yes / 08.02.2017
Yes / Civil work is under progress.
8 / ELURU / 0.50 / 20.04.2016
Yes / Yes / Yes / Yes / 06.05.2016
Yes / Pathway works is under progress and 80% of civil works completed.
9 / Vijayawada / 0.25 / 27.06.2016
Yes / Yes / Yes / Yes / 23.09.2016
Yes / Work is yet to be started.
10 / Vijayawada / 0.25 / 27.06.2016
Yes / Yes / Yes / Yes / 18.07.2016
Yes / Work is yet to be started.
11 / Vijayawada / 0.25 / 27.06.2016
Yes / Yes / Yes / Yes / 18.07.2016
Yes / Work is yet to be started.
12 / Vijayawada / 0.25 / 27.06.2016
Yes / Yes / Yes / Yes / 18.07.2016
Yes / Work is yet to be started.
13 / Machilipatnam / 0.50 / 19.10.2016
Yes / Yes / Yes / Yes / 15.02.2017
Yes / Work order issued and work is yet to be started.
14 / Gudivada / 0.50 / 25.10.2016
Yes / Yes / Yes / Yes / 18.01.2017
Yes / Work order issued and work is yet to be started.
15 / Tenali / 0.50 / 07.10.2016
Yes / Yes / Yes / Yes / 17.11.2016
Yes / Earth work and compound wall work is under progress.
16 / Guntur / 0.50 / 10.06.2016
Yes / Yes / Yes / Yes / 18.07.2016
Yes / Gazebo work is in progress (40%)
17 / Narasaraopeta / 0.50 / 03.10.2016
Yes / Yes / Yes / Yes / 02.12.2016
Yes / Jungle clearance work is under progress (5%)
18 / Chilakaluripeta / 0.50 / 23.09.2016
Yes / Yes / Yes / Yes / 01.12.2016
Yes / Jungle clearance work is under progress.
19 / Ongole / 0.50 / 11.08.2016
Yes / Yes / Yes / Yes / 17.10.2016
Yes / Walking track work is started .
20 / Nellore / 0.50 / 26.05.2016
Yes / Yes / Yes / Yes / 17.06.2016
Yes / Filling work is in progress
21 / Tirupathi / 0.75 / 17.08.2016
Yes / Yes / No / No
22 / Chittoor / 0.50 / 29.07.2016
Yes / Yes / Yes / Yes / 23.09.2016
Yes / 80% of kerbing work is completed, skating rink, Gazebo civil work under progress.
23 / Madanapalli / 0.50 / 17.08.2016
Yes / Yes / Yes / Yes / 31.08.2016
Yes / Civil work is under progress.
24 / Dharamavaram / 0.50 / 02.10.2016
Yes / Yes / Yes / Yes / 01.01.2017
Yes / Work is under progress, 25% completed.
25 / Guntakul / 0.50 / 03.10.2016
Yes / Yes / Yes / Yes / No / Proposed cancellation of the tender since market yard chairman has qualified in the bid. The commissioner placed cancellation order before the council and going for re-tender process.
26 / Kadapa / 0.25 / 12.08.2016
Yes / Yes / Yes / Yes / 24.09.2016
Yes / Marking completed, the Contractor was not responding and the Commissioner has issued notice to the contractor.
27 / Kadapa / 0.25 / 12.08.2016
Yes / Yes / Yes / Yes / 24.09.2016
Yes / Marking completed, the Contractor was not responding and the Commissioner has issued notice to the contractor.
28 / Kurnool / 0.50 / 16.07.2016
Yes / Yes / Yes / Yes / 03.08.2016
Yes / 80% civil work completed.
29 / Adoni / 0.50 / 29.10.2016
Yes / Yes / Yes / Yes / 26.12.2016
Yes / Construction of compound wall is completed and filling works are under progress.
30 / Nandyala / 0.50 / 28.07.2016
Yes / Yes / Yes / Yes / 24.09.2016
Yes / Filling works is under progress.
31 / Ananthapuramu / 0.50 / 02.06.2016
Yes / Yes / Yes / Yes / 25.06.2016
Yes / Civil work is under progress (30% completed).
32 / Hindupur / 0.50 / 06.10.2016
Yes / Yes / Yes / Yes / 03.12.2016
Yes / Civil work is under progress (30% completed).
33 / Tadipatri / 0.50 / 17.10.2016
Yes / Yes / Yes / Yes / 06.12.2016
Yes / Works started 20% work completed.
