Day 1- Oct 23, 2009 Afternoon: Stream P (Plenary Hall- 2nd Level)
Timeslot / Presenter / Title / Category
1:30 – 2:00 / # 1P Tech Paper:
Mr. Young Sun Hong, Korean Standards Association, Korea / KOREAN NATIONAL QUALITY CIRCLE COMPETITION SYSTEMS AND EVALUATION CRITERIA / NGO – Continuous Improvement
2:00 – 2:30 / # 2P Project Competition
ANWESHANA, SAIL - Rourkela Steel Plant , India / Elimination of Cobble in ROT Side Guard in HSM / Production
2:30 – 3:00 / # 3P Project Competition:
HULANTER, PT Pamapersada Nusantara , Indonesia / Increased Production Target from 16.582.387 ton to 17.000.000 Tons / Production
3:00 – 3:30 / # 4P Project Competition
MC2 QCC12, TVS Motor Company Ltd., India / Reduction of internal customer complaints in Scooty pep Scooterettes / Production
3:30 – 4:00 / # 5P Project Competition
KIRAN, Aditya Birla Insulators India / Reduction in high firing rejection of insulators thru’ focused improvement / Production
4:00 – 4:30 / # 6P Project Presentation
MOP Creative, PT. Indominco Mandiri, Indonesia / Increased High Ash Coal Production equal to 43% during 7 month. / Production
4:30– 5:00 / # 7P Project Competition
FARADAY , Chrome Ore Beneficiation Plant, FAMD, TATA STEEL India / Increasing the Plant availability by minimizing the down time of Tailing Thickener / Production
5:00- 5:30 / #8P Project Competition
TRIPLE ONE, Bharat Heavy Electricals Ltd , India / Cycle Time Reduction in Hemi-spherical Dished End Cover Manufacturing. / Production
Day 2- Oct 24, 2009 Morning: Stream P (Plenary Hall- 2nd Level)
Timeslot / Presenter / Title / Category
8:00-8:30 / # 1P Project Competition
D’ Survivor
Toyota Motor Philippines Corp., Philippines / Elimination of Falling Door Assembly from Pallet / Production
8:30 – 9:00 / # 2P Project Competition
VIKAS-1489, SAIL Alloy Steel Plant, India / Failure of Temperature & Sample Car at AOD Refining Unit / Production
9:00-9:30 / #3P – Project Showcase
Sweeper Team, China Mobile Group Guangdong Co. Ltd, China / How to Reduce the Complaints of SMS / Service- Continuous Improvement
9:30-10:00 / # 4P Project Competition
RAINBOW, Lucas TVS Ltd, Netapakkam, Pududcherry, India / Elimination of Assembly Line Rejection on Gear Reduction Starter Motor Assembly / Production
10:00-10:30 / # 5P Project Competition
S.T.A.R.S.
Sanyo Semiconductors Manufacturing Philippines Corp., Philippines / 92.3% Reduction of Insufficient Preform Abnormality Originating at Die Bonding Solder Wire Assembly by March 2008 / Production
10:30-11:00 / # 6P Project Showcase:
The Network Service Support QC, China Mobile Group Guangdong Co. Ltd., China / Develop a New Method of Semantic of SMS port / Service- Continuous Improvement
11:00-11:30 / # 7P Project Competition
Ultra, PT. Semen Gresik (Persero) Tbk.,Indonesia / Lowering the Delays Frequency on the Cement Distribution at the Group 63DPM1 Packer Machine, the 2nd Tuban / Production
11:30-12:00 / # 8P Project Competition
GAGAN, Hero Motors Limited India / Backlash not adjusted within specification / Production
12:00 – 13:00 / Lunch Break (Lunch @ Exhibit Hall 2- Main Level)
Day 1- Oct 23, 2009 Afternoon: Stream A ( EXHIBIT HALL 1-Main Level)
Timeslot / Presenter / Title / Category
1:30 – 2:00 / # 1A Tech Paper
Mr. Cezar Travina, Nestle Philippines Inc., Phils / JOURNEY TO MISSION-DIRECTED WORK TEAM: THE NESTLE PHILIPPINES-CAGAYAN DE ORO FACTORY EXPERIENCE / Manufacturing- Continuous Improvement
2:00 – 2:30 / # 2A Project Competition
NIDAN, SAIL –Bolani Ore Mines India / Frequent jamming & stopping of primary screen house trolley / Production
2:30 – 3:00 / # 3A Project Competition
SAMBHABANA, SAIL - Rourkela Steel Plant , India / Improving the life of burner motors in Synthesis gas plant of SSM / Production
3:00 – 3:30 / # 4A Project Competition
Wastreat, PT ANTAM Tbk.
