PLAN CHECKLIST FOR PEDESTRIAN AND BICYCLE FACILITIES
Plans will be required for the construction of pedestrian and bicycle facilities and should consist of the following:
A. COVER SHEET
· Applicant or agency name.
· Description of activity.
· Location map.
· Index of sheet numbers which should include description of sheet including Georgia DOT standards.
· Name of consulting engineer or architect.
· Length of project.
· Disclaimer notes (if required).
· Note requiring project to be constructed as per current Georgia D.O.T. Standard Specifications as approved by the Federal Highway Administration.
· Scale (if required).
· North arrow.
· Georgia D.O.T. project number and project identification number.
· Date when plans completed.
· Revision dates (any revisions to plans after submission to Georgia D.O.T. for final review).
B. REVISION SUMMARY SHEEET
· Date of revision.
· Sheet number of revised sheet.
· Description of revision.
(Note: Only revisions to be noted on this sheet will be after submission to Georgia D.O.T. for final review.)
C. TYPICAL SECTIONS
· Lane widths.
· Asphalt paving and base thickness.
· Shoulder widths.
· Direction of cross slopes for paving, shoulders and sidewalk.
· Station application to each section.
D. SUMMARY SHEETS (Optional)
· Summary of all bid items required to construct facility.
E. DETAILED ESTIMATE
· Bid item number.*
· Description of item.*
· General notes (if required).*
*See Georgia D.O.T. Bid Item Index
F. PLAN SHEETS
· Pertinent topographic features.
· Centerline data.
· Lane widths.
· Stationing.
· Drainage structures (if required).
· Required right of way and/or easements.
G. PROFILE SHEETS
· Existing ground profile.
· Proposed grades (P.V.C station, P.V.I. station, P.V.T. station and length of vertical curve).
H. GEORGIA D.O.T. STANDARDS AND CONSTRUCTION DETAILS
I. EROSION CONTROL PLAN
· An Erosion Control,, Sedimentation, and Pollution Control Plan and comprehensive monitoring program will be required for projects having a disturbed area of 5 or more acres. Contact the GDOT District Office for the latest equipments.