34 / Proddutur / 0.50 / 28.10.2016
Yes / Yes / Yes / No / No / Tender opened and sent to C.E. office for opinion.
SAAP 2016-20 Projects (Summary)
S.No. / Sector / SAAP Approved Cost (Cr.) / No. of DPRs / DPRs Submitted / DPRs to be submitted / SLTC Approved / SHPSC Approved / TS Accorded
1 / Water Supply / 1374.74 / 29 / 19 / 13 / 25 / 25 / 0
Status / Remarks / Comments
DPR Design Stage(4):Nellore, Nellore, Kurnool, Kavali
Approved by SHPSC(25): Srikakulam,Vizianagaram,GVMC,Tadepalligudem,Bhimavaram,ELURU,Machilipatnam,Gudivada,Guntur,Narasaraopeta,
Chilakaluripeta,Ongole,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,Adoni,Nandyala,
Ananthapuramu, Hindupur, Tadipatri, Proddutur, Srikalhasthi
2 / Parks & Green Spaces / 18.29 / 32 / 32 / 32 / 32 / 32 / 0
Status / Remarks / Comments
Approved by SHPSC(32):Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Guntur,Narasaraopeta,Chilakaluripeta,Ongole,Nellore,Tirupathi,Chittoor,Madanapalli,
Dharamavaram,Guntakul,Kadapa,Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,
Kavali,Srikalhasthi
3 / Sewerage & Septage Management / 517.94 / 27 / 18 / 24 / 27 / 27 / 0
Status / Remarks / Comments
Approved by SHPSC(27):Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Chilakaluripeta,Ongole,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,
Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Kavali,Srikalhasthi
4 / Storm Water Drainage / 296.64 / 8 / 3 / 5 / 5 / 5 / 0
Status / Remarks / Comments
DPR Design Stage(3):Tadepalligudem,Nellore,Ananthapuramu
Approved by SHPSC(5):Srikakulam,Rajahmundry,Kakinada,Machilipatnam,Tirupathi
1. Water Supply DPRs (2016-20)
S.No. / Name of ULB / SAAP Project Cost (Cr.) / SLTC Approval / Administrative Sanction
(GO) / DPR Submitted for TS / TS Accorded / Remarks
No / Date / Approved Cost (Cr.) / No / Date
1 / Srikakulam / 5.00 / 3 / 06.01.2017 / 5.57 / 82 / 03.03.2017 / 20.03.2017 / Appraisal note submitted for TS
2 / Vizianagaram / 77.41 / 5 / 23.03.2017 / 22.40 / 168 / 01.05.2017 / DPR submitted for TS and estimates being updated for finalization at O/o EnC
3 / GVMC / 67.41 / 6 / 08.05.2017 / 75.16 / 211 / 24.05.2017 / DPR reviewed by SE (GVMC). Suggested additional pipeline to be included. Comments being incorporated
4 / Tadepalligudem / 17.12 / 6 / 08.05.2017 / 31.64 / 211 / 24.05.2017 / DPR under review for Technical Sanction
5 / Bhimavaram / 22.75 / 6 / 08.05.2017 / 36.54 / 211 / 24.05.2017 / DPR being reviewed by O/o EnC for TS
6 / ELURU / 4.20 / 5 / 23.03.2017 / 5.23 / 168 / 01.05.2017 / 01.05.2017 / DPR and estimates finalised and forwarded for TS from EnC
7 / Machilipatnam / 11.00 / 5 / 23.03.2017 / 22.70 / 168 / 01.05.2017 / DPR being reviewed by O/o SE (PH) Guntur for TS
8 / Gudivada / 14.60 / 5 / 23.03.2017 / 20.35 / 168 / 01.05.2017 / DPR being reviewed by O/o SE (PH) Guntur for TS
9 / Guntur / 25.00 / 5 / 23.03.2017 / 33.53 / 168 / 01.05.2017 / 05.05.2017 / DPR being reviewed by O/o EnC for TS
10 / Narasaraopeta / 4.50 / 3 / 06.01.2017 / 5.08 / 82 / 03.03.2017 / 11.04.2017 / DPR and estimates finalised and forwarded for TS from EnC
11 / Chilakaluripeta / 117.41 / 3 / 06.01.2017 / 139.80 / 82 / 03.03.2017 / Yes / Tender Floated (for an amount of Rs. 129.95 Cr.) on 25.05.2017, Last date for bid submission 08.06.2017.
12 / Ongole / 105.43 / 6 / 08.05.2017 / 123.00 / 211 / 24.05.2017 / 08.05.2017 / DPR Submitted to SE-PH office for TS.
