ARTICLE 5.1NOTIFICATIONS FOR ENHANCED CONTROLS OR INSPECTIONS
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[1]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 5.2DETENTION
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[2]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 5.3TEST PROCEDURES
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[3]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
Article 7.2ELECTRONIC PAYMENT
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[4]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note :
ARTICLE 7.9PERISHABLE GOODS
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[5]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 8: BORDER AGENCY COOPERATION
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[6]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 10.2ACCEPTANCE OF COPIES
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[7]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
Article 10.3 USE OF INTERNATIONAL STANDARDS
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[8]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
Article 10.4SINGLE WINDOW
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[9]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
Article 10.7COMMON BORDER PROCEDURES AND UNIFORM DOCUMENTATION REQUIREMENTS
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[10]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 10.8REJECTED GOODS
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[11]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
TN/TF/W/143/Rev.7
Page 1
ARTICLE 23.2. NATIONAL COMMITTEE ON TRADE FACILITATION
I. Situational/Gap Analysis
Describe Your Current Situation / Barriers(Give Reasons for non-compliance) / Actions/Resources Required & Cost
(Number the Actions) / TACB Resources Needed
(Specify Action Number)
A. Policy/Legal Framework: / 1.
B. Procedures: / 1.
C. Institutional Framework: / 1.
D. Human Resources/Training: / 1.
E. Communication/Information Technology: / 1.
F. Equipment & Infrastructure: / 1.
G. Other Issues to Note[12]: / 1.
II. Questionnaire
- Do you comply with this measure?
- You expect to implement this measure by:
- If Category B or C approximately how much time will you need to implement?
- Identify technical assistance projects/agencies that have, or are, helping you implement this measure:
- Lead agency or organization and other stakeholders that would be responsible for implementation of this measure:
- Stakeholders not participating in assessment of this measure that should be consulted:
- National Priority Level (For implementation):
- Issues to note:
[1]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[2]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[3]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[4]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[5]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[6]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[7]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[8]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[9]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[10]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[11]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).
[12]For example, resistance to change; lack of political will or stakeholder awareness or buy-in; other issues (positive or negative).