LCLSInjector Down-Time Work Prioritized for Fall of 2007
September13, 2007
P. Emma, et al.
Laser Repair and Upgrade (refer to B. White’s more complete list)
Top Priority:
- Install and test new oscillator
- Commission laser iris position feedback loop
Second Priority:
- Change magnification for larger spot size on vacuum transport windows
- Remove all air currents in laser room to stabilize laser beam
- Add energy attenuator where it will not affect temporal shape
- Make sure temperature monitors are everywhere needed, with alarm limits
- Add anamorphic imaging to remove ellipticity in laser spot
Beamline Repairs
Top Priority (and in order):
- Shim fields for BX12 & BX13 BC1 dipoles (remove and re-measure)
- Phase match X-band structure input/output couplers (possibly in situ)
- Realign X-band structure – move it 0.6-mm horizontally toward wall (north)?
- Add polarizing filter to OTRS11 to cut synchrotron radiation background
- Extend travel of YAGG1 and align (y-position needs to be lowered significantly)
- Fix TCAV roll angle (is presently rolled 2.5º CW looking downbeam)
- Inspect OTR2 foil for damage and possibly replace
- Repair FC01 and IM01, and reverse and align AM01 mirror
- Realign GTL YAG01, YAG02, BPM2, and BPM3 (and more?)
- Replace all 20-micron diameter wires with 40-micron (still Tungsten)
Second Priority:
- Realign RF gun (especially in z, where gun is presently 0.3 inches upstream)
- Widen BC1 mover range to 300 mm (original design requirement)
- Commission injector beamline laser alignment system (after AM01 mirror fixed)
- Replace VV03 with remotely controllable vacuum valve (is manual valve now)
- Fix roll angle (and database!) for BPM201 & BPMS1
- Rotate wire cards in WS04 and WS13 (becomes top priority if wires are replaced)
- Fix temporary support (jack stand) under BPM13
- Install VVS1 properly (remove C-clamp)
- Refine alignment of all components as time allows (QM02?)
- Install BPM processor on BPMM14 (take BPMG1 processor if needed) (done)
- Add amplifiers to bunch length monitors to extend dynamic range
- Measure permeability of QM02 vacuum chamber
- Re-align CQ11 tweaker quad (~1 mm off in x – beam data available)
- Fix all OTR/YAG-screen travel so that they no longer get stuck (fail to extract)
- Test gear-reducer to fix wire vibration
Beamline Upgrades (if possible)
Top Priority (if any upgrade can be implemented):
- Add an OTR screen nearby PR55 in BSY (or replace) – use OTR1?
- Add an OTR screen in sector-30, if time and location determined – use OTR3 (drop for now).
Second Priority:
- Add BPM between WS12 & OTR12 (if possible) (drop for now)
- Add color digital camera at OTR12 (see J. Frisch)
RF Systems
Second Priority:
- New LCLS master oscillator (or alternate)
- Need an automated procedure/software to fix phase jumps in the LLRF system
- Phase the three L1S sections w.r.t. each other (21-1d is 30 out of phase?)
- Move RF Hut water temperature regulation sensor to INSIDE of room
- Complete software and installation for Klystron PADs
- Complete beam synchronous data acquisition for RF system
- Provide EPICS feedback loop for LCLS-to-linac RF phase control (Matlab now)
Controls
Top Priority:
- Save/Compare/Restore facility in EPICS
Second Priority:
- Crop camera images in IOC’s and do centroid and rms calculations in IOC?
- Add tolerances and alarms on RF parameters