13 / Nellore / 30.00 / 4 / 08.03.2017 / 34.20 / 116 / 28.03.2017 / AS accorded. TS to be Accorded
14 / Nellore / 36.00 / 4 / 08.03.2017 / 41.04 / 116 / 28.03.2017 / AS accorded. TS to be Accorded
15 / Tirupathi / 43.98 / 6 / 08.05.2017 / 55.17 / 211 / 24.05.2017 / 03.05.2017 / DPR to be submitted to O/o EnC
16 / Chittoor / 152.25 / 6 / 08.05.2017 / 192.16 / 211 / 24.05.2017 / 03.05.2017 / DPR submitted by SE PH to EnC office on 03.05.2017.
17 / Madanapalli / 8.00 / 6 / 08.05.2017 / 10.24 / 211 / 24.05.2017 / 03.05.2017 / DPR submitted by SE PH to EnC office on 03.05.2017.
18 / Dharamavaram / 8.00 / 5 / 23.03.2017 / 11.18 / 168 / 01.05.2017 / 18.05.2017 / DPR submitted by SE-PH to EnC-PH office on 18.05.2017.
19 / Guntakul / 8.38 / 5 / 23.03.2017 / 10.98 / 168 / 01.05.2017 / 18.05.2017 / DPR submitted by SE-PH to EnC-PH office on 18.05.2017.
20 / Kadapa / 55.00 / 6 / 08.05.2017 / 67.73 / 211 / 24.05.2017 / 03.05.2017 / ULB submitted DPR to SE-PH on 03.05.2017.
21 / Kurnool / 42.00 / During EnC visit on 22.04.2017, Tadakanapalli MI tank conversion in to SS tank is dropped. During SE-PH visit, source locations and WTP location discussed with Commissioner, KMC. On 17.05.2017, discussions of EnC, MLA regarding GDP source. Final components yet to be decided.
22 / Adoni / 16.00 / 5 / 23.03.2017 / 23.58 / 168 / 01.05.2017 / 18.05.2017 / DPR submitted by SE-PH to EnC-PH office on 18.05.2017.
23 / Nandyala / 117.50 / 5 / 23.03.2017 / 137.34 / 168 / 01.05.2017 / 03.04.2017 / Discussions are in progress regarding component finalisation.
24 / Ananthapuramu / 10.00 / 5 / 23.03.2017 / 15.35 / 168 / 01.05.2017 / SS tank Geo-technical investigation completed. Estimate preparation in progress. DPR to be submitted for Technical Sanction.
25 / Hindupur / 106.00 / 6 / 08.05.2017 / 194.00 / 211 / 24.05.2017 / 03.05.2017 / DPR submitted by SE-PH to EnC office for Technical Sanction.
26 / Tadipatri / 115.50 / 5 / 23.03.2017 / 145.14 / 168 / 01.05.2017 / 03.05.2017 / DPR submitted by SE-PH to EnC office for Technical Sanction.
27 / Proddutur / 115.46 / 6 / 08.05.2017 / 151.38 / 211 / 24.05.2017 / 03.05.2017 / DPR submitted to SE-PH office on 03.05.2017.
28 / Kavali / 34.84 / 211 / 24.05.2017 / DPR submitted to ULB for TS.
29 / Srikalhasthi / 4.00 / 6 / 08.05.2017 / 5.24 / 211 / 24.05.2017 / 19.05.2017 / DPR Submitted to SE-PH office on 19.05.2017.
