Traffic Calming Measures in Finger Lakes
(Region 3 and 4)
Location Description Date
Skaneateles Extend 30 MPH speed limit zone on RTE 41A Sept 2008
Extend 30 MPH speed limit zone on RTE 20 Sept 2008
Ovid Add 45 MPH speed limit on RTE 414 Nov 2008
Replace school speed limit signs Oct 2008
Install edge lines for parking RTE 414 Aug 2008
Enhance crosswalks on RTE 414 Aug 2008
Interlaken Install edge lines for parking on RTE 96 Aug 2008
Enhance crosswalks on RTE 96 Sept 2008
Upgrade school ped crossing signs & beacons April 2009
Extend 30 MPH speed limit RTE 96 & RTE 96A Oct 2008
Install “Noise Limit 90 Decibel” signs Oct 2008
Waterloo Enhance school crosswalks and signs RTE 96 Nov 2008
Enhance crosswalk RTE 5/20 Nov 2008
Seneca Falls Install edge lines RTE 5/20 Sept 2008
Extend 30 MPH speed limit RTE 414 Nov 2008
Add new crosswalk RTE 5/20, PIN 307620 2011
Union Springs Add 45 MPH speed limit RTE 90 Nov 2008
Enhance crosswalks and upgrade signs RTE 90 Sept 2008
Add 2 new crosswalks and signs RTE 90 Sept 2008
Cayuga Add 45 MPH speed limit RTE 90 Sept 2008
Enhance crosswalks RTE 90 Oct 2008
Install “Fire House Ahead” sign RTE 90 Oct 2008
Aurora Add 45 MPH speed limit RTE 90 Mar 2009
Add “Yield to Peds in Crosswalk” signs RTE 90 Apr 2009
Add “Grade Warning “ signs RTE 90, PIN 315524 2010
Homer Upgrade school crosswalk signs RTE 11, 41 & 90 Oct 2008
Enhance crosswalks RTE 11, 41 & 90 Aug 2008
Add Playground Signs RTE 90 Sept 2008
Install edge lines for parking RTE 11 Sept 2009
Add 40 MPH speed limit RTE 41 Sept 2008
Homer ( con’t ) Enhance ped signal RTE 11 @ James Jan 2009
Ithaca Add park sign RTE 89 Dec 2008
Add new crosswalk and signs RTE 89 Aug 2008
Enhance crosswalk RTE 89 Aug 2008
Add 45 MPH speed limit RTE 13/34/96 Dec 2008
Add Driveway warning signs Dec 2008
Add grade warning signs w/Flashing Beacons RT 96 Mar 2009
Add grade warning signs w/Flashing Beacons RT 79 Mar 2009
Palmyra Install tick mark pavement markings[i] Sep 2008
Install larger Speed Zone Ahead warning sign Sep 2008
Geneva Signal Replacement- 5&20 at Pultney Street[ii] Spring, 2010
As of April 2010, 41 items are complete and 3 items remain to be done as part of the ongoing capital projects – 2 items to be completed in 2010 and 1 in 2011.
[i] Short pavement markings perpendicular to pavement edge lines to slow down the traffic.
[ii] In the works, encountered problems with underground utilities. EIC is working with Contractor to resolve...to be complete in Spring, 2010.