Technical preliminary remarks for object preparation with Kaifinish

Corrosion protection/renovation of pipes and plants with subsequent insulation work inside the building.
The following service description is based on the following contractual conditions, standards and directives:

DIN 4140: "Insulation work on industrial installations and building equipment - Execution of thermal and cold insulations"

AGI Q 151 (corrosion protection under insulations)

DIN EN ISO 12944: "Paints and varnishes - Corrosion protection of steel structures by powder coating systems"

Mounting notes of the manufacturers

Corrosion protection with system corrosion protection with Kaifinish Primer, Base and Cover.

Kaifinish Primer:

First coat with primer.Mandatory for non-ferrous metals.

Colour: Ochre-yellow

Kaifinish Base:

Base coat on ferrous metals or Kaifinish Primer. Compensates for grooves and erosion.

Colour: Light grey (matte)

Layers:2-3 layers necessary

Consumption:Approx. 250 g/m2 (indicated per layer, observe multiple-layered structure)

Layer thickness:Wet:approx. 180 µm(indicated per layer, observe multiple-layered structure)

Dry:approx. 80 µm(indicated per layer, observe multiple-layered structure)

Drying time:between the brushing runs: 10 minutes

Total drying time:30 minutes

(at ambience and surface temperatures of 20°C and a rel. humidity of 65%)

Critical humidity (at least +3°C above dew point limit) and current Technical Bulletin must be observed.

Kaifinish Cover:

Topcoat is applied on Kaifinish Base. Completes the system structure.

Colour: Dark grey

Layers:2-3 layers necessary

Consumption:Approx. 240 g/m2 (indicated per layer, observe multiple-layered structure)

Layer thickness:Wet:approx. 160 µm(indicated per layer, observe multiple-layered structure)

Dry:approx. 80 µm(indicated per layer, observe multiple-layered structure)

Drying time:between the brushing runs: 10 minutes

Total drying time: 3 hours

(at ambience and surface temperatures of 20°C and a rel. humidity of 65%. Complete curing depends on layer thicknesses and environment; it must be reviewed from case to case)

Critical humidity (at least +3°C above dew point limit) and current Technical Bulletin must be observed.

Kaifinish Primer
First coat with primer.
Tube length:______m

Outer tube diameter:______cm

Surface:______m2

Kaifinish Base

Base coat on ferrous metals or Kaifinish Primer.

Tube length:______m

Outer tube diameter:______cm

Surface:______m2

Kaifinish Base

Topcoat is applied on Kaifinish Base.

Tube length:______m

Outer tube diameter:______cm

Surface:______m2