2. Sewage & Septage Management DPRs (2016-20)
S.No. / Name of ULB / SAAP Project Cost (Cr.) / SLTC Approval / Administrative Sanction
(GO) / DPR Submitted for TS / TS Accorded / Remarks
No / Date / Approved Cost (Cr.) / No / Date
1 / Srikakulam / 6.25 / 2 / 22.11.2016 / 28.44 / 82 / 03.03.2017 / 13.04.2017 / DPR under review for TS
2 / Vizianagaram / 9.75 / 3 / 06.01.2017 / 16.76 / 82 / 03.03.2017 / 11.04.2017 / Appraisal note submitted for TS
3 / GVMC / 30.00 / 5 / 23.03.2017 / 33.31 / 168 / 01.05.2017 / 11.05.2017 / DPR under review for TS
4 / Rajahmundry / 9.75 / 2 / 22.11.2016 / 17.98 / 82 / 03.03.2017 / 10.04.2017 / Appraisal note submitted for TS
5 / Kakinada / 9.75 / 2 / 22.11.2016 / 29.17 / 82 / 03.03.2017 / 11.04.2017 / DPR under review for TS
6 / Tadepalligudem / 23.94 / 3 / 06.01.2017 / 58.32 / 82 / 03.03.2017 / Appraisal note submitted for TS
7 / Bhimavaram / 15.00 / 3 / 06.01.2017 / 31.81 / 82 / 03.03.2017 / 10.04.2017 / DPR under review for TS
8 / Eluru / 27.55 / 6 / 08.05.2017 / 37.48 / 211 / 24.05.2017
9 / Vijayawada / 36.20 / 6 / 08.05.2017 / 39.88 / 211 / 24.05.2017 / DPR under review for TS
10 / Machilipatnam / 9.75 / 2 / 22.11.2016 / 16.76 / 82 / 03.03.2017 / 07.04.2017 / Appraisal note submitted for TS
11 / Gudivada / 9.75 / 3 / 06.01.2017 / 16.76 / 82 / 03.03.2017 / 06.04.2017 / Appraisal note submitted TS
12 / Tenali / 18.50 / 2 / 22.11.2016 / 30.06 / 82 / 03.03.2017 / 30.03.2017 / Appraisal note submitted for TS
13 / Chilakaluripeta / 9.75 / 2 / 22.11.2016 / 16.76 / 82 / 03.03.2017 / 03.04.2017 / Appraisal note submitted for TS
14 / Ongole / 17.50 / 2 / 22.11.2016 / 30.79 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017.
15 / Tirupathi / 50.00 / 6 / 08.05.2017 / 59.05 / 211 / 24.05.2017 / 03.05.2017 / DPR to be submitted to O/o EnC
16 / Chittoor / 17.50 / 3 / 06.01.2017 / 33.39 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017.
17 / Madanapalli / 9.00 / 3 / 06.01.2017 / 15.95 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017.
18 / Dharamavaram / 16.00 / 2 / 22.11.2016 / 48.17 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to for TS on 04.04.2017. After EnC PH visit on 21.04.2017, Commissioner conveyed that earlier locations considered while preparation of DPR are changed. Accordingly DPR revision in progress and revised DPR to be submitted for TS.
19 / Guntakul / 16.00 / 3 / 06.01.2017 / 26.71 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to for TS on 04.04.2017. After EnC PH visit on 21.04.2017, ULB conveyed that earlier locations considered while preparation of DPR is changed. Accordingly DPR revision in progress and revised DPR to be submitted for TS.
20 / Kadapa / 52.00 / 2 / 22.11.2016 / 94.35 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017.
21 / Kurnool / 28.00 / 3 / 06.01.2017 / 47.93 / 82 / 03.03.2017 / 04.04.2017 / During joint discussions with Commissioner, SE-PH on 06.05.2017, Commissioner conveyed to reduce 2 nos 2.5 MLD STPs (Kota Anjaneya Temple & Mangalagiri Toilet block) and suggested to add 1 no STP, opposite to KMC swimming pool. Revision under progress and revised DPR to be submitted for TS.
22 / Adoni / 8.75 / 3 / 06.01.2017 / 15.84 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017
23 / Nandyala / 17.50 / 3 / 06.01.2017 / 33.47 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017
24 / Ananthapuramu / 17.50 / 3 / 06.01.2017 / 29.76 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to for TS on 04.04.2017. After EnC PH visit on 21.04.2017, ULB conveyed that earlier location considered while preparation of DPR is changed. Accordingly DPR revision in progress and revised DPR to be submitted for TS.
25 / Kavali / 12.25 / 2 / 22.11.2016 / 29.11 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB & SE-PH office for Technical Sanction on 04.04.2017
26 / Srikalhasthi / 17.50 / 3 / 06.01.2017 / 26.85 / 82 / 03.03.2017 / 04.04.2017 / DPR submitted to ULB &SE-PH office for Technical Sanction on 04.04.2017.