Gold Mining Business Unit Indonesia / Reduction of Deviation from target of Thickener Overflow’s Suspended Solid Parameter at Tailings Treatment Area / Production
3:30 – 4:00 / # 5A Project Competition
ABHIYAN, SAIL - Bhilai Steel Plant , India / Developing a Solution for Optimum Moisture Control in Sinter Raw Mix / Production
4:00 – 4:30 / # 6A Project Competition
Power of Pentagon, Sundaram Clayton Ltd., India / Productivity Improvement in HX 25W Compressor Cover machining cell / Production
4:30 – 5:00 / # 7A Project Competition
CHUNAUTI, SAIL - Bhilai Steel Plant , India / Stabilization of 7 Meters Tall Battery Health / Production
5:00-5:30 / # 8A Project Competition
THE AMINATORS 2, Pilipinas Kao, Inc., Philippines / Reduction of Anti-Foaming Agent Usage at Tertiary Amine Plant 2 / Production
Day 2- Oct 24, 2009 Stream A (EXHIBIT HALL 1- Main Level)
Timeslot / Presenter / Title / Category
8:00 – 8:30 / # 1A Project Competition
Quantum Team
ST MicroElectronics Inc., Philippines / Broken Wafer Elimination at FCC1-004 / Production
8:30 – 9:00 / # 2A Project Competition
MODULE, Hindustan Aeronautics Ltd. – Avionics Division , India / Reducing the Lifting of Wire Bonds on Ultrasonic Wire Bonder / Production
9:00-9:30 / #3A Project Showcase
Advance Gas Detector
Hongkong & China Gas Co., Ltd.Hongkong, China / Retractable and Expandable Visual Gas Detector for Varying Angle Inspection. / Mfg- Continuous Improvement
9:30-10:00 / #4A Project Competition
AGNI, Hindustan Aeronautics Ltd., India / Rejection of Hot Working Steel profile Mandrel Used in Ring Rolling Operation / Production
10:00-10:30 / # 5A Project Competition
NAVSHAKTI, NTPC Ltd., India / Enhancement of Effectiveness of Soot Blower for Higher Generation. / Production
10:30-11:00 / # 6A Project Competition
SRADDHA – CMM, RINL-Visakhapatnam Steel Plant India / Reduction of Hammer Crusher Downtime in Sinter Plant / Production
11:00-11:30 / # 7A Project Competition
PUL 03 M, Bharat Heavy Electricals Ltd., India / Higher Productivity in Machining of Mill Side Housing and Base on Vertical Boring Machine. / Production
11:30-12:00 / #8 Project Showcase
PELANGI, Fire and Rescue Department of Malaysia, Malaysia / Difficulty during Operations when Using Fire Hydrant with Missing Elbow. / Showcase
12:00 – 1:00 / Lunch Break(Lunch @ Exhibit Hall 2-Main Level)
Day 1- Oct 23, 2009 Afternoon: Stream B (RM 101-Main Level)
Timeslot / Presenter / Title / Category
1:30 – 2:00 / # 1B Tech Paper
Mr. Nandan Raghuwanshi & Mr. Devendra Patel, Hero Motors, India / CREATIVE WAYS TO DEVELOP TEAMS AND ENHANCE TEAMWORK / Manufacturing- People Development
2:00 – 2:30 / # 2B Project Competition
MC2 QCC 15, TVS Motor Company Ltd., India / Internal Customer Schedule no Meet. / Production
2:30 – 3:00 / # 3B Project Competition
AQUILINES, NTTF at RD
Tata Technical Educational Centre, India / Integrated Negative Development Using Software / Production
3:00 – 3:30 / # 4B Project Competition
PATRIOT, WABCO-TVS(India) Limited ,India / Capacity Enhancement of Spring Brake Actuator as a Product / Production
3:30 – 4:00 / # 5B :Project Showcase
Interactive MMS Group, China Mobile Group Guangdong Co. Ltd., China / The Development of Interactive MMS Technology / Service- Continuous Improvement
4:00 – 4:30 / # 6B Project Competition
VIDYUT, BEML Limited, India / Elimination of Electrical Problems on BG825 Equipment / Production
4:30 – 5:00 / # 7B Project Competition
SOURA SAKTHI, Solar Semiconductor Pvt. Ltd. , India / Track Erases on M1 Machine / Production
