RECOMMENDATION TO NAESB WGQ EXECUTIVE COMMITTEE

Request No.: 2016 WGQ AP Item 3(c)(iii) / 2017 WGQ AP Item 3(b)(ii)

(Request R16007)

Part 2 - 2016 WGQ AP Item 3(c)(i) / 2017 WGQAP Item 3(b)(i)

(Request R16003 b)

Requester: FIS Global – Energy Services (R16007)

Skipping Stone & EDF (R16003)

1. RECOMMENDED ACTION: EFFECT OF EC VOTE TO ACCEPT RECOMMENDED ACTION:

Accept as requested / X / Change to Existing Practice
X / Accept as modified below / Status Quo
Decline

2. TYPE OF DEVELOPMENT/MAINTENANCE

Per Request: / Per Recommendation:
Initiation / Initiation
X / Modification / X / Modification
Interpretation / Interpretation
Withdrawal / Withdrawal
Principle (x.1.z) / Principle (x.1.z)
X / Definition (x.2.z) / X / Definition (x.2.z)
X / Business Practice Standard (x.3.z) / X / Business Practice Standard (x.3.z)
Document (x.4.z) / Document (x.4.z)
Data Element (x.4.z) / Data Element (x.4.z)
Code Value (x.4.z) / Code Value (x.4.z)
X12 Implementation Guide / X12 Implementation Guide
Business Process Documentation / Business Process Documentation

3. RECOMMENDATION

SUMMARY:

Add NAESB WGQ Definition 1.2.[z1] and NAESB WGQ Standard 1.3.[z1].

Page 2 of 3

RECOMMENDATION TO NAESB WGQ EXECUTIVE COMMITTEE

Request No.: 2016 WGQ AP Item 3(c)(iii) / 2017 WGQ AP Item 3(b)(ii)

(Request R16007)

Part 2 - 2016 WGQ AP Item 3(c)(i) / 2017 WGQAP Item 3(b)(i)

(Request R16003 b)

Requester: FIS Global – Energy Services (R16007)

Skipping Stone & EDF (R16003)

STANDARDS LANGUAGE

NAESB WGQ Proposed Definition 1.2.[z1]

A Shaped Nomination is a nomination in which a Service Requester provides both a daily quantity and a quantity for each hour of the Gas Day, with each hour beginning at the start of the hour (e.g. 10:00 AM).

NAESB WGQ Proposed Standard 1.3.[z1]

Where a Transportation Service Provider offers a service under its tariff, general terms and conditions, and/or contract provisions which expressly provides for a Service Requester (SR) to submit a Shaped Nomination, the SR should submit its nomination for that service as a Shaped Nomination using NAESB WGQ Standard No. 1.4.1 (Nomination). Receipt of service expressly providing for the use of a Shaped Nomination may require additional coordination with interconnected parties.

A SR utilizing other services that do not expressly provide for the use of a Shaped Nomination should not be required to submit a Shaped Nomination nor does this standard prescribe any affect for services that do not expressly provide for Shaped Nominations.

4. SUPPORTING DOCUMENTATION

a. Description of Request:

Develop business practices as needed to support R16007: “Update the NAESB Nomination dataset and related datasets to support the ability for a service requester to submit a single nomination with hourly quantities when such a service is supported by the TSP.”

b. Description of Recommendation:

Business Practices Subcommittee

See the agenda and corresponding meeting minutes for the Business Practices Subcommittee for GEH related annual plan items and their corresponding discussions for the following dates:

·  07/12/2016

·  07/28/2016

·  08/11/2016

·  08/25/2016

·  09/12-13/2016

·  09/29/2016

·  10/04/2016

·  10/18/2016

·  10/27-28/2016

·  11/02/2016

·  11/09-10/2016

·  11/16/2016

·  11/30-12/01/2016

·  12/08-09/2016

·  12/14/2016

·  12/19-20/2016

·  01/17/2017

Motion (01/17/2017):

Proposed Revised NAESB WGQ Definition 1.2.[z1]

A Shaped Nomination is a nomination in which a Service Requester provides both a daily quantity and a quantity for each hour of the Gas Day, with each hour beginning at the start of the hour (e.g. 10:00 AM).

Motion passed unanimously

Motion (12/08-09/2016):

Proposed NAESB WGQ Definition 1.2.[z1]

A Shaped Nomination is a nomination in which a Service Requester provides both a daily quantity and a quantity for each hour of the Gas Day.

Proposed NAESB WGQ Standard 1.3.[z1]

Where a Transportation Service Provider offers a service under its tariff, general terms and conditions, and/or contract provisions which expressly provides for a Service Requester (SR) to submit a Shaped Nomination, the SR should submit its nomination for that service as a Shaped Nomination using NAESB WGQ Standard No. 1.4.1 (Nomination). Receipt of service expressly providing for the use of a Shaped Nomination may require additional coordination with interconnected parties.

A SR utilizing other services that do not expressly provide for the use of a Shaped Nomination should not be required to submit a Shaped Nomination nor does this standard prescribe any affect for services that do not expressly provide for Shaped Nominations.

Proposed Instruction to IR and Technical Subcommittees:

The WGQ BPS instructs the Joint IR/Technical Subcommittees to accommodate the ability for a Service Requester to submit Shaped Nominations during each of the NAESB nomination cycles in the NAESB WGQ Standard No. 1.4.1 Nomination and any other corresponding data sets as necessary. Additionally, IR/Technical should investigate whether the solution should accommodate daylight savings time variances of 23-hour days and 25-hour days.

Motion passed a balance vote with 7.71 in favor and .28 opposed

Segment / Votes Cast / Balanced Vote
YES / NO / TOTAL / YES / NO / TOTAL
End Users / 1 / 0 / 1 / 1 / 0 / 1
LDCs / 6 / 1 / 7 / 1.714286 / 0.285714 / 2
Pipeline / 12 / 0 / 12 / 2 / 0 / 2
Producer / 1 / 0 / 1 / 1 / 0 / 1
Services / 5 / 0 / 5 / 2 / 0 / 2
Total / 24 / 1 / 25 / 7.714286 / 0.285714 / 8

Page 2 of 3