3. Storm Water Drainage DPRs (2016-20)
S.No. / Name of ULB / SAAP Project Cost (Cr.) / SLTC Approval / Administrative Sanction
(GO) / DPR Submitted for TS / TS Accorded / Remarks
No / Date / Approved Cost (Cr.) / No / Date
1 / Srikakulam / 35.13 / 6 / 08.05.2017 / 40.02 / 211 / 24.05.2017 / AS accorded. TS to be Accorded
2 / Rajahmundry / 60.41 / 6 / 08.05.2017 / 82.16 / 211 / 24.05.2017 / AS accorded. TS to be Accorded
3 / Kakinada / 76.97 / 6 / 08.05.2017 / 91.48 / 211 / 24.05.2017 / 02.05.2017 / DPR being reviewed by O/o EnC for TS
4 / Machilipatnam / 17.14 / 6 / 08.05.2017 / 21.51 / 211 / 24.05.2017 / 06.05.2017 / DPR being reviewed by O/o EnC for TS
5 / Nellore / 71.00 / AS accorded. TS to be Accorded
6 / Tirupathi / 10.30 / 6 / 08.05.2017 / 12.19 / 211 / 24.05.2017 / 23.05.2017 / Revised DPR submitted to ULB on 23.05.2017 for Technical Sanction.
7 / Ananthapuramu / 18.76 / AS accorded. TS to be Accorded
4. Parks & Green Spaces DPRs (2016-20)
S.No. / Name of ULB / SAAP Project Cost (Cr.) / SLTC Approval / Administrative Sanction
(GO) / DPR Submitted for TS / TS Accorded / Remarks
No / Date / Approved Cost (Cr.) / No / Date
1 / Srikakulam / 0.50 / 4 / 08.03.2017 / 3.45 / 116 / 28.03.2017 / AS accorded. TS to be Accorded
2 / Vizianagaram / 0.50 / 4 / 08.03.2017 / 1.44 / 116 / 28.03.2017 / TS Accorded
3 / GVMC / 1.20 / 4 / 08.03.2017 / 2.24 / 116 / 28.03.2017 / TS Accorded, Tender Floated
4 / Rajahmundry / 0.50 / 4 / 08.03.2017 / 1.92 / 116 / 28.03.2017 / TS Accorded
5 / Kakinada / 0.75 / 4 / 08.03.2017 / 1.05 / 116 / 28.03.2017 / TS Accorded
6 / Tadepalligudem / 0.50 / 4 / 06.01.2017 / 1.02 / 116 / 28.03.2017 / TS Accorded, Tender Floated
7 / Bhimavaram / 0.50 / 4 / 06.01.2017 / 0.89 / 116 / 28.03.2017 / TS Accorded
8 / Eluru / 0.50 / 4 / 08.03.2017 / 1.19 / 116 / 28.03.2017 / TS Accorded, Tender Floated
9 / Vijayawada / 1.20 / 4 / 06.01.2017 / 1.75 / 116 / 28.03.2017 / TS Accorded, Tender Floated
10 / Machilipatnam / 0.50 / 4 / 06.01.2017 / 1.00 / 116 / 28.03.2017 / TS Accorded, Tender Floated
11 / Gudivada / 0.50 / 4 / 06.01.2017 / 0.82 / 116 / 28.03.2017 / TS Accorded, Tender Floated
12 / Tenali / 0.50 / 4 / 06.01.2017 / 0.83 / 116 / 28.03.2017 / TS Accorded, Tender Floated
13 / Guntur / 0.75 / 4 / 06.01.2017 / 1.26 / 116 / 28.03.2017 / TS Accorded
14 / Narasaraopeta / 0.50 / 4 / 06.01.2017 / 0.74 / 116 / 28.03.2017 / TS Accorded, Tender Floated
15 / Chilakaluripeta / 0.50 / 4 / 06.01.2017 / 1.07 / 116 / 28.03.2017 / TS Accorded, Tender Floated
16 / Ongole / 0.50 / 4 / 06.01.2017 / 0.67 / 116 / 28.03.2017 / TS Accorded, Tender Floated
17 / Nellore / 0.63 / 4 / 06.01.2017 / 1.11 / 116 / 28.03.2017 / TS Accorded
18 / Tirupathi / 0.63 / 4 / 08.03.2017 / 0.97 / 116 / 28.03.2017 / TS Accorded, Tender Floated
19 / Chittoor / 0.50 / 4 / 08.03.2017 / 1.29 / 116 / 28.03.2017 / TS Accorded, Tender Floated
20 / Madanapalli / 0.50 / 4 / 06.01.2017 / 0.74 / 116 / 28.03.2017 / TS Accorded
21 / Dharamavaram / 0.50 / 4 / 06.01.2017 / 1.10 / 116 / 28.03.2017 / TS Accorded, Tender Floated
22 / Guntakul / 0.50 / 4 / 06.01.2017 / 0.66 / 116 / 28.03.2017 / TS Accorded, Tender Floated
23 / Kadapa / 0.50 / 4 / 08.03.2017 / 1.23 / 116 / 28.03.2017 / TS Accorded