5:00- 5:30 / # 8B Project Competition
CHAITANYA, Solar Semiconductor Pvt. , India / High Cell Breakage Rate in Auto Line / Production
Day 2- Oct 24, 2009 Stream B (RM 101-Main Level)
Timeslot / Presenter / Title / Category
8:00-8:30 / # 1B Project Competition
SIGMA, MCC PTA India Corp. Private , India / High Cost in Consumable Materials / Production
8:30 – 9:00 / # 2B Project Competition
Dharam, Naval Dockyard, Mumbai, India / Frequent Delay in Completing Trials of Steam and Motor Driven Pumps / Production
9:00-9:30 / # 3B Project Competition
EVERGREEN, Adahi India Glass Ltd., India / To Reduce Rear Axle Breakdown / Production
9:30-10:00 / #4B Project Competition
ENVIRO, Lucas TVS Ltd MTH Road, Padi Chennai, India / Elimination of Quality Variation in Sewage Treated Water / Production
10:00-10:30 / # 5B Project Competition
NORTHERN SPRING TEAM: Pilmico Foods Corp., Philippines / Elimination of first pallet flour handling cost starting February 2008 / Production
10:30-11:00 / # 6B Project Competition
IDLER, Asok Heyland, Ennore, India / Machine Down time reduction in Idler Gear Bore & Face grinding Machine through process improvements in 5 phases / Production
11:00-11:30 / #7B Project Competition
SPARK, BHEL - Heavy Electricals Equipment Plants India / Frequent Breakdowns in Table Movement of Plano-Milling Machine / Production
11:30-12:00 / # 8B Project Competition
DELIGHT, Asok Heyland, Ennore, India / Elimination of Front Axle Rejection due to Hub End Play and Reduce effort and Ergonomic Index in Hub Sub-Assembly / Production
12:00 – 1:00 / Lunch Break(Lunch @ Exhibit Hall 2-Main Level)
Day 1- Oct 23, 2009 Afternoon: Stream C (RM 102- Main Level)
Timeslot / Presenter / Title / Category
1:30 – 2:00 / # 1C Tech Paper
Mr. Gilbert M. Llovit, GCC Ltd, Philippines / THE SAGA OF NAGA CITY: LOCAL SOLUTIONS TO WORLD-CLASS QUALITY GOVERNANCE / Government- Continuous Improvement
2:00 – 2:30 / # 2C Project Competition
e-Power, Apollo Tyres Ltd India / Reduction in the down time of cutter carriage / Production
2:30 – 3:00 / # 3C Project Competition
SMART QUALITY CIRCLE, FAG Bearings India Ltd.,India / Customer Complaint related to Axial Play / Production
3:00 – 3:30 / # 4C Project Competition
R&D 10, TVS Motor Company Ltd., India / Elimination of Vehicle Rejection in Scooty Streak / Production
3:30 – 4:00 / #5C Project Showcase
DEARBC TEAM, Del Monte Phils. Employees Agrarian Reform Beneficiaries Coop, Philippines / Modified Tractor Furrower Used for Bedding / KSC
4:00 – 4:30 / # 6C Project Competition
QCC POWER, Hindustan Aeronautics Ltd., India / Failure of Potentiometers for Ajax assembly of Jaguar Aircraft / Production
4:30 – 5:00 / #7C Project Competition
ACTIVATORS CIRCLE: Philippine Sinter Corp., Philippines / Level-up Sinter Productivity Thru Advanced Activation of Burnt Lime / Production
5:00 – 5:30 / # 8C Project Competition
SENDZIMER, SAIL – Salem Steel Plant , India / Frequent Tearing of Z-mill Recovery Filter Mesh / Production
Day 2- Oct 24, 2009 Stream C (RM 102-Main Level)
Timeslot / Presenter / Title / Category
8:00-8:30 / # 1C Project Competition
EKTAA, Jayushin Ltd., India / Reduce the Steering Body Rejection due to Buzzer Wire NG / Production
8:30 – 9:00 / # 2C Project Competition
ORBIT QUALITY CIRCLE, Hindustan Aeronautics Ltd., India / Production Delay of Feed Line N – Top Assembly due to Geometrical Deviations / Production
9:00-9:30 / # 3C Project Showcase
Exploration Team, China Mobile Group Guangdong Co. Ltd., China / Decreasing TD-SCDMA Video Phone Call Loss Rate of HK-Zhuhai-Macao Bridge Construction Line / Service- Continuous Improvement
