Traffic Calming Measures in Finger Lakes

(Region 3 and 4)

Location Description Date

Skaneateles Extend 30 MPH speed limit zone on RTE 41A Sept 2008

Extend 30 MPH speed limit zone on RTE 20 Sept 2008

Ovid Add 45 MPH speed limit on RTE 414 Nov 2008

Replace school speed limit signs Oct 2008

Install edge lines for parking RTE 414 Aug 2008

Enhance crosswalks on RTE 414 Aug 2008

Interlaken Install edge lines for parking on RTE 96 Aug 2008

Enhance crosswalks on RTE 96 Sept 2008

Upgrade school ped crossing signs & beacons April 2009

Extend 30 MPH speed limit RTE 96 & RTE 96A Oct 2008

Install “Noise Limit 90 Decibel” signs Oct 2008

Waterloo Enhance school crosswalks and signs RTE 96 Nov 2008

Enhance crosswalk RTE 5/20 Nov 2008

Seneca Falls Install edge lines RTE 5/20 Sept 2008

Extend 30 MPH speed limit RTE 414 Nov 2008

Add new crosswalk RTE 5/20, PIN 307620 2011

Union Springs Add 45 MPH speed limit RTE 90 Nov 2008

Enhance crosswalks and upgrade signs RTE 90 Sept 2008

Add 2 new crosswalks and signs RTE 90 Sept 2008

Cayuga Add 45 MPH speed limit RTE 90 Sept 2008

Enhance crosswalks RTE 90 Oct 2008

Install “Fire House Ahead” sign RTE 90 Oct 2008

Aurora Add 45 MPH speed limit RTE 90 Mar 2009

Add “Yield to Peds in Crosswalk” signs RTE 90 Apr 2009

Add “Grade Warning “ signs RTE 90, PIN 315524 2010

Homer Upgrade school crosswalk signs RTE 11, 41 & 90 Oct 2008

Enhance crosswalks RTE 11, 41 & 90 Aug 2008

Add Playground Signs RTE 90 Sept 2008

Install edge lines for parking RTE 11 Sept 2009

Add 40 MPH speed limit RTE 41 Sept 2008

Homer ( con’t ) Enhance ped signal RTE 11 @ James Jan 2009

Ithaca Add park sign RTE 89 Dec 2008

Add new crosswalk and signs RTE 89 Aug 2008

Enhance crosswalk RTE 89 Aug 2008

Add 45 MPH speed limit RTE 13/34/96 Dec 2008

Add Driveway warning signs Dec 2008

Add grade warning signs w/Flashing Beacons RT 96 Mar 2009

Add grade warning signs w/Flashing Beacons RT 79 Mar 2009

Palmyra Install tick mark pavement markings[i] Sep 2008

Install larger Speed Zone Ahead warning sign Sep 2008

Geneva Signal Replacement- 5&20 at Pultney Street[ii] Spring, 2010

As of April 2010, 41 items are complete and 3 items remain to be done as part of the ongoing capital projects – 2 items to be completed in 2010 and 1 in 2011.

[i] Short pavement markings perpendicular to pavement edge lines to slow down the traffic.

[ii] In the works, encountered problems with underground utilities. EIC is working with Contractor to resolve...to be complete in Spring, 2010.