24 / Kurnool / 0.63 / 4 / 08.03.2017 / 1.26 / 116 / 28.03.2017 / TS Accorded, Tender Floated
25 / Adoni / 0.50 / 4 / 06.01.2017 / 0.72 / 116 / 28.03.2017 / TS Accorded, Tender Floated
26 / Nandyala / 0.50 / 4 / 06.01.2017 / 0.95 / 116 / 28.03.2017 / TS Accorded, Tender Floated
27 / Ananthapuramu / 0.50 / 4 / 08.03.2017 / 0.77 / 116 / 28.03.2017 / TS Accorded, Tender Floated
28 / Hindupur / 0.50 / 4 / 06.01.2017 / 0.61 / 116 / 28.03.2017 / TS Accorded, Tender Floated
29 / Tadipatri / 0.50 / 4 / 08.03.2017 / 0.67 / 116 / 28.03.2017 / AS accorded. TS to be Accorded
30 / Proddutur / 0.50 / 4 / 06.01.2017 / 0.91 / 116 / 28.03.2017 / TS Accorded, Tender Floated
31 / Kavali / 0.50 / 4 / 06.01.2017 / 1.21 / 116 / 28.03.2017 / TS Accorded, Tender Floated
32 / Srikalhasthi / 0.50 / 4 / 06.01.2017 / 1.07 / 116 / 28.03.2017 / AS accorded. TS to be Accorded
SAAP 2017-20 Projects (Summary)
S.No. / Sector / SAAP Approved Cost (Cr.) / No. of DPRs / DPRs Submitted / DPRs to be submitted / SLTC Approved / SHPSC Approved / TS Accorded / TS Approved Cost (Cr.)
1 / Parks & Green Spaces / 31.85 / 32 / 0 / 32 / 1 / 1 / 0
Status / Remarks / Comments
DPR Design Stage(31):Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,Gudivada,Tenali,Guntur,
Narasaraopeta,Chilakaluripeta,Ongole,Nellore,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,Kurnool,Adoni,
Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,Kavali,Srikalhasthi
Approved by SLTC(1): Srikakulam
Approved by SHPSC(1): Srikakulam
4. Parks & Green Spaces DPRs (2017-20)
S.No. / Name of ULB / SAAP Project Cost (Cr.) / SLTC Approval / Administrative Sanction
(GO) / DPR Submitted for TS / TS Accorded / Remarks
No / Date / Approved Cost (Cr.) / No / Date
1 / Srikakulam / 0.87 / 4 / 08.03.2017 / 116 / 28.03.2017 / DPR prepared under SAAP 2016-17 project for entire mission period
2 / Vizianagaram / 0.87 / DPR submission due
3 / GVMC / 2.09 / DPR submission due
4 / Rajahmundry / 0.87 / DPR submission due
5 / Kakinada / 1.31 / DPR submission due
6 / Tadepalligudem / 0.87 / DPR submission due
7 / Bhimavaram / 0.87 / DPR submission due
8 / ELURU / 0.87 / DPR submission due
9 / Vijayawada / 2.09 / DPR submission due
10 / Machilipatnam / 0.87 / DPR submission due
11 / Gudivada / 0.87 / DPR submission due
12 / Tenali / 0.87 / DPR submission due
13 / Guntur / 1.31 / DPR submission due
14 / Narasaraopeta / 0.87 / DPR submission due
15 / Chilakaluripeta / 0.87 / DPR submission due
16 / Ongole / 0.87 / DPR submission due
17 / Nellore / 1.10 / DPR submission due
18 / Tirupathi / 1.10 / DPR submission due
19 / Chittoor / 0.87 / DPR submission due
20 / Madanapalli / 0.87 / DPR submission due
21 / Dharamavaram / 0.87 / DPR submission due
22 / Guntakul / 0.87 / DPR submission due
23 / Kadapa / 0.87 / DPR submission due
24 / Kurnool / 1.10 / DPR submission due
25 / Adoni / 0.87 / DPR submission due
26 / Nandyala / 0.87 / DPR submission due
27 / Ananthapuramu / 0.87 / DPR submission due
28 / Hindupur / 0.87 / DPR submission due
29 / Tadipatri / 0.87 / DPR submission due
30 / Proddutur / 0.87 / DPR submission due
31 / Kavali / 0.87 / DPR submission due
32 / Srikalhasthi / 0.87 / DPR submission due