9:30-10:00 / # 4C Project Competition
Linspire Roberts Automotive Industrial Parts Manufacturing Corp., Philippines / Hard to Insert bolt to weld nut (Customer Claims) / Production
10:00-10:30 / # 5C Project Competition
PMD 01, TVS Motor Company Ltd., India / Reduction of Energy Loss at Plant 1 / Production
10:30-11:00 / # 6C Project Showcase
THE SWEEPERS TEAM, Allied Services Multi-Purpose Coop., Philippines / Pressure Washer / KSC
11:00-11:30 / # 7C Project Competition
LAKSHYA, Hindustan Aeronautics Ltd. – Engine Division , India / High Rejection and Rework in Rivetting of Wheel Assembly Turbine Part at Engine Assembly Part No. 8675697 / Production
11:30-12:00 / #8C Project Competition

SMS Quality Circle, Mazagon Dock Ltd., India

/ Difficulty in Cutting of Pre-insulated Double Spiral Duct / Production
12:00 – 1:00 / Lunch Break(Lunch @ Exhibit Hall 2-Main Level)
Day 1- Oct 23, 2009 Afternoon: Stream D (RM 103-Main Level)
Timeslot / Presenter / Title / Category
1:30 – 2:00 / # 1D Tech Paper
Mr. Gopal Prasad Singh, Bhilai Steel Plant, India / ENHANCING EFFECTIVENESS OF QUALITY CIRCLE THROUGH MIS / Manufacturing- People Development
2:00 – 2:30 / #2D Project Showcase
Human Machine, Korea Midland Power Co. Ltd Korea / Profit increase in trading electric power by improving Maintenance methods of Pump/Turbine / Service-Continuous Improvement
2:30 – 3:00 / # 3D Project Competition
QUEST, SAIL - Rourkela Steel Plant , India / Elimination of equipment damage and thereby coal mix-up in coal blending bunkers / Non-Production
3:00 – 3:30 / # 4D Project Competition
OSHE 2, National University of Singapore, Singapore / Workspace for Laboratory OH & S Certification Scheme / Non-Production
3:30 – 4:00 / # 5D Project Competition
VOYAGER, Bharath Heavy Electricals Ltd. Electronics Division , India / Complicated process, More varieties of hardwares and tools and increased cycle time in (Stat. Freq. Control) Panel / Non-Production
4:00 – 4:30 / # 6D Project Competition
Euripides QC, NEC Telecom Software Philippines, Inc., Philippines / An experiential report on software QC Circle (SWQC) activities based on the Process Network Analysis / Non-Production
4:30 – 5:00 / # 7D Project Competition
VIDYUT, OCL India Ltd., India / High down time of the Freight Elevator of Silica Refractory Plant Mill House / Non-Production
5:00- 5:30 / #8D Project Competition
CARTO, Lucas TVS Ltd
MTH Road,
Padi Chennai, India / Reduction of Inventory in DE Hardening Machine / Non-Production
Day 2- Oct 24, 2009 Stream D (RM 103-Main Level)
Timeslot / Presenter / Title / Category
8:00-8:30 / # 1D Project Competition
EXHIBITORS, Singapore Police Force, Singapore / Enhanced Safety and Security in Public Parks / Non-Production
8:30 – 9:00 / # 2D Project Competition
AVISHKAR, SAIL - Durgapur Steel Plant , India / Malfunctioning of Thermax System Motorized Valved / Non-Production
9:00-9:30 / # 3D Project Competition
Manos Dela Colada, Alabang Medical Clinic Las Piñas Branch, Philippines / Poor Compliance on Hand Hygiene / Non-Production
9:30-10:00 / # 4D Project Competition
Tin Commanders
ST MicroElectronics Inc., Philippines / Solderability Failure Elimination on QFP80-02. / Non-Production
10:00-10:30 / # 5D Project Competition
MORWITS, Singapore Armed Forces (Army)
Ministry of Defence, Singapore / Automated Cleaning Kit For Gun Barrel / Non-Production
10:30-11:00 / # 6D Project Competition
Thejas, Saint-Gobain Glass India, India / Higher process Setup time Reduction / Non-Production