Progress

Since our last update, We have to-date:-

…at Workfront No. 1 (Cabra Gate to Lyndon Gate – south side of road)

(i)Completed the blockwork and placed the stone facing to the new boundary wall fronting the area known as the Poor Man’s Well;

(ii)Constructed the new cast-in-place concrete kerb;

(iii)Placed two sections of new footpath (either side of the Poor Man’s Well);

(iv)Erected railing posts.

…and at Workfront No. 2 (Lyndon Gate to entrance to Park Crescent Apartments – south side)

(i)Completed the construction of new boundary wall at the back of path fronting Park Crescent House (opposite Nephin Road junction)

(ii)Completed the construction ofnew kerb and footpath over same extent;

(iii)Completed the reconstruction[except surface layer to be placed at the end of the Works] of the carriageway over half of same extent, and

…and at Workfront No. 3 (Vehicular entrance to Park Crescent Apartments, to east end of Park Crescent Apartments – south side)

(i)Completed half of the construction of new boundary wall at the back of path fronting Park Crescent House;

(ii)Excavated old footpath and carriageway;

(iii)Placed stone foundation to carriageway area;

(iv)Place new ducting in footpath for ESB Networks over same extent;

(v)Have excavated, and are now constructing new gully pots and gully connections;

…and at Workfront No. 4 (The so-called Pallet Yard – south side)

(i)Completed the construction of a temporary boundary palisade fence – this fence will be removed before Christmas;

(ii)Felled the trees along the boundary of the Pallet Yard;

Meanwhile:

(a)The progress of the Works is currently disadvantaged due to the unavailability of ESB Networks to carry out essential cable relocations at Workfront 3 [fronting Park Crescent House apartments]. Works on Workfront 3 cannot progress further without ESB Networks’ assistance. Similarly, the Works cannot reasonably proceed to Workfront 4 (South) [i.e. fronting the Pallet Yard] until Workfront 3 is completed and re-opened to traffic.

And,

(b)If you should be experiencing any difficulty, in any way, consequent on these roadworks, you are cordially invited to directly contact my Site-based colleague, Aaron McMorrow, Site Engineer, contact details below.

Imminent Plans

[Subject to ESB Networks arriving on Site and carrying out essential cable relocation] The Contractor will now, over the coming weeks, complete the carriageway reconstruction, kerb laying, and footpath contraction fronting Park Crescent House.

Meanwhile, the construction of a new permanent stone-faced boundary wall fronting the Pallet Yard will commence next week, and continue to [same wall] completion by Christmas.

Contrary to as previously suggested, the Contractor has now decided to complete the south side of the road (i.e. up to and including the junction with Springfield Road), before commencing work on the north side of the road. Currently, when works commence on the north side of the road, it is intended to commence at the Cabra Gate end, and proceed eastwards, in section lengths similar to what has been done on the south side of the road.

Contractor’s Contact Details

The Contractor, Actavo, may be contacted …

Actavo (Ireland) Ltd., [formerly ‘SIERRA Communications Ltd.’]

Westland House,

Willow Road,

New Nangor Road,

Dublin 12.

Phone: +353 1 90 59 700

Email:

Web:

However, for day-to-day matters, please contactMr. Aaron McMorrow, Site Engineer, at either mobile phone number 086 048 70 69, or

If needed, you may also wish to contact Roads Construction Division (Ph. 01 222 30 66; e-mail: ), Environment and Transportation Department, Dublin City Council, or contact Mr. Padraig McNulty, Senior Resident Engineer, Roads Construction Division, DCC, at 086 8150 509 or e-mail .

Acknowledgement

Both Contractor, Actavo (Ireland) Ltd., and Employer, Dublin City Council:

(i)Recognise that roadworks, by their very nature, do cause some degree of inconvenience to both residents, locals, and other road users, and accordingly, both regrets and apologies for this, and will positively endeavour to do all things reasonable to minimise any such inconvenience,

and,

(ii)seeks, welcomes, and acknowledges, and appreciates in anticipation, the public’s understanding and cooperation during the course of these important, and essential, Road Improvement Works.

Yours faithfully,

______

Padraig Herlihy

Civils Manager, Actavo (Ireland) Ltd.

Blackhorse Avenue – Section 2 RISInterim PR Circular Letter #3

Page